Prometheus Hyperscale Falls Ranch Data Center Campus

Glenrock, Converse County, Wyoming · All 5 Prometheus Hyperscale sites

ProposedContestedAI confirmedRecord updated August 19, 2026

Prometheus Hyperscale Falls Ranch Data Center Campus is a proposed data center in Glenrock, Wyoming (Converse County), operated by Prometheus Hyperscale. The public record puts it at announced October 2025, 1.5 GW planned, a reported $500 million investment. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Prometheus Hyperscale
Facility type
Data center, AI use confirmed
Location
Glenrock, Converse County, WY
Coordinates
42.8700, -106.1500 (approximate)
Power capacity
1.5 GW planned
Land
Not established from a public source
Investment
$500 million
Announced
October 2025
Utility
PacifiCorp
Power source
Mixed
On site generation
1.5 GW
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Wyoming Data Center Sales Tax Exemption, Wyoming, 2022
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Yes. Prometheus Hyperscale Falls Ranch Data Center Campus in Glenrock, Converse County, Wyoming is contested. Hearings, public comment, petitions, or organized opposition are on record. Neighboring landowners mounted "fierce pushback" over noise, heat, fumes, and traffic concerns, prompting developers to weigh relocating to an alternate parcel as of July 2026 (no denial or lawsuit yet).

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Neighboring landowners mounted "fierce pushback" over noise, heat, fumes, and traffic concerns, prompting developers to weigh relocating to an alternate parcel as of July 2026 (no denial or lawsuit yet).

Source: Oil City News

Power and water

On-site generation with a minimum $500M initial investment; carbon-negative operations via partnership with Spiritus and Casper Carbon Capture, combining natural gas with proprietary geothermal systems and carbon capture.

Developer describes proprietary aquifer, non-consumptive water-cooling systems for the high-density compute halls.

Public money on the record

ProgramAmountGranted byYear
Wyoming Data Center Sales Tax ExemptionNot establishedWyoming2022

Notes on the record

1.5GW campus proposed on the Falls Ranch property spanning the Natrona/Converse county line near I-25, roughly 10 miles east of Casper. Site plan still in flux as of July 2026, with developers weighing an alternate parcel south of I-25; targeted operational by 2028.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Permanent jobs promised
  • Land area
Which document closes each gap
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Prometheus Hyperscale Falls Ranch Data Center Campus in Glenrock?

Yes. Prometheus Hyperscale Falls Ranch Data Center Campus in Glenrock, Converse County, Wyoming is contested. Hearings, public comment, petitions, or organized opposition are on record. Neighboring landowners mounted "fierce pushback" over noise, heat, fumes, and traffic concerns, prompting developers to weigh relocating to an alternate parcel as of July 2026 (no denial or lawsuit yet).

Has anyone filed a lawsuit over the Prometheus Hyperscale Falls Ranch Data Center Campus?

The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.

How much water does Prometheus Hyperscale Falls Ranch Data Center Campus use?

No water withdrawal figure for Prometheus Hyperscale Falls Ranch Data Center Campus is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Prometheus Hyperscale Falls Ranch Data Center Campus, and how big is it?

Prometheus Hyperscale is the operator on record. We hold 5 sites for that company across the registry. Capacity on record is 1.5 GW.

How to cite this page

SueDataCenters.org Data Center Registry, "Prometheus Hyperscale Falls Ranch Data Center Campus," updated August 19, 2026, https://suedatacenters.org/data-centers/prometheus-hyperscale-casper-wy.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/prometheus-hyperscale-casper-wy, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Casper Lands Massive 1.5-Gigawatt Data Center Project on Nearby Ranch · Cowboy State Daily · retrieved July 22, 2026
  2. 2.Prometheus Hyperscale plans data hall, energy infrastructure in Natrona County · Oil City News · retrieved July 22, 2026
  3. 3.Commissioners: Prometheus data center developers considering new Natrona County site · Oil City News · retrieved July 22, 2026
  4. 4.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
  5. 5.Prometheus Hyperscale works with carbon capture firms on new data center campus in Wyoming (Falls Ranch, Casper; up to 1.5 GW) · DatacenterDynamics · retrieved August 7, 2026
  6. 6.Prometheus Hyperscale, Spiritus, and Casper Carbon Capture Announce Strategic Partnership to Build Carbon-Negative Data Halls and Energy Infrastructure in Wyoming · PR Newswire · retrieved August 7, 2026
  7. 7.Prometheus Hyperscale, Spiritus, and Casper Carbon Capture Announce Strategic Partnership to Build Carbon-Negative Data Halls and Energy Infrastructure in Wyoming · Prometheus Hyperscale · retrieved August 19, 2026
  8. 8.Wyoming Business Council program & service catalog, materials prepared for the Joint Minerals Committee (June 2026), Data Center Sales Tax Exemption recipients · Wyoming Business Council / Wyoming Legislature · retrieved August 19, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us