AVAIO Digital Leo Campus

Pulaski County, Arkansas · All 4 AVAIO Digital Partners sites

ProposedContestedAI confirmedRecord updated July 6, 2026

AVAIO Digital Leo Campus is a proposed data center in Arkansas (Pulaski County), operated by AVAIO Digital Partners. The public record puts it at announced January 2026, 1 GW planned, 760 acres, a reported $6 billion investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
AVAIO Digital Partners
Facility type
Data center, AI use confirmed
Location
Pulaski County, AR
Coordinates
34.6800, -92.2960
Power capacity
1 GW planned
Land
760 acres
Investment
$6 billion
Announced
January 2026
Utility
Entergy Arkansas
Power source
Mixed
Cooling
Not established
Water use
Not established from a public source
Jobs
500 permanent
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. January 2026
    Proposed
    AVAIO Digital announces $6B+ AI-ready data center campus in Pulaski County; Governor Sanders describes it as largest economic investment in Arkansas history; construction targeted Q1 2026 start Source: Arkansas Economic Development Commission

Opposition and litigation at this site

Yes. AVAIO Digital Leo Campus in Pulaski County, Arkansas is contested. Hearings, public comment, petitions, or organized opposition are on record. Pulaski County adopted a one-year data-center moratorium (10 votes) in May 2026 but exempted AVAIO by a bare 8-vote majority, the minimum on the 15-member Quorum Court.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Pulaski County adopted a one-year data-center moratorium (10 votes) in May 2026 but exempted AVAIO by a bare 8-vote majority, the minimum on the 15-member Quorum Court. Residents opposed the project over water use and farmland; it is backed by state and county leadership and the Little Rock Regional Chamber.

Source: UALR Public Radio

Power and water

150 MW contracted from Entergy Arkansas (grid supply, energized Q2 2027); additional substantial on-site natural gas infrastructure planned (capacity not specified in sources); up to 1 GW anticipated total demand as facility grows. Rainwater capture, rooftop solar, and advanced cooling economization also planned.

AVAIO's project manager testified to the Pulaski County Quorum Court that the campus would demand about 200,000 gallons of water per day on average during warmer months, dropping to near zero in winter; the specific cooling technology was not disclosed.

Notes on the record

Location: off Interstate 530 near 145th Street, Pulaski County; coordinates are approximate for the I-530 corridor south of Little Rock. Named after the Leo constellation. Initial $6B investment may grow to $21B through full build-out. First phase completion targeted June 2027. Campus sits near long-haul fiber routes connecting Dallas, Atlanta, and Memphis. Q1 2026 construction start was planned as of announcement; current construction status unconfirmed as of research date. Fix: energy.source corrected from 'on_site_gas' to 'mixed'; onSiteGenerationMw removed, the 150 MW figure is the Entergy Arkansas grid supply contract, not on-site generation; on-site gas capacity is unquantified in sources. Arkansas's data-center sales-and-use tax exemption (Act 819 of 2023, expanded by Act 548 of 2025) likely applies given the investment scale, but no AVAIO-specific incentive award has been published.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the AVAIO Digital Leo Campus in Pulaski County, Arkansas?

Yes. AVAIO Digital Leo Campus in Pulaski County, Arkansas is contested. Hearings, public comment, petitions, or organized opposition are on record. Pulaski County adopted a one-year data-center moratorium (10 votes) in May 2026 but exempted AVAIO by a bare 8-vote majority, the minimum on the 15-member Quorum Court.

Has anyone filed a lawsuit over the AVAIO Digital Leo Campus?

The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.

How much water does AVAIO Digital Leo Campus use?

No water withdrawal figure for AVAIO Digital Leo Campus is on record here. Cooling is recorded as unknown, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates AVAIO Digital Leo Campus, and how big is it?

AVAIO Digital Partners is the operator on record. We hold 4 sites for that company across the registry. Capacity on record is 1 GW. The site is recorded at 760 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "AVAIO Digital Leo Campus," updated July 6, 2026, https://suedatacenters.org/data-centers/avaio-digital-leo-little-rock-ar.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/avaio-digital-leo-little-rock-ar, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.AVAIO Digital Announces New Large-Scale AI-Ready Data Center and Power Campus in Little Rock, Arkansas · Arkansas Economic Development Commission · retrieved July 6, 2026
  2. 2.AVAIO Digital Announces New Large-Scale AI-Ready Data Center and Power Campus in Little Rock, Arkansas · PR Newswire · retrieved July 6, 2026
  3. 3.Arkansas's most populous county approves data-center moratorium, but with an AVAIO exemption · UALR Public Radio · retrieved July 6, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us