Data Center Registry
Mid-County Industrial Park Data Center Campus
Prince William County County, Virginia
Mid-County Industrial Park Data Center Campus is a permitted data center in Virginia (Prince William County County), operated by Minnieville Capital Acquisitions. The public record puts it at 64 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- Minnieville Capital Acquisitions
- Facility type
- Data center
- Location
- Prince William County County, VA
- Coordinates
- 38.6321, -77.4219 (approximate)
- Power capacity
- Not established from a public source
- Land
- 64 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Contested
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 4, 2024PermittedBoard of County Supervisors approved 5-3: about 40 acres rezoned from agricultural to industrial plus ~20 acres in Colchester Industrial Park. Source: InsideNoVa
Opposition and litigation at this site
Yes. Mid-County Industrial Park Data Center Campus in Prince William County County, Virginia is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. The Planning Commission unanimously recommended denial.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
The Planning Commission unanimously recommended denial. The site borders the Potomac Reserve community, and the board approved 5-3.
Notes on the record
Three data center buildings and an electric substation, about 250 feet northwest of the Dumfries Road (Route 234) and Minnieville Road intersection, with buildings nearest Route 234 capped at 75 feet. Press has linked a Minnieville-tied buyer to an Amazon P.O. box, but end-user identity is not confirmed. The coordinates are an approximate point on Dumfries Road at Independent Hill, not the parcel.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Our reporting on this site
- The Prince William Digital Gateway Lawsuit · Plaintiff win
- Great Oak v. the Hum · Dispute, no suit filed
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- CloudHQ Manassas MCC Campus · Manassas · CloudHQ7 mi · Under construction · 382 MW · Mixed reception
- Aurora AI Factory · Manassas · Digital Realty9 mi · Under construction · 96 MW
- Yondr Manassas Data Center Campus · Manassas · Yondr Group / Cerberus Capital Management9 mi · Proposed · 72 MW
- Wellington Road Data Center Campus (Sharpless) · Bristow · Sharpless Enterprises LLC10 mi · Permitted
- Amazon Devlin Technology Park · Bristow · Amazon Web Services10 mi · Permitted · Contested
- Microsoft Bristow Data Center Campus (MNZ03) · Bristow · Microsoft10 mi · Operating · Mixed reception
- Iron Mountain VA-6 · Manassas · Iron Mountain11 mi · Operating · 32 MW
- Iron Mountain VA-4 · Manassas · Iron Mountain12 mi · Operating · 32 MW
Questions people ask about this site
Is there opposition to the Mid-County Industrial Park Data Center Campus in Prince William County County, Virginia?
Yes. Mid-County Industrial Park Data Center Campus in Prince William County County, Virginia is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. The Planning Commission unanimously recommended denial.
Has anyone filed a lawsuit over the Mid-County Industrial Park Data Center Campus?
No lawsuit over Mid-County Industrial Park Data Center Campus appears in the record we track as of October 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Mid-County Industrial Park Data Center Campus use?
No water withdrawal figure for Mid-County Industrial Park Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Mid-County Industrial Park Data Center Campus, and how big is it?
Minnieville Capital Acquisitions is the operator on record. No capacity figure is on record for this site. The site is recorded at 64 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Mid-County Industrial Park Data Center Campus," updated October 14, 2026, https://suedatacenters.org/data-centers/minnieville-mid-county-industrial-park-prince-william-va.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/minnieville-mid-county-industrial-park-prince-william-va, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Prince William supervisors approve contentious Mid-County Industrial Park data center project · InsideNoVa · retrieved October 14, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us