Data Center Registry
Project Tembo
Cheyenne, Laramie County, Wyoming · All 53 Google sites · Every Google case on our tracker
Project Tembo is a data center under construction in Cheyenne, Wyoming (Laramie County), operated by Google. The public record puts it at announced January 2026, 2.7 GW planned, 716 acres. It has documented support and documented opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Facility type
- Data center, AI use likely
- Location
- Cheyenne, Laramie County, WY
- Coordinates
- 41.1200, -104.8200
- Power capacity
- 2.7 GW planned
- Land
- 716 acres
- Investment
- Not established from a public source
- Announced
- January 2026
- Utility
- Black Hills Energy
- Power source
- On site gas
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- 400 permanent; 5,000 construction
- Public subsidy
- Not established from a public source
- Community reception
- Mixed reception
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 2026Under constructionGoogle publicly revealed as owner/operator (via subsidiary Jupiter Star Holdings, which replaced Crusoe Energy as builder); project renamed 'Project Tembo'. Capacity confirmed at 2.7GW with potential to scale to 10GW total. Completion targeted 2031. Source: Cowboy State Daily
- January 2026Under constructionLaramie County approved the project Jan 2026; site work underway at Switchgrass Industrial Park (Hwy 85 south of Cheyenne). Crusoe (original builder) exited June 2026; Tallgrass now works directly with the unnamed DC client Source: Data Center Dynamics
Opposition and litigation at this site
Partly. Both documented support and documented opposition to Project Tembo in Cheyenne, Laramie County, Wyoming appear in the record, with no clear majority position.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.
Power and water
Cheyenne Power Hub natural-gas plant (Tallgrass), scalable toward multi-GW; Black Hills Energy co-invested.
Closed-loop cooling systems recirculating treated water; plans include deep wells beneath the Lance Formation to reach industrial water below the Ogallala Aquifer. Wastewater treatment is to occur on site with evaporative lagoon storage, which is disposal rather than the heat-rejection method.
Notes on the record
Switchgrass Industrial Park, Hwy 85 south of Cheyenne, Laramie County - geographically distinct from Meta (Project Cosmo) and Microsoft's Cheyenne campuses. 716-acre campus. Originally announced at 1.8GW as 'Project Jade' with an undisclosed hyperscale client (Crusoe Energy as builder); Crusoe exited June 2026. On 2026-07-08, Google was publicly revealed as owner/operator via subsidiary Jupiter Star Holdings, and the project was renamed 'Project Tembo'; capacity confirmed at 2.7GW with an ultimate ceiling of up to 10GW. The Cheyenne Power Hub on-site natural-gas plant supplies power (Tallgrass Energy; Black Hills Energy co-invested). ~$50B total project figure remains a projection. Completion targeted 2031.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Crypto Knight Hosting Cheyenne Bitcoin Mining Facility · Cheyenne · Crypto Knight Hosting1 mi · Operating
- CleanSpark Cheyenne Bitcoin Mining Campus · Cheyenne · CleanSpark, Inc.1 mi · Operating · 75 MW
- Lunavi Cheyenne Data Center · Cheyenne · Lunavi2 mi · Operating · 8 MW
- Microsoft Cheyenne Mega-Campus Expansion · Cheyenne · Microsoft3 mi · Permitted · Supported
- Meta Cheyenne Data Center · Cheyenne · Meta3 mi · Under construction · 109 MW · Supported
- NCAR-Wyoming Supercomputing Center · Cheyenne · University Corporation for Atmospheric Research (UCAR)4 mi · Operating
- Related Digital Cheyenne Data Center Campus · Cheyenne · Related Digital4 mi · Under construction · 302 MW
- EchoStar Cheyenne Data Center and Satellite Uplink Facility · Cheyenne · EchoStar5 mi · Operating
Questions people ask about this site
Is there opposition to the Project Tembo data center in Cheyenne?
Partly. Both documented support and documented opposition to Project Tembo in Cheyenne, Laramie County, Wyoming appear in the record, with no clear majority position.
Has anyone filed a lawsuit over the Project Tembo data center?
No lawsuit over Project Tembo appears in the record we track as of September 2, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Project Tembo use?
No water withdrawal figure for Project Tembo is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Project Tembo, and how big is it?
Google is the operator on record. We hold 53 sites for that company across the registry. Capacity on record is 2.7 GW. The site is recorded at 716 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Tembo," updated September 2, 2026, https://suedatacenters.org/data-centers/tallgrass-project-jade-cheyenne-wy.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/tallgrass-project-jade-cheyenne-wy, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Crusoe gets go-ahead for 1.8GW data center campus and power plant in Cheyenne, Wyoming · Data Center Dynamics · retrieved July 7, 2026
- 2.Partner pulling out doesn't slow huge 2.7GW Cheyenne Project Jade data center · Cowboy State Daily · retrieved July 7, 2026
- 3.Say Hello To Google, The Mystery Owner Behind Wyoming's Largest Data Center Project · Cowboy State Daily · retrieved July 9, 2026
- 4.Say Hello To Google, The Mystery Owner Behind Wyoming's Largest Data Center Project · Cowboy State Daily · retrieved August 7, 2026
- 5.Wyoming Approves Data Center Campus That Includes 2.7 GW of New Natural Gas-Fired Generation · POWER Magazine · retrieved August 7, 2026
- 6.Wyoming data center power projects highlight new entrants, partnerships in power generation market · Power Engineering · retrieved September 2, 2026
- 7.Laramie County approves construction of what could become the largest data center in US · WyoFile · retrieved September 2, 2026
- 8.Say Hello To Google, The Mystery Owner Behind Wyoming's Largest Data Center, Now Project Tembo · Cowboy State Daily · retrieved September 2, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us