Cook Inlet Subsea-Compute & Infrastructure Hub is a proposed data center in Nikiski, Alaska (Kenai Peninsula Borough County), operated by DeepGreen Cook Inlet SPV LLC. The public record puts it at announced February 11, 2026, 100 MW planned, 1,650 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
DeepGreen Cook Inlet SPV LLC
Facility type
Data center
Location
Nikiski, Kenai Peninsula Borough County, AK
Coordinates
60.6903, -151.2889 (approximate)
Power capacity
100 MW planned
Land
1,650 acres
Investment
Not established from a public source
Announced
February 11, 2026
Utility
Not established from a public source
Power source
Other
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. February 11, 2026
    Proposed
    FERC preliminary permit application filed (P-15423-000), supplemented 2026-06-26 and accepted in September 2026. A preliminary permit does not authorize construction. Source: Peninsula Clarion

Opposition and litigation at this site

Yes. Cook Inlet Subsea-Compute & Infrastructure Hub in Nikiski, Kenai Peninsula Borough County, Alaska is contested. Hearings, public comment, petitions, or organized opposition are on record. The Kenai Peninsula Borough, the Center for Biological Diversity and the Alaska Commercial Fisheries Conservation Alliance moved to intervene at FERC, and most of the roughly 40 public comments filed oppose the project.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

The Kenai Peninsula Borough, the Center for Biological Diversity and the Alaska Commercial Fisheries Conservation Alliance moved to intervene at FERC, and most of the roughly 40 public comments filed oppose the project. The Alaska Energy Authority also plans to intervene.

Source: Peninsula Clarion

Power and water

Proposed to be powered by roughly 330-350 marine hydrokinetic (tidal) turbines in Cook Inlet; the developer describes tying in with the Alaska Energy Authority's planned Cook Inlet PowerLink transmission line, but AEA says the company has not contacted it.

Underwater server 'hives' cooled by ambient seawater; the developer claims no freshwater use.

Notes on the record

The plan calls for 66 modular data-center pods in a 1,650-acre seabed envelope west of Nikiski (East Foreland corridor), 45-166 ft deep, with a 3.5-mile cable to a Nikiski landing. Only preliminary studies are proposed (about $4.5M over 4 years). The pin is the Nikiski hamlet; the site is offshore to the west.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Free case review

Living near Cook Inlet Subsea-Compute & Infrastructure Hub?

Tell us the basics and an independent attorney handling data center cases in your state will follow up. Free, and you are never obligated to hire anyone.

Questions people ask about this site

Is there opposition to the Cook Inlet Subsea-Compute & Infrastructure Hub data center in Nikiski?

Yes. Cook Inlet Subsea-Compute & Infrastructure Hub in Nikiski, Kenai Peninsula Borough County, Alaska is contested. Hearings, public comment, petitions, or organized opposition are on record. The Kenai Peninsula Borough, the Center for Biological Diversity and the Alaska Commercial Fisheries Conservation Alliance moved to intervene at FERC, and most of the roughly 40 public comments filed oppose the project.

Has anyone filed a lawsuit over the Cook Inlet Subsea-Compute & Infrastructure Hub data center?

The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.

How much water does Cook Inlet Subsea-Compute & Infrastructure Hub use?

No water withdrawal figure for Cook Inlet Subsea-Compute & Infrastructure Hub is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Cook Inlet Subsea-Compute & Infrastructure Hub, and how big is it?

DeepGreen Cook Inlet SPV LLC is the operator on record. Capacity on record is 100 MW. The site is recorded at 1650 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Cook Inlet Subsea-Compute & Infrastructure Hub," updated September 28, 2026, https://suedatacenters.org/data-centers/deepgreen-cook-inlet-nikiski-ak.

Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/deepgreen-cook-inlet-nikiski-ak, retrieved October 1, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Underwater data center proposed for Alaska's Cook Inlet by East Coast company · Anchorage Daily News · retrieved September 28, 2026
  2. 2.Federal review advances for subsea data center off Nikiski · Peninsula Clarion · retrieved September 28, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us