Project Cannoli
Van Buren Township, Wayne County, Michigan · All 61 Google sites · Every Google case on our tracker
Project Cannoli is a data center under construction in Van Buren Township, Michigan (Wayne County), operated by Google. The public record puts it at 1 GW planned, 282 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Facility type
- Data center, AI use likely
- Location
- Van Buren Township, Wayne County, MI
- Coordinates
- 42.2300, -83.4400 (approximate)
- Power capacity
- 1 GW planned
- Land
- 282 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- DTE Energy
- Power source
- Mixed
- Cooling
- Not established
- Water use
- Not established from a public source
- Jobs
- 51 permanent
- Public subsidy
- Local tax abatement approved by Van Buren Township, $125 million, Charter Township of Van Buren, Michigan, 2026 | Wayne County tax exemption (County Commission overrode the executive's veto), $125 million, Wayne County, MI, 2026
- Community reception
- Contested
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- October 24, 2026Under constructionThe Van Buren Township Planning Commission approved the final site plan 5-1 on Oct. 14, 2026. Early construction is underway: residents have reported crews and dust since August, and phased underground utility work runs through early 2027. Google expects to draw power by late 2027. Source: Planet Detroit
Opposition and litigation at this site
Yes. Project Cannoli in Van Buren Township, Wayne County, Michigan is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. The planning commission voted 5-2 in February 2026 to grant preliminary site plan approval for the data center and approved the final site plan 5-1 on October 14, 2026.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
The planning commission voted 5-2 in February 2026 to grant preliminary site plan approval for the data center and approved the final site plan 5-1 on October 14, 2026. As of February 2026, Planet Detroit reported that 1,400 people had signed a petition opposing the project; as of October 2026, Gander Newsroom reports that more than 2,700 residents have signed a petition against it.
Power and water
~1GW need per a DTE utility deal (450MW storage + 1.6GW renewables). $125M in local tax reduction in exchange for $15.4M developer-funded infrastructure + 51 jobs.
Planet Detroit (February 2026), citing the township's frequently asked questions, reports around 2 million to 3.6 million gallons of water a day; Bridge Michigan (via The Manchester Mirror) reports the facility will draw up to 3.6 million gallons per day from the Great Lakes Water Authority. These are projected maximums, not reported actual use, so no water-use figure is recorded.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Local tax abatement approved by Van Buren Township | $125 million | Charter Township of Van Buren, Michigan | 2026 |
| Wayne County tax exemption (County Commission overrode the executive's veto) | $125 million | Wayne County, MI | 2026 |
Notes on the record
Google confirmed evaluating the site. Coordinates are approximate. Developer: Panattoni Development Co. The township planning commission granted preliminary site plan approval in February 2026 and approved the final site plan 5-1 on October 14, 2026. As of October 2026, early construction was reported underway, and Google expects the facility to begin drawing power by late 2027. The record is listed as under construction.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- U-M / Los Alamos Research Computing Center · Ypsilanti · University of Michigan (with Los Alamos National Laboratory)6 mi · Proposed · Opposed
- Otava Metro Detroit Data Center · Westland · Otava7 mi · Operating · 1.2 MW
- Klever Technology Center Data Center Proposal (27181 Southern Street, Inkster) · Inkster · Klever Technology Center LLC8 mi · Cancelled · Opposed
- Allen Park Data Center · Allen Park · Solstice Data13 mi · Cancelled · 26 MW · Opposed
- Thor Equities Augusta Township Data Center (Form8tion) · Augusta Township · Thor Equities15 mi · Cancelled · Opposed
- Gibraltar Data Center (former McLouth Steel site) · Gibraltar · Raeden (with Cal Realty / Ferragon Corp.)15 mi · Proposed · 100 MW · In litigation
- York Township Data Center (Platt Road / former Toyota land) · York Township · Sansone Group16 mi · Cancelled
- Otava Ann Arbor Data Center · Ann Arbor · Otava16 mi · Operating
Questions people ask about this site
Is there opposition to the Project Cannoli data center in Van Buren Township?
Yes. Project Cannoli in Van Buren Township, Wayne County, Michigan is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. The planning commission voted 5-2 in February 2026 to grant preliminary site plan approval for the data center and approved the final site plan 5-1 on October 14, 2026.
Has anyone filed a lawsuit over the Project Cannoli data center?
No lawsuit over Project Cannoli appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Project Cannoli use?
No water withdrawal figure for Project Cannoli is on record here. Cooling is recorded as unknown, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Project Cannoli, and how big is it?
Google is the operator on record. We hold 61 sites for that company across the registry. Capacity on record is 1 GW. The site is recorded at 282 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Cannoli," updated October 28, 2026, https://suedatacenters.org/data-centers/project-cannoli-van-buren-township-wayne-county-mi.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/project-cannoli-van-buren-township-wayne-county-mi, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Van Buren Township OKs Google data center substation · Planet Detroit · retrieved July 9, 2026
- 2.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
- 3.Van Buren Township, Data Center FAQ · Charter Township of Van Buren, Michigan · retrieved September 9, 2026
- 4.Van Buren Township officials to consider final site plan for Google data center · Detroit Free Press via Yahoo News · retrieved September 14, 2026
- 5.Google, DTE Van Buren data center contracts: 20-year special contracts before the MPSC, decision requested by September 10, 2026 · Planet Detroit · retrieved September 14, 2026
- 6.Van Buren Township, Data Center Project page (1.0 GW maximum facility load; load begins Dec 2027, maximum Dec 2028; development agreement May 20, 2026) · Van Buren Charter Township · retrieved September 21, 2026
- 7.Planet Detroit, Van Buren Township advances 1 GW 'Project Cannoli' (282 acres, 800,000 sq ft, 2 to 3.6M gallons/day, two air-cooled and one water-cooled building, 156 diesel backup generators) · Planet Detroit · retrieved September 21, 2026
- 8.Planet Detroit, Google, DTE plan 1 gigawatt Michigan data center (2.7 GW new resources: 1.6 GW renewables, 450 MW storage; MPSC contested case filed 2026-03-17) · Planet Detroit · retrieved September 21, 2026
- 9.Michigan regulators OK DTE contracts for Google data center · Michigan Public · retrieved October 7, 2026
- 10.Michigan regulators OK DTE contracts for Google data center · Planet Detroit · retrieved October 24, 2026
- 11.How many AI data centers are planned in Michigan? We counted. · Gander Newsroom · retrieved October 7, 2026
- 12.Google data center secures Van Buren Township approval, with startup expected in late 2027 · Planet Detroit · retrieved October 24, 2026
- 13.Google data center secures Van Buren Township approval, with startup expected in late 2027 · Planet Detroit · retrieved October 24, 2026
- 14.Van Buren Township officials approve plans for controversial Google data center campus (construction already underway) · WXYZ Detroit · retrieved October 24, 2026
- 15.Township vote paves way for Michigan's second hyperscale data center · The Manchester Mirror (Bridge Michigan syndication) · retrieved October 24, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us