Wixom Road Data Center Campus

Wixom, Oakland County, Michigan

ProposedOpposedRecord updated September 9, 2026

Wixom Road Data Center Campus is a proposed data center in Wixom, Michigan (Oakland County), operated by Wixom Industrial One / Sansone Group. The public record puts it at 55 acres. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Wixom Industrial One / Sansone Group
Facility type
Data center
Location
30625 S. Wixom Road, Wixom, Oakland County, MI
Coordinates
42.5184, -83.5375 (approximate)
Power capacity
Not established from a public source
Land
55 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 2026
    Proposed
    City council unanimously voted down the developer's application to lift the moratorium early; a separate ordinance setting future data-center rules was postponed. Source: Civic Media
  2. March 2026
    Proposed
    Wixom enacted a six-month data-center moratorium running through August 2026. Source: Detroit Free Press (via Yahoo News)

Opposition and litigation at this site

Yes. Organized local opposition to Wixom Road Data Center Campus in Wixom, Oakland County, Michigan is documented in the public record, without a lawsuit on file in the sources we track. City council unanimously rejected the developer's request to lift a data-center moratorium early, calling it 'unreasonable as it relates to the potential health, safety, and welfare impacts in the city.' The source reports that during roughly 90 minutes of public comment no speaker expressed support, with concerns centred on proximity to schools, day cares and homes.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

City council unanimously rejected the developer's request to lift a data-center moratorium early, calling it 'unreasonable as it relates to the potential health, safety, and welfare impacts in the city.' The source reports that during roughly 90 minutes of public comment no speaker expressed support, with concerns centred on proximity to schools, day cares and homes. Developer Dennis Griffin said data centers were being treated 'very, very unfairly.'

Source: Detroit Free Press (via Yahoo News)

Notes on the record

Three-building complex, each building stated at more than 200,000 sq ft for a total of more than 519,000 sq ft, on vacant light-industrial land. Status is 'proposed' and remains blocked by the municipal moratorium, no site-plan or rezoning approval is recorded. Capacity: NO megawatt figure is stated in either source; capacityMw is therefore omitted rather than inferred from square footage. Water use is not quantified in the sources. Investment figure not stated. The source notes the site sits near a DTE Energy transmission line with natural gas service available, but no interconnection or generation arrangement is described, so energy is left unset. Coordinates from the US Census geocoder for the street address named in the source; parcel boundary not confirmed.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Wixom Road Data Center Campus in Wixom?

Yes. Organized local opposition to Wixom Road Data Center Campus in Wixom, Oakland County, Michigan is documented in the public record, without a lawsuit on file in the sources we track. City council unanimously rejected the developer's request to lift a data-center moratorium early, calling it 'unreasonable as it relates to the potential health, safety, and welfare impacts in the city.' The source reports that during roughly 90 minutes of public comment no speaker expressed support, with concerns centred on proximity to schools, day cares and homes.

Has anyone filed a lawsuit over the Wixom Road Data Center Campus?

No lawsuit over Wixom Road Data Center Campus appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Wixom Road Data Center Campus use?

No water withdrawal figure for Wixom Road Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Wixom Road Data Center Campus, and how big is it?

Wixom Industrial One / Sansone Group is the operator on record. No capacity figure is on record for this site. The site is recorded at 55 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Wixom Road Data Center Campus," updated September 9, 2026, https://suedatacenters.org/data-centers/sansone-wixom-road-mi.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/sansone-wixom-road-mi, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Michigan officials keep data center moratorium, call developer's request unreasonable · Detroit Free Press (via Yahoo News) · retrieved September 9, 2026
  2. 2.Michigan Data Centers: The Weekly Download · Civic Media · retrieved September 9, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us