DeepGreen Western Passage Tidal-Powered Subsea Data Center (Kendall Head, Eastport) is a proposed data center in Eastport, Maine (Washington County), operated by DeepGreen Western Passage SPV LLC. The public record puts it at announced February 11, 2026, 15 MW planned, a reported $100 million investment. It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- DeepGreen Western Passage SPV LLC
- Facility type
- Data center
- Location
- Eastport, Washington County, ME
- Coordinates
- 44.9345, -67.0114 (approximate)
- Power capacity
- 15 MW planned
- Land
- Not established from a public source
- Investment
- $100 million
- Announced
- February 11, 2026
- Utility
- Not established from a public source
- Power source
- Other
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- February 11, 2026ProposedStatus change recorded. Source: Bangor Daily News
Opposition and litigation at this site
Yes. Organized local opposition to DeepGreen Western Passage Tidal-Powered Subsea Data Center (Kendall Head, Eastport) in Eastport, Washington County, Maine is documented in the public record. The Eastport City Council unanimously enacted a 180-day data center moratorium, and the Port Authority board expressed opposition.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
The Eastport City Council unanimously enacted a 180-day data center moratorium, and the Port Authority board expressed opposition. Passamaquoddy officials and the residents' group Eastport Residents for Healthy Oceans oppose the project. Two citizen-initiated petitions were filed (BDN, 2026-08-24).
Power and water
Proposed in-stream tidal turbines in the Western Passage would power subsea AI server pods. A 1.5-mile subsea cable would connect to an onshore facility on Kendall Head (Boston Globe). The original February 2026 filing described a 51 MW tidal energy and subsea data center. The filing FERC accepted in August 2026 lowered output to a maximum of 15 MW.
Notes on the record
DeepGreen Western Passage SPV LLC (Needham, MA; managing member Louis Wolfson) filed for a 48-month FERC preliminary permit on Feb. 11, 2026. The permit is for feasibility and environmental studies only. FERC found the application deficient in July 2026 and accepted the revised filing in August 2026. Acceptance is not a construction permit; public comments were due Oct. 19, 2026. The investment was $415M in the February filing and $100M in the accepted filing, which also lists a 27-acre footprint in the bay. The pin is the OSM node for Kendall Head (node/358221168), the planned onshore landing, so precision is approximate. The developer has said feasibility is not yet determined.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Questions people ask about this site
Is there opposition to the DeepGreen Western Passage Tidal-Powered Subsea Data Center (Kendall Head, Eastport) in Eastport?
Yes. Organized local opposition to DeepGreen Western Passage Tidal-Powered Subsea Data Center (Kendall Head, Eastport) in Eastport, Washington County, Maine is documented in the public record. The Eastport City Council unanimously enacted a 180-day data center moratorium, and the Port Authority board expressed opposition.
Has anyone filed a lawsuit over the DeepGreen Western Passage Tidal-Powered Subsea Data Center (Kendall Head, Eastport)?
The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.
How much water does DeepGreen Western Passage Tidal-Powered Subsea Data Center (Kendall Head, Eastport) use?
No water withdrawal figure for DeepGreen Western Passage Tidal-Powered Subsea Data Center (Kendall Head, Eastport) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates DeepGreen Western Passage Tidal-Powered Subsea Data Center (Kendall Head, Eastport), and how big is it?
DeepGreen Western Passage SPV LLC is the operator on record. Capacity on record is 15 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "DeepGreen Western Passage Tidal-Powered Subsea Data Center (Kendall Head, Eastport)," updated October 22, 2026, https://suedatacenters.org/data-centers/deepgreen-western-passage-eastport-me.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/deepgreen-western-passage-eastport-me, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Developer eyes Down East Maine as home for proposed underwater AI data center · Bangor Daily News · retrieved October 22, 2026
- 2.FERC accepts DeepGreen preliminary permit filing for Eastport underwater data center · Bangor Daily News · retrieved October 22, 2026
- 3.A data center. Underwater. Yes, some in this small Maine town are worried. · The Boston Globe · retrieved October 22, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys