Riot Platforms Corsicana Facility
Corsicana, Navarro County, Texas · All 4 Riot Platforms sites
Riot Platforms Corsicana Facility is an operating crypto mining site in Corsicana, Texas (Navarro County), operated by Riot Platforms. The public record puts it at announced January 2025, 1 GW planned, 858 acres, a reported $640 million investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Riot Platforms
- Facility type
- Crypto mining, AI use likely
- Location
- Corsicana, Navarro County, TX
- Coordinates
- 32.0900, -96.4700
- Power capacity
- 400 MW operating; 1 GW planned
- Land
- 858 acres
- Investment
- $640 million
- Announced
- January 2025
- Utility
- ERCOT grid with demand response participation
- Power source
- Grid
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- 140 permanent
- Public subsidy
- Chapter 312 property-tax abatement, Reinvestment Zone 24-102 (10-year term from tax year 2025), Navarro County, TX, 2024
- Community reception
- Contested
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- January 2025ProposedRiot halts 600 MW Phase II Bitcoin mining expansion and formally launches AI/HPC feasibility evaluation for remaining power capacity. Source: Riot Platforms
- April 2024Operating400 MW Phase I enters operation for Bitcoin mining using immersion-cooling. Source: Data Center Dynamics
Opposition and litigation at this site
Yes. Riot Platforms Corsicana Facility in Corsicana, Navarro County, Texas is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Organized local opposition (Concerned Citizens of Navarro County; Change.org petition).
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Organized local opposition (Concerned Citizens of Navarro County; Change.org petition). County commissioners declined an earlier, larger reinvestment-zone request in March 2024 after resident pushback; a smaller Chapter 312 abatement passed on a 3-2 vote in October 2024. Cited concerns: noise, peak water use, ERCOT grid strain, and limited permanent jobs relative to power draw.
Power and water
ERCOT-connected; net power cost ~3.2 cents/kWh via demand response and grid participation. MOU with Terrestrial Energy to co-locate molten salt reactors (IMSR) for eventual nuclear-powered AI capacity.
Immersion cooling for the operational 400 MW Bitcoin-mining phase; cooling for the future AI/HPC phase is not yet confirmed. The facility is projected to consume up to 1.5 million gallons of water per day at peak summer demand under a city-water agreement, a seasonal peak, not an average daily rate.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Chapter 312 property-tax abatement, Reinvestment Zone 24-102 (10-year term from tax year 2025) | Not established | Navarro County, TX | 2024 |
Notes on the record
Phase I (400 MW) operational for Bitcoin mining with immersion cooling. AMD contracted 50 MW for HPC workloads. Riot developing 112 MW Core and Shell infrastructure at Corsicana for future hyperscale AI tenants. Campus acquired in phases to 858 total acres. ERCOT-approved for 1 GW total. Navarro County's October 2024 abatement records cite a considered $640M investment and 140 new jobs; the signed agreement sets a $380M minimum taxable value and 140 FTE by January 1, 2026 (a Riot spokesperson separately cited 180 jobs). Re-tagged from data_center to crypto_mining (2026-07-10): the operational 400 MW is Bitcoin mining (current majority use); the 600 MW AI/HPC evaluation remains at proposal stage, not built. Riot does not disclose hash rate per-site (only company-wide EH/s spanning Corsicana + Rockdale + Kentucky), so hashRateThPerS is left unknown here rather than misattributing a company total. Miners are MicroBT ASICs designed for immersion cooling. ERCOT demand-response/curtailment participation (Four Coincident Peaks program) is a structural, revenue-generating part of Riot's operating model company-wide (~$21M in Q1 2026 curtailment credits), so power arrangement is tagged "mixed" rather than plain grid.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Nexus Hubbard Data Center & Power Campus · Hubbard · Nexus Data Centers26 mi · Under construction · 612 MW · Contested
Questions people ask about this site
Is there opposition to the Riot Platforms Corsicana Facility in Corsicana?
Yes. Riot Platforms Corsicana Facility in Corsicana, Navarro County, Texas is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Organized local opposition (Concerned Citizens of Navarro County; Change.org petition).
Has anyone filed a lawsuit over the Riot Platforms Corsicana Facility?
No lawsuit over Riot Platforms Corsicana Facility appears in the record we track as of July 6, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Riot Platforms Corsicana Facility use?
No water withdrawal figure for Riot Platforms Corsicana Facility is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Riot Platforms Corsicana Facility, and how big is it?
Riot Platforms is the operator on record. We hold 4 sites for that company across the registry. Capacity on record is 1 GW. The site is recorded at 858 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Riot Platforms Corsicana Facility," updated July 6, 2026, https://suedatacenters.org/data-centers/riot-platforms-corsicana-tx.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/riot-platforms-corsicana-tx, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Riot launches formal AI/HPC evaluation for 600 MW Corsicana capacity · Riot Platforms · retrieved July 6, 2026
- 2.Riot Platforms acquires additional 238 acres at Corsicana campus · Data Center Dynamics · retrieved July 6, 2026
- 3.Navarro County Resolution 2024.13, Tax Abatement Agreement with Riot Corsicana LLC (approved Oct 15, 2024) · Navarro County, TX · retrieved July 6, 2026
- 4.Bitcoin miner's $640m megadeal stumbles as Texans sour on industry's promise of jobs and growth · DL News · retrieved July 6, 2026
- 5.Riot Purchases 7.6 EH/s of Next Generation Miners From MicroBT · Riot Platforms · retrieved July 10, 2026
- 6.Riot Platforms 10-K FY2024 · SEC EDGAR · retrieved July 10, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us