Meta Cheyenne Data Center
Cheyenne, Laramie County, Wyoming · All 28 Meta sites · Every Meta case on our tracker
Meta Cheyenne Data Center is a data center under construction in Cheyenne, Wyoming (Laramie County), operated by Meta. The public record puts it at announced July 2024, 109 MW planned, 960 acres, a reported $800 million investment. It has documented public support and no documented opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Meta
- Facility type
- Data center, AI use confirmed
- Location
- Cheyenne, Laramie County, WY
- Coordinates
- 41.0990, -104.7690
- Power capacity
- 109 MW planned
- Land
- 960 acres
- Investment
- $800 million
- Announced
- July 2024
- Utility
- Black Hills Energy
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- 100 permanent; 1,000 construction
- Public subsidy
- Wyoming Data Center Sales Tax Exemption, Wyoming, 2022
- Community reception
- Supported
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- January 2024Under constructionConstruction began months before official July 2024 Meta announcement; Fortis Construction serving as GC; 715,000 sq ft, at least two buildings Source: Data Center Dynamics
- November 2023PermittedProject Cosmo approved by Cheyenne City Council; Meta used shell company Goat Systems LLC during planning Source: Data Center Dynamics
Opposition and litigation at this site
Not that we can document. Local officials or residents have expressed public support for Meta Cheyenne Data Center in Cheyenne, Laramie County, Wyoming, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of August 19, 2026. Meta announced Data Center Community Action Grants for Cheyenne schools and nonprofits in 2026.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.
Meta announced Data Center Community Action Grants for Cheyenne schools and nonprofits in 2026. Wyoming tax incentives for data center operators cited as a deciding factor in site selection.
Power and water
Served under Black Hills Energy Large Power Contract Service tariff with customized renewable procurement. Meta and Black Hills Energy partnered to add new renewable resources to the Wyoming grid. Note: Meta signed a separate January 2026 portfolio-wide PPA with TerraPower for up to 8 remote Natrium reactors (power delivery via grid, not at the Cheyenne site); no on-site nuclear generation planned at this location per cited sources.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Wyoming Data Center Sales Tax Exemption | Not established | Wyoming | 2022 |
Notes on the record
715,000 sq ft campus at High Plains Business Park, Meta's 25th global data center. Originally Project Cosmo. Optimized for AI workloads with new H-departed design. Expected operational 2027. Coordinates approximate for High Plains Business Park in SE Cheyenne. Energy.notes corrected: removed on-site nuclear claim (Meta-TerraPower PPA is portfolio-wide grid delivery, not an on-site Cheyenne plant) and removed unverified $1.2B solar claim. jobs.sourceIndex corrected from 0 to 1 (Cheyenne LEADS is the source for the 1,000 construction jobs figure).
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Lunavi Cheyenne Data Center · Cheyenne · Lunaviunder 1 mile · Operating · 8 MW
- Microsoft Cheyenne Mega-Campus Expansion · Cheyenne · Microsoft1 mi · Permitted · Supported
- Related Digital Cheyenne Data Center Campus · Cheyenne · Related Digital3 mi · Under construction · 302 MW
- Project Tembo · Cheyenne · Google3 mi · Under construction · 2.7 GW · Mixed reception
- EchoStar Cheyenne Data Center and Satellite Uplink Facility · Cheyenne · EchoStar3 mi · Operating
- Crypto Knight Hosting Cheyenne Bitcoin Mining Facility · Cheyenne · Crypto Knight Hosting4 mi · Operating
- CleanSpark Cheyenne Bitcoin Mining Campus · Cheyenne · CleanSpark, Inc.4 mi · Operating · 75 MW
- NCAR-Wyoming Supercomputing Center · Cheyenne · University Corporation for Atmospheric Research (UCAR)7 mi · Operating
Questions people ask about this site
Is there opposition to the Meta Cheyenne Data Center in Cheyenne?
Not that we can document. Local officials or residents have expressed public support for Meta Cheyenne Data Center in Cheyenne, Laramie County, Wyoming, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of August 19, 2026. Meta announced Data Center Community Action Grants for Cheyenne schools and nonprofits in 2026.
Has anyone filed a lawsuit over the Meta Cheyenne Data Center?
No lawsuit over Meta Cheyenne Data Center appears in the record we track as of August 19, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Meta Cheyenne Data Center use?
No water withdrawal figure for Meta Cheyenne Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Meta Cheyenne Data Center, and how big is it?
Meta is the operator on record. We hold 28 sites for that company across the registry. Capacity on record is 109 MW. The site is recorded at 960 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Meta Cheyenne Data Center," updated August 19, 2026, https://suedatacenters.org/data-centers/meta-cheyenne-wy.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/meta-cheyenne-wy, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Meta Officially Announces Data Center in Cheyenne, Wyoming · Data Center Dynamics · retrieved July 6, 2026
- 2.Meta Announces New Data Center, a Major Investment, in Cheyenne, Wyoming · Cheyenne LEADS · retrieved July 6, 2026
- 3.Meta/Facebook Announces Plans for $800-Million Data Center in Cheyenne, WY · Electrical Wholesaling · retrieved August 7, 2026
- 4.Meta Cheyenne, Building 1 (109 MW) · CleanView · retrieved August 7, 2026
- 5.Wyoming Business Council program & service catalog, materials prepared for the Joint Minerals Committee (June 2026), Data Center Sales Tax Exemption recipients · Wyoming Business Council / Wyoming Legislature · retrieved August 19, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us