Sequitor Edge Rapid City is a proposed data center in Rapid City, South Dakota (Pennington County), operated by Sequitor Edge. The public record puts it at 10 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Sequitor Edge
Facility type
Data center
Location
S Highway 79, Black Hills Industrial Center, Rapid City, Pennington County, SD
Coordinates
44.0223, -103.1914 (approximate)
Power capacity
Not established from a public source
Land
10 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Black Hills Energy
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Opposition and litigation at this site

Nothing on record as of September 13, 2026. No lawsuit, organized opposition, or contested hearing over Sequitor Edge Rapid City in Rapid City, Pennington County, South Dakota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Power and water

Reported to require no new grid infrastructure for the initial phase.

Closed-loop cooling system with a one-time water fill of approximately 19,000 gallons (Baxtel, fetched 2026-09-13).

Notes on the record

Capacity is disputed between the two sources fetched this run and is deliberately omitted from capacityMw rather than guessed: Baxtel states an initial 2MW phase scaling to 10MW; KOTA TV separately reports 15MW for the same project (also citing a 1.3 PUE design target vs. an industry average of 1.8-2.0). Tier 3 edge computing facility, greenfield, an initial ~30,000 sq ft building on a 1-acre footprint within a 10-acre site, expandable to five data halls across 7 acres. Construction was reported (both sources) to begin late summer 2026 with a roughly 14-month build targeting a 2027 opening; no source checked this run (2026-09-13) confirms construction has actually started. Coordinate is an OSM Nominatim road-level geocode of S Highway 79, Rapid City -- not a confirmed parcel.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Questions people ask about this site

Is there opposition to the Sequitor Edge Rapid City data center in Rapid City?

Nothing on record as of September 13, 2026. No lawsuit, organized opposition, or contested hearing over Sequitor Edge Rapid City in Rapid City, Pennington County, South Dakota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Sequitor Edge Rapid City data center?

No lawsuit over Sequitor Edge Rapid City appears in the record we track as of September 13, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Sequitor Edge Rapid City use?

No water withdrawal figure for Sequitor Edge Rapid City is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Sequitor Edge Rapid City, and how big is it?

Sequitor Edge is the operator on record. We hold 2 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 10 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Sequitor Edge Rapid City," updated September 13, 2026, https://suedatacenters.org/data-centers/sequitor-edge-rapid-city-sd.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/sequitor-edge-rapid-city-sd, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Sequitor Edge: Rapid City, South Dakota Data Center · Baxtel · retrieved September 13, 2026
  2. 2.South Dakota drought strains power grid as Rapid City data center moves forward · KOTA TV · retrieved September 13, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us