Project Matador

Amarillo, Carson County, Texas

Under constructionContestedAI confirmedRecord updated August 26, 2026

Project Matador is a data center under construction in Amarillo, Texas (Carson County), operated by Fermi America. The public record puts it at announced 2025, 5,769 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Fermi America
Facility type
Data center, AI use confirmed
Location
Amarillo, Carson County, TX
Coordinates
35.3960, -101.5430
Power capacity
Not established from a public source
Land
5,769 acres
Investment
Not established from a public source
Announced
2025
Utility
Xcel Energy (SPS)
Power source
Mixed
Cooling
Not established
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2025
    Proposed
    Fermi America founded January 2025 by Rick Perry, Toby Neugebauer, and Griffin Perry. Project Matador announced on ~5,769-acre site in Carson County under 99-year lease with Texas Tech University System, adjacent to DOE Pantex Plant. Source: Fortune
  2. 2025
    Under construction
    600MW+ natural gas turbines acquired across two deals (July 2025); COLA for four AP1000 reactors filed with NRC June 17 2025; NRC accepted COLA for review September 2025; TCEQ preliminary approval for first 6GW gas generation (November 2025); geotechnical work commenced on campus. Source: PR Newswire

Opposition and litigation at this site

Yes. Project Matador in Amarillo, Carson County, Texas is contested. Hearings, public comment, petitions, or organized opposition are on record. TCEQ air permit process (for 93 planned gas turbines) drew 279+ public comments, majority opposed.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

TCEQ air permit process (for 93 planned gas turbines) drew 279+ public comments, majority opposed. 63 contested case hearing requests filed before State Office of Administrative Hearings; 21 additional public meeting requests. Primary opposition group: Panhandle Taxpayers for Transparency. Key concerns: air quality (modeled 2,140 tpy CO and 1,591 tpy NOx), water demand, impacts on farmland and nearby cattle operations (Tyson Foods facility adjacent). Fermi bused in college students to a December 2025 public meeting, stoking further controversy.

Source: Sierra Club Texas

Power and water

Initial generation: on-site natural gas. Fermi acquired 600MW+ of gas turbines in two deals (July 2025): 478MW from Firebird LNG/Siemens Energy (six SGT800 turbines + heat recovery steam generators + one SST600 steam turbine) and 135MW from GE 6B Frame units acquired from a New Jersey facility. TCEQ issued preliminary approval for up to 6GW of combined-cycle gas (November 2025); air permit secured February 2026 after ~279 public comments. Long-term plan adds four Westinghouse AP1000 reactors (~4.4GW nuclear baseload; COLA filed June 17 2025, NRC accepted two of three parts for review September 2025, Part 3 deadline December 31 2026, first reactor targeted 2031, all four by 2038) plus solar and battery storage. Fermi is also evaluating SMRs (MOU with Doosan Enerbility). Entire campus is behind-the-meter, private grid, no public utility offtake.

No confirmed water use figures published. Community opposition raised concerns about Ogallala Aquifer impacts from combined cooling demand of gas plants and data centers. Arid Texas Panhandle location heightens water supply risk.

People and entities in the record

  • Rick Perry · founder via Fermi America

    Co-founder and director of Fermi America, developer of this campus, holding 2.5% of common stock after the October 2025 IPO. Former Texas governor (2000-2015) and U.S. Energy Secretary (2017-2019).

    Source
  • Griffin Perry · founder via Fermi America

    Co-founder of Fermi America, developer of this campus, holding 19.4% of common stock after the October 2025 IPO, the second-largest individual holding.

    Source
  • Toby Neugebauer · founder via Fermi America

    Co-founder and former CEO of Fermi America, developer of this campus. As of June 2026 he was soliciting shareholder consents to call a special meeting, which the company publicly opposed.

    Source

Notes on the record

11GW is the long-term ceiling for the HyperGrid campus; near-term company targets include 1GW by end of 2026 and 2.3GW first-phase delivery, these are company goals, not firm commitments. Land acreage reported variously (5,769 acres per DCD July 2025 and 5,855 acres per other sources; later company materials cite 7,570 acres on 7,570 acres); using 5,769 as the earliest confirmed figure, sourced from the gas turbine acquisition announcement. Coordinates approximate (seed-provided; site in Carson County ~12 miles NE of Amarillo, adjacent to DOE Pantex Plant). Fermi America co-founded January 2025 by former Texas Governor and U.S. Energy Secretary Rick Perry, Toby Neugebauer (CEO, departed April 2026 after being fired 'without cause'), and Griffin Perry. IPO raised $682M on Nasdaq under ticker FRMI (October 2025), valuing company at ~$19B at opening; market cap collapsed to ~$3.4B by April 2026 after leadership exits and loss of anchor tenant ($150M LOI canceled December 2025). Company organized as a REIT; had zero revenue at IPO. Investment: equipment financing commitments exceed $600M ($500M MUFG turbine warehouse + $200M Keystone/Cape facility); projected total project cost $70 to 90B is a range/projection, not a firm figure, omitted from investmentUsd per data-rigor policy. Jobs: 50,000+ projected across campus lifetime, projection only, omitted from jobs field. Nuclear campus name in NRC COLA filings: 'President Donald J. Trump Advanced Energy and Intelligence Campus'; publicly marketed as Project Matador / HyperGrid.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Project Matador data center in Amarillo?

Yes. Project Matador in Amarillo, Carson County, Texas is contested. Hearings, public comment, petitions, or organized opposition are on record. TCEQ air permit process (for 93 planned gas turbines) drew 279+ public comments, majority opposed.

Has anyone filed a lawsuit over the Project Matador data center?

The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.

How much water does Project Matador use?

No water withdrawal figure for Project Matador is on record here. Cooling is recorded as unknown, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Project Matador, and how big is it?

Fermi America is the operator on record. No capacity figure is on record for this site. The site is recorded at 5769 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Project Matador," updated August 26, 2026, https://suedatacenters.org/data-centers/fermi-matador-amarillo-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/fermi-matador-amarillo-tx, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Fermi America acquires 600MW of gas turbines for 11GW AI mega campus in Amarillo, Texas · Data Center Dynamics · retrieved July 7, 2026
  2. 2.Fermi America Makes Initial Draw on $200M Equipment Facility to Accelerate 2.3GW Delivery · PR Newswire · retrieved July 7, 2026
  3. 3.Fermi America and State of Texas Announce TCEQ Preliminary Approval for First 6GW Natural Gas Facilities · PR Newswire · retrieved July 7, 2026
  4. 4.Fermi America Project Matador AP1000 Units 1-4 Combined License Application · U.S. Nuclear Regulatory Commission · retrieved July 7, 2026
  5. 5.Fermi America looks to go public as NRC accepts COLA for AP1000s · ANS Nuclear Newswire · retrieved July 7, 2026
  6. 6.Project Matador: Massive AI Data Center in Texas Panhandle Promises Pollution · Sierra Club Texas · retrieved July 7, 2026
  7. 7.Rick Perry's AI power startup Fermi already has a $16 billion market cap-and zero revenue · Fortune · retrieved July 7, 2026
  8. 8.Financially struggling, AI power startup Fermi loses its CEO and CFO for '2.0' reset · Fortune · retrieved July 7, 2026
  9. 9.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
  10. 10.Fermi Inc. IPO prospectus (Form 424B4), beneficial ownership table · U.S. Securities and Exchange Commission · retrieved August 26, 2026
  11. 11.Fermi Inc. proxy solicitation materials (DEFA14A), June 2026 · U.S. Securities and Exchange Commission · retrieved August 26, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us