Data Center Registry
Meta Hyperion
Delhi vicinity, Richland County, Louisiana · All 28 Meta sites · Every Meta case on our tracker
Meta Hyperion is a data center under construction in Delhi vicinity, Louisiana (Richland County), operated by Meta. The public record puts it at announced January 2025, 2 GW planned, 2,250 acres, a reported $10 billion investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
What our reporting adds
The base record's reception is mixed. Our reporting adds the police crash record for the construction phase, the fatality, the unlicensed commercial driver and the closed school playground, and sets the reception to contested on that basis.
Facility record
Under construction
- Operator
- Meta
- Facility type
- Data center, AI use confirmed
- Location
- Delhi vicinity, Richland County, LA
- Coordinates
- 32.4442, -91.4906
- Power capacity
- 2 GW planned
- Land
- 2,250 acres
- Investment
- $10 billion
- Announced
- January 2025
- Utility
- Entergy Louisiana
- Power source
- Mixed
- Cooling
- Closed loop
- Water use
- 5 million gallons a day, reported
- Jobs
- 500 permanent; 5,000 construction
- Public subsidy
- Louisiana Act 730 data center equipment sales/use tax exemption (20 years, state and local), Louisiana, 2025
- Community reception
- Contested
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- November 22, 2025Under constructionGulf States Newsroom publishes the crash records: 64 crashes in nine months against nine the year before, a driver killed, a driver with no license.
- June 2025Under constructionGovernor Landry visits Holly Ridge and meets the sheriff's office over traffic complaints; the state converts three Highway 80 intersections to all-way stops.
- January 2025ProposedAnnounced as part of Meta's $65B 2025 capex plan; described as a 2-gigawatt AI data center campus Source: Reuters
- 2025Under constructionSite preparation and construction underway Source: Meta
- December 2024Under constructionMeta breaks ground on Hyperion, described by the company as the largest data center in the world, in a parish where nearly a quarter of residents live below the poverty line.
Opposition and litigation at this site
Yes. Meta Hyperion in Delhi vicinity, Richland County, Louisiana is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Police records obtained by the Gulf States Newsroom show 64 crashes on the roads around the site from January to mid September 2025, against nine in all of 2024.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Police records obtained by the Gulf States Newsroom show 64 crashes on the roads around the site from January to mid September 2025, against nine in all of 2024. A dump truck driver was killed in August 2025. An 18-wheeler driver told a deputy he had never held a license. Holly Ridge Elementary closed its playground, which faces the truck route. About a dozen residents interviewed said no one from the company or the parish had contacted them after complaints.
Power and water
Entergy Louisiana is building new natural-gas combined-cycle generation (7+ units, 5,200+ MW) to serve the load, plus Meta committed up to 2,500 MW of new solar; Meta pledges to match total use with 100% clean and renewable energy. The gas buildout and its ratepayer impact are contested by advocates.
Sierra Club reporting states ~5 million gallons/day (~2 billion/year). Cooling type not disclosed in primary sources. Meta pledges 100% water restoration by 2030 via a 316-acre restoration project with Resource Environmental Solutions.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Louisiana Act 730 data center equipment sales/use tax exemption (20 years, state and local) | Not established | Louisiana | 2025 |
Notes on the record
A second, larger Meta data center development at the same Richland Parish complex is in progress under the internal name 'Project Evest' (Evest LLC, a Meta subsidiary and Laidley affiliate), the subject of a new, not-yet-docketed LPSC certification application (Direct Testimony of Laura K. Beauchamp on behalf of Entergy Louisiana, filed March 2026, public-redacted version). The testimony states Evest 'seeks to develop adjacent to Laidley's data center in Richland Parish, Louisiana, that was the subject of the proceedings in LPSC Docket No. U-37425' (i.e., the already-tracked Hyperion project). To serve Evest, Entergy is seeking certification of seven new 754 MW 1x1 CCCT generators (four near the Richland Parish site, three sited near the existing Big Cajun site in Pointe Coupee Parish) plus battery storage co-located at the Bogalusa West Solar and Cypress Harvest Solar facilities -- on top of the three CCCTs (Franklin Farms 1&2, Waterford 5) already approved for Hyperion itself. Investigative coverage (The Lens, 2026-04-14) puts the combined Hyperion+Evest generation build at 10 new gas plants, 7,000+ MW, and $16B+ in new fossil-fuel infrastructure serving this one customer, and reports the underlying Entergy-Meta commercial agreements are not fully public. This is DISTINCT NEW information not yet reflected in the existing record's notes/community fields (which per the roster are already populated) -- flagging for maintainer review rather than as a field-merge, since 'community' on this record is locked (already has a value) and it is not yet certain whether Evest will ship as a second facility record or as an update to this one once its own docket number and site-specific coordinates are public.
Our reporting on this site
- 'Poverty, Crime and Squalor' · Guide
Questions people ask about this site
Is there opposition to the Meta Hyperion data center in Delhi vicinity?
Yes. Meta Hyperion in Delhi vicinity, Richland County, Louisiana is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Police records obtained by the Gulf States Newsroom show 64 crashes on the roads around the site from January to mid September 2025, against nine in all of 2024.
Has anyone filed a lawsuit over the Meta Hyperion data center?
No lawsuit over Meta Hyperion appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Meta Hyperion use?
5 million gallons a day is the reported figure on record. Cooling is recorded as closed_loop. Sierra Club reporting states ~5 million gallons/day (~2 billion/year).
Who operates Meta Hyperion, and how big is it?
Meta is the operator on record. We hold 28 sites for that company across the registry. Capacity on record is 2 GW. The site is recorded at 2250 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Meta Hyperion," updated September 10, 2026, https://suedatacenters.org/data-centers/meta-hyperion-richland-parish-la.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/meta-hyperion-richland-parish-la, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Meta to build AI data center in Louisiana, Reuters · Reuters · retrieved July 5, 2026 · original offline, no archived copy found
- 2.Meta Announces 2-Gigawatt AI Data Center in Louisiana, Meta Newsroom · Meta · retrieved July 5, 2026 · original offline, no archived copy found
- 3.Meta Selects Northeast Louisiana as Site of $10 Billion AI-Optimized Data Center · Louisiana Economic Development · retrieved July 6, 2026
- 4.Richland Parish Data Center · Meta · retrieved July 6, 2026
- 5.Meta's $10 billion Louisiana data center is getting $3.3 billion in tax breaks · Fortune · retrieved July 6, 2026
- 6.Entergy Louisiana announces new agreement with Meta · Entergy Louisiana · retrieved July 6, 2026
- 7.In Rural Louisiana, Meta's New Data Center Promises Growth, But at What Cost? · Sierra Club · retrieved July 6, 2026
- 8.Meta's Richland Parish Data Center · Meta · retrieved August 20, 2026
- 9.The largest Meta data center yet brings big impact to Louisiana, Richland Parish Data Center · Meta · retrieved August 26, 2026
- 10.Entergy Louisiana receives LPSC approval for major infrastructure investments to support Meta's data center · Entergy · retrieved August 26, 2026
- 11.Direct Testimony of Laura K. Beauchamp, Entergy Louisiana (Project Evest), March 2026, seven additional 754 MW CCCTs and 400 MW of battery storage · Louisiana Public Service Commission · retrieved August 26, 2026
- 12.Teachers and Local Businesses Win as Meta Expands Louisiana Data Center · Meta · retrieved September 3, 2026
- 13.Construction on Meta's largest data center brings 600% crash spike, chaos to rural Louisiana · Louisiana Illuminator / Gulf States Newsroom · retrieved September 5, 2026
- 14.'Poverty, Crime and Squalor': the president's data center claim, checked against the records · SueDataCenters.org · retrieved September 5, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us