Sioux Falls Technology Park (Gemini Data Center)

Sioux Falls, Minnehaha County, South Dakota

PermittedContestedAI likelyRecord updated July 6, 2026

Sioux Falls Technology Park (Gemini Data Center) is a permitted data center in Sioux Falls, South Dakota (Minnehaha County), operated by Gemini Data Center SD LLC. The public record puts it at announced 2025, 500 MW planned, 164 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Permitted

Operator
Gemini Data Center SD LLC
Facility type
Data center, AI use likely
Location
Sioux Falls, Minnehaha County, SD
Coordinates
43.5830, -96.6850
Power capacity
500 MW planned
Land
164 acres
Investment
Not established from a public source
Announced
2025
Utility
Xcel Energy
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. January 2026
    Permitted
    Sioux Falls City Council approved annexation (October 8, 2025) and unanimously approved rezoning from agricultural to light industrial (January 2026), despite hours of opposing testimony. Construction was targeted for 2026 and operation for 2028. The developer committed to funding all utility extensions at its own cost. Source: SiouxFalls.Business
  2. 2025
    Proposed
    Gemini Data Center SD LLC (a California family office under Michael Anvar) acquired ~164 acres from Xcel Energy northeast of Sioux Falls, adjacent to Xcel's Split Rock substation, and sought city approvals for a data center supporting up to 500 MW. Gemini is the land developer, not the operator; no tenant is signed. Source: SiouxFalls.Business

Opposition and litigation at this site

Yes. Sioux Falls Technology Park (Gemini Data Center) in Sioux Falls, Minnehaha County, South Dakota is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. The city council approved rezoning unanimously despite hours of opposing public testimony; a citizen petition drive is gathering signatures that could force the rezoning to a public vote.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

The city council approved rezoning unanimously despite hours of opposing public testimony; a citizen petition drive is gathering signatures that could force the rezoning to a public vote. A state 50-year sales-tax exemption bill failed in the 2026 legislative session.

Source: SiouxFalls.Business

Power and water

Site adjacent to Xcel's Split Rock substation and Angus Anson power station; an Xcel facility study is in process. The developer committed to funding utility extensions and substation upgrades.

Notes on the record

aiClassification is 'likely' (not 'confirmed'): Gemini is the land developer, no tenant is signed, and only developer aspiration to attract a hyperscale/AI/neocloud tenant is on record. Capacity (500 MW) and acreage per SiouxFalls.Business; an earlier report cited 160 acres. Coordinates are approximate for the northeast Sioux Falls site. As a developer land project with no signed tenant, its water, subsidy, investment, and job figures remain developer projections only (South Dakota has no state income tax and rejected data-center incentive bills); all recorded as honest-zeros pending a confirmed tenant.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Sioux Falls Technology Park (Gemini Data Center) in Sioux Falls?

Yes. Sioux Falls Technology Park (Gemini Data Center) in Sioux Falls, Minnehaha County, South Dakota is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. The city council approved rezoning unanimously despite hours of opposing public testimony; a citizen petition drive is gathering signatures that could force the rezoning to a public vote.

Has anyone filed a lawsuit over the Sioux Falls Technology Park (Gemini Data Center)?

No lawsuit over Sioux Falls Technology Park (Gemini Data Center) appears in the record we track as of July 6, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Sioux Falls Technology Park (Gemini Data Center) use?

No water withdrawal figure for Sioux Falls Technology Park (Gemini Data Center) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Sioux Falls Technology Park (Gemini Data Center), and how big is it?

Gemini Data Center SD LLC is the operator on record. Capacity on record is 500 MW. The site is recorded at 164 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Sioux Falls Technology Park (Gemini Data Center)," updated July 6, 2026, https://suedatacenters.org/data-centers/gemini-data-center-sioux-falls-sd.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/gemini-data-center-sioux-falls-sd, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Hyperscale data center seeking city approvals to build northeast of Sioux Falls · SiouxFalls.Business · retrieved July 6, 2026
  2. 2.Sioux Falls data center developers detail next steps · SiouxFalls.Business · retrieved July 6, 2026
  3. 3.Planned hyperscale data center moving into South Dakota's largest city · The Dakota Scout · retrieved July 6, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us