Stak Energy North Slope Data Center

North Slope County, Alaska

ProposedMixed receptionAI confirmedRecord updated October 18, 2026

Stak Energy North Slope Data Center is a proposed data center in Alaska (North Slope County), operated by Stak Energy. The public record puts it at announced May 2026, 3 GW planned, 715 acres, a reported $500 million investment. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Stak Energy
Facility type
Data center, AI use confirmed
Location
North Slope County, AK
Coordinates
69.8400, -148.5000
Power capacity
3 GW planned
Land
715 acres
Investment
$500 million
Announced
May 2026
Utility
Tdx North Slope Generating Co
Power source
On site gas
On site generation
3 GW
Cooling
air
Water use
Not established from a public source
Jobs
60 permanent; 1,500 construction
Public subsidy
Not established from a public source
Community reception
Mixed reception
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. May 2026
    Proposed
    Alaska DNR issued preliminary best-interest finding supporting long-term state land lease for 715.4 acres; public review process initiated Source: Alaska Public Media

Opposition and litigation at this site

Partly. Both documented support and documented opposition to Stak Energy North Slope Data Center in North Slope County, Alaska appear in the record, with no clear majority position. No confirmed customers or investors as of May 2026.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

No confirmed customers or investors as of May 2026. Turbine sourcing delays (industry backlog up to 7 years) cited as major risk. Alaska-native leadership including former state DNR commissioner John Boyle. Indigenous opposition reported.

Source: Alaska Public Media

Power and water

New pipeline to carry North Slope natural gas to on-site power plant. Self-contained, not connected to Alaska's statewide electrical grid.

Arctic air cooling reduces water consumption by 90%+ compared to industry norms per company. Sub-freezing average temperatures enable free air cooling.

Notes on the record

Preliminary state land lease approval covers 715.4 acres (corrected from 640; one square mile = 640 acres exactly but the approved lease footprint is 715.4 acres per Alaska Beacon). Campus is approximately 26 miles south of Deadhorse/Prudhoe Bay off the Dalton Highway (corrected from 25 miles). Supports AI training, cloud computing, and HPC. 3 GW is the project's claimed ultimate potential; $500M is Phase 1 capital. Coordinates estimated (~26 miles south of Prudhoe Bay 70.2N/148.5W); exact site not publicly disclosed.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Stak Energy North Slope Data Center?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Stak Energy North Slope Data Center in North Slope County, Alaska?

Partly. Both documented support and documented opposition to Stak Energy North Slope Data Center in North Slope County, Alaska appear in the record, with no clear majority position. No confirmed customers or investors as of May 2026.

Has anyone filed a lawsuit over the Stak Energy North Slope Data Center?

No lawsuit over Stak Energy North Slope Data Center appears in the record we track as of October 18, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Stak Energy North Slope Data Center use?

No water withdrawal figure for Stak Energy North Slope Data Center is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Stak Energy North Slope Data Center, and how big is it?

Stak Energy is the operator on record. Capacity on record is 3 GW. The site is recorded at 715 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Stak Energy North Slope Data Center," updated October 18, 2026, https://suedatacenters.org/data-centers/stak-energy-north-slope-ak.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/stak-energy-north-slope-ak, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Alaska's North Slope Proposed as Home for Massive AI Data Center · Alaska Public Media · retrieved July 6, 2026
  2. 2.A Huge Data Center Could Rise on Alaska's North Slope · Anchorage Daily News · retrieved July 6, 2026
  3. 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
  4. 4.STAK Energy Corporation ADL 422741 Preliminary Decision (Director's Decision, May 12, 2026) · Alaska Department of Natural Resources, Division of Oil and Gas · retrieved September 28, 2026
  5. 5.Data center in play · Petroleum News · retrieved October 18, 2026
  6. 6.STAK Energy Campus: What the State's Lease Documents Reveal About Scale, Risk, and Unanswered Questions · Northern Alaska Environmental Center · retrieved October 18, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us