AVAIO Digital Leo Campus

Pulaski County, Arkansas · All 4 AVAIO Digital Partners sites

ProposedContestedAI confirmedRecord updated October 28, 2026

AVAIO Digital Leo Campus is a proposed data center in Arkansas (Pulaski County), operated by AVAIO Digital Partners. The public record puts it at announced January 2026, 760 acres, a reported $6 billion investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
AVAIO Digital Partners
Facility type
Data center, AI use confirmed
Location
145th Street, Pulaski County, AR
Coordinates
34.6800, -92.2960 (approximate)
Power capacity
Not established from a public source
Land
760 acres
Investment
$6 billion
Announced
January 2026
Utility
Entergy Arkansas
Power source
Mixed
On site generation
500 MW
Cooling
Closed loop
Water use
Not established from a public source
Jobs
500 permanent
Public subsidy
State of Arkansas sales and use tax incentives for qualifying data center tenant capital expenditures, Arkansas
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. January 2026
    Proposed
    AVAIO Digital announces $6B+ AI-ready data center campus in Pulaski County; Governor Sanders describes it as largest economic investment in Arkansas history; construction targeted Q1 2026 start Source: Arkansas Economic Development Commission

Opposition and litigation at this site

Yes. AVAIO Digital Leo Campus in Pulaski County, Arkansas is contested. Hearings, public comment, petitions, or organized opposition are on record. Pulaski County adopted a one-year data-center moratorium (10 votes) in May 2026 but exempted AVAIO by a bare 8-vote majority, the minimum on the 15-member Quorum Court.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Pulaski County adopted a one-year data-center moratorium (10 votes) in May 2026 but exempted AVAIO by a bare 8-vote majority, the minimum on the 15-member Quorum Court. Residents opposed the project over water use and farmland; it is backed by state and county leadership and the Little Rock Regional Chamber.

Source: UALR Public Radio

Power and water

150 MW contracted from Entergy Arkansas (grid supply; energized Q2 2027 per the January 2026 announcement, Q4 2027 per AVAIO's development page as of October 2026); additional substantial on-site natural gas infrastructure planned (the January 2026 announcement gives no capacity; as of October 2026, AVAIO's development page lists "500 MW Total Baseload BTM" without naming the fuel); up to 1 GW anticipated total demand as facility grows. Rainwater capture, rooftop solar, and advanced cooling economization also planned.

AVAIO's project manager testified to the Pulaski County Quorum Court that the campus would demand about 200,000 gallons of water per day on average during warmer months, dropping to near zero in winter; as of July 6, 2026, the specific cooling technology had not been disclosed. At a community meeting in Wrightsville on July 13, 2026, AVAIO said it planned a closed-loop cooling system that recirculates water and would consume 8,000 gallons a day of potable water from Central Arkansas Water, with 4,000 gallons a day discharged into the 145th Street Sewer District (Arkansas Times). Both figures are company projections; the campus is not yet operating.

Public money on the record

ProgramAmountGranted byYear
State of Arkansas sales and use tax incentives for qualifying data center tenant capital expendituresNot establishedArkansas

Notes on the record

Location: off Interstate 530 near 145th Street, Pulaski County; coordinates are approximate for the I-530 corridor south of Little Rock. Named after the Leo constellation. Initial $6B investment may grow to $21B through full build-out. First phase completion targeted June 2027. Campus sits near long-haul fiber routes connecting Dallas, Atlanta, and Memphis. A Q1 2026 construction start was planned as of announcement. As of October 2026, AVAIO's development page says AVAIO "has broken ground" on the campus, while at a July 13, 2026 community meeting AVAIO's project manager said construction was expected to begin in early 2027, with the permits needed to start earthworks in hand (Arkansas Times); the record is listed as proposed. The 760-acre land area is the site size given in the January 2026 announcement and the July 2026 Arkansas Times account; as of October 2026, AVAIO's development page describes a 296-acre project located about 7.7 km from the map pin, which stays approximate. The January 2026 announcement says AVAIO anticipates power demand of up to 1 GW as the facility grows; that is a ceiling on power demand, not IT capacity, so no planned capacity is recorded. The energy source is mixed rather than on-site gas. The 150 MW figure is the Entergy Arkansas grid supply contract, not on-site generation, and as of July 2026 on-site gas capacity was unquantified in sources. The recorded 500 MW of on-site generation is from AVAIO's development page for the campus, which lists "500 MW Total Baseload BTM" (behind the meter) alongside "570 MW Total Grid Power" and "1,070 MW Total Baseload Power"; as of October 2026, the page does not name the fuel for the behind-the-meter capacity. Arkansas's data-center sales-and-use tax exemption (Act 819 of 2023, expanded by Act 548 of 2025) likely applies given the investment scale. AVAIO's development page states that "the State of Arkansas offers substantial Sales and Use Tax incentives for data center tenants, reducing total cost of ownership on qualifying capital expenditures", but as of October 2026 names no award or amount; as of July 2026 no AVAIO-specific incentive award had been published.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near AVAIO Digital Leo Campus?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the AVAIO Digital Leo Campus in Pulaski County, Arkansas?

Yes. AVAIO Digital Leo Campus in Pulaski County, Arkansas is contested. Hearings, public comment, petitions, or organized opposition are on record. Pulaski County adopted a one-year data-center moratorium (10 votes) in May 2026 but exempted AVAIO by a bare 8-vote majority, the minimum on the 15-member Quorum Court.

Has anyone filed a lawsuit over the AVAIO Digital Leo Campus?

The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.

How much water does AVAIO Digital Leo Campus use?

No water withdrawal figure for AVAIO Digital Leo Campus is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates AVAIO Digital Leo Campus, and how big is it?

AVAIO Digital Partners is the operator on record. We hold 4 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 760 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "AVAIO Digital Leo Campus," updated October 28, 2026, https://suedatacenters.org/data-centers/avaio-digital-leo-little-rock-ar.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/avaio-digital-leo-little-rock-ar, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.AVAIO Digital Announces New Large-Scale AI-Ready Data Center and Power Campus in Little Rock, Arkansas · Arkansas Economic Development Commission · retrieved July 6, 2026
  2. 2.AVAIO Digital Announces New Large-Scale AI-Ready Data Center and Power Campus in Little Rock, Arkansas · PR Newswire · retrieved July 6, 2026 · original offline, archived copy from October 1, 2026
  3. 3.Arkansas's most populous county approves data-center moratorium, but with an AVAIO exemption · UALR Public Radio · retrieved July 6, 2026
  4. 4.Entergy re-submits AVAIO power agreement to Arkansas Public Service Commission · Arkansas Democrat-Gazette · retrieved September 15, 2026
  5. 5.Giga-what?! AVAIO comes clean about big plans in Wrightsville · Arkansas Times · retrieved September 15, 2026
  6. 6.Little Rock, Arkansas Campus, AVAIO Digital development page · AVAIO Digital Partners · retrieved October 18, 2026
  7. 7.$26B in Data-Center Builds Move Forward in Arkansas, Mississippi · Engineering News-Record · retrieved September 29, 2026
  8. 8.AVAIO finally faced the Wrightsville community over its $6 billion data center · Arkansas Times · retrieved October 18, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us