Solis Arx Progress Park Data Center Campus

Max Meadows, Wythe County, Virginia

ProposedContestedAI confirmedRecord updated July 26, 2026

Solis Arx Progress Park Data Center Campus is a proposed data center in Max Meadows, Virginia (Wythe County), operated by Solis Arx. The public record puts it at announced December 5, 2025. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Solis Arx
Facility type
Data center, AI use confirmed
Location
Max Meadows, Wythe County, VA
Coordinates
36.9580, -80.8990 (approximate)
Power capacity
Not established from a public source
Land
Not established from a public source
Investment
Not established from a public source
Announced
December 5, 2025
Utility
Appalachian Power
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. December 5, 2025
    Proposed
    Wythe County and Solis Arx announced a data center / 'AI factory' campus on a 99-acre lot in Progress Park; Wythe County has no zoning, so no rezoning is required. Source: Cardinal News

Opposition and litigation at this site

Yes. Solis Arx Progress Park Data Center Campus in Max Meadows, Wythe County, Virginia is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Residents voiced concerns at county informational sessions over the proposed AI campus.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Residents voiced concerns at county informational sessions over the proposed AI campus.

Source: Southwest Virginia Sun

Notes on the record

Solis Arx (owner-operator; AI-compute tenant reported as Fluidstack) plans a phased AI data center campus on a 99-acre tract in Wythe County's Progress Park, ~15 minutes from Wytheville, served by Appalachian Power and Wytheville water. Coordinates are an approximate geocode of Progress Park (Max Meadows / Fort Chiswell area off I-81), not a parcel-confirmed point.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Solis Arx Progress Park Data Center Campus in Max Meadows?

Yes. Solis Arx Progress Park Data Center Campus in Max Meadows, Wythe County, Virginia is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Residents voiced concerns at county informational sessions over the proposed AI campus.

Has anyone filed a lawsuit over the Solis Arx Progress Park Data Center Campus?

No lawsuit over Solis Arx Progress Park Data Center Campus appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Solis Arx Progress Park Data Center Campus use?

No water withdrawal figure for Solis Arx Progress Park Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Solis Arx Progress Park Data Center Campus, and how big is it?

Solis Arx is the operator on record. No capacity figure is on record for this site.

How to cite this page

SueDataCenters.org Data Center Registry, "Solis Arx Progress Park Data Center Campus," updated July 26, 2026, https://suedatacenters.org/data-centers/solis-arx-progress-park-wythe-va.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/solis-arx-progress-park-wythe-va, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Data center campus announced for Wythe County · Cardinal News · retrieved July 26, 2026
  2. 2.Solis Arx Digital Infrastructure Project at Progress Park · Wythe County, VA (government) · retrieved July 26, 2026
  3. 3.Wythe County and Solis Arx Announce New Digital Infrastructure Investment in Progress Park · Wythe County, VA (government) · retrieved July 26, 2026 · original offline, no archived copy found
  4. 4.AI computing center headed to Wythe County · WSLS 10 · retrieved July 26, 2026
  5. 5.County explains Solis Arx data center plans as residents voice concerns · Southwest Virginia Sun · retrieved July 26, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us