Holtec HI-CLOUD Indian Point data center campus (proposed) is a proposed data center in Buchanan, New York (Westchester County), operated by Holtec International (Holtec Decommissioning International). The public record puts it at announced July 31, 2025, 200 MW planned. It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Holtec International (Holtec Decommissioning International)
- Facility type
- Data center, AI use likely
- Location
- 450 Broadway, Buchanan, Westchester County, NY, 10511
- Coordinates
- 41.2697, -73.9519 (approximate)
- Power capacity
- 200 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- July 31, 2025
- Utility
- Consolidated Edison
- Power source
- Grid
- Cooling
- Not established
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 31, 2025ProposedHoltec announced HI-CLOUD, naming Indian Point as anchor site with an initial 200 MW target Source: Holtec International
- October 2024ProposedHoltec asked NYISO to study 200 MW of load for a potential data center at the Indian Point training-building property (disclosed at the Dec 5, 2024 Decommissioning Oversight Board meeting) Source: Peekskill Herald
Opposition and litigation at this site
Yes. Organized local opposition to Holtec HI-CLOUD Indian Point data center campus (proposed) in Buchanan, Westchester County, New York is documented in the public record, without a lawsuit on file in the sources we track. An Oct 2025 virtual rally against Holtec's Indian Point plans drew 279 attendees (Food & Water Watch, Indian Point Safe Energy Coalition, Stop Holtec, Mothers Out Front, Ramapough Munsee Nation); Westchester County Legislature introduced an opposition act.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
An Oct 2025 virtual rally against Holtec's Indian Point plans drew 279 attendees (Food & Water Watch, Indian Point Safe Energy Coalition, Stop Holtec, Mothers Out Front, Ramapough Munsee Nation); Westchester County Legislature introduced an opposition act.
Power and water
Holtec cites existing grid systems capable of up to 2,000 MW and a future SMR-300 option; no generation is built.
Holtec cites 'direct Hudson River access for cooling'; cooling method not specified.
Notes on the record
Concept-stage: Holtec has a NYISO load-study request and a corporate HI-CLOUD announcement but, per its site VP (Dec 2024), 'no offer' and no tenant. Holtec cites up to 2,000 MW of existing grid interconnection, Hudson River access for cooling, dark fiber, and potential future SMR-300 on-site generation. The site sits within Holtec's 240-acre Indian Point decommissioning property; the Village of Buchanan/Town of Cortlandt zoning question is unresolved.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Evocative JFK2 (NY2) Chappaqua · Chappaqua · Evocative (formerly VPLS)12 mi · Operating
- TierPoint Hawthorne (11 & 17 Skyline Drive) · Hawthorne · TierPoint14 mi · Operating
- JPMorgan Chase Data Center, Orangeburg · Orangeburg · JPMorgan Chase16 mi · Operating · Contested
- DataBank LGA3 (Orangeburg Data Center Campus) · Orangeburg · DataBank16 mi · Operating · 40 MW
- Bloomberg LP Data Center · Orangeburg · Bloomberg LP16 mi · Operating · 50 MW
- Sterling Forest Business Resiliency Services Center (former IBM/Kyndryl Sterling Forest data center) · Sterling Forest (Town of Warwick) · Watchtower Bible and Tract Society of New York (acquired from Kyndryl, June 2026)17 mi · Operating · 8.75 MW
- NYSE Data Center (Mahwah) · Mahwah · New York Stock Exchange17 mi · Operating · 2.2 MW
- Treetop East Fishkill Data Center (proposed, no application filed) · East Fishkill · Treetop Development20 mi · Proposed · 1 GW · Opposed
Questions people ask about this site
Is there opposition to the Holtec HI-CLOUD Indian Point data center campus (proposed) in Buchanan?
Yes. Organized local opposition to Holtec HI-CLOUD Indian Point data center campus (proposed) in Buchanan, Westchester County, New York is documented in the public record, without a lawsuit on file in the sources we track. An Oct 2025 virtual rally against Holtec's Indian Point plans drew 279 attendees (Food & Water Watch, Indian Point Safe Energy Coalition, Stop Holtec, Mothers Out Front, Ramapough Munsee Nation); Westchester County Legislature introduced an opposition act.
Has anyone filed a lawsuit over the Holtec HI-CLOUD Indian Point data center campus (proposed)?
No lawsuit over Holtec HI-CLOUD Indian Point data center campus (proposed) appears in the record we track as of September 21, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Holtec HI-CLOUD Indian Point data center campus (proposed) use?
No water withdrawal figure for Holtec HI-CLOUD Indian Point data center campus (proposed) is on record here. Cooling is recorded as unknown, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Holtec HI-CLOUD Indian Point data center campus (proposed), and how big is it?
Holtec International (Holtec Decommissioning International) is the operator on record. Capacity on record is 200 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Holtec HI-CLOUD Indian Point data center campus (proposed)," updated September 21, 2026, https://suedatacenters.org/data-centers/holtec-hi-cloud-indian-point-buchanan-ny.
Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/holtec-hi-cloud-indian-point-buchanan-ny, retrieved October 1, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Holtec Announces HI-CLOUD: A Strategic Redevelopment Initiative (Indian Point anchor site, initial 200 MW target) · Holtec International · retrieved September 21, 2026
- 2.Holtec tells decommissioning board it wants to bring data center to Indian Point (200 MW NYISO request) · Peekskill Herald · retrieved September 21, 2026
- 3.Holtec's Indian Point Proposal Draws Community Scrutiny (SMR-300 + 200 MW AI data center; opposition rally) · The Examiner News · retrieved September 21, 2026
- 4.New York Data Center Map, 'Proposed Datacenters at 450 Broadway', Holtec Decommissioning International, Buchanan, 200 MW planned · dcmap.us · retrieved September 21, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us