Data Center Registry
Expedient Denver (Centennial) Data Center
Centennial, Arapahoe County, Colorado · All 11 Expedient sites
Expedient Denver (Centennial) Data Center is an operating data center in Centennial, Colorado (Arapahoe County), operated by Expedient. The public record puts it at 2.5 MW operating.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Expedient
- Facility type
- Data center
- Location
- 7347 S Revere Pkwy, Centennial, Arapahoe County, CO, 80112
- Coordinates
- 39.5812, -104.8426 (approximate)
- Power capacity
- 2.5 MW operating
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- November 17, 2021OperatingExpedient announced the 32,000 sq ft, 2.5 MW Centennial data center began operations. Source: Built In Colorado
Opposition and litigation at this site
Nothing on record as of October 19, 2026. No lawsuit, organized opposition, or contested hearing over Expedient Denver (Centennial) Data Center in Centennial, Arapahoe County, Colorado appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
The street address comes from directory listings and the OSM building record (Building C), not the launch article. The facility was previously associated with Digital Fortress.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- DataBank DEN5, Centennial II · Centennial · DataBankunder 1 mile · Operating · 16 MW
- Flexential Denver - Centennial (DEN05) · Centennial · Flexentialunder 1 mile · Operating
- Csquare (Centersquare) DEN2 Denver - Englewood · Englewood · Csquare (Centersquare)1 mi · Operating
- Flexential Denver - Englewood · Englewood · Flexential2 mi · Operating · 18 MW
- US Signal CO01 Denver Data Center · Englewood · US Signal2 mi · Operating
- EdgeConneX DEN01 Denver · Englewood · EdgeConneX2 mi · Operating · 3 MW
- Flexential Parker (Compark) · Parker · Flexential2 mi · Under construction · 22.5 MW · Supported
- H5 Data Centers Denver (Denver Tech Center campus) · Greenwood Village · H5 Data Centers4 mi · Operating
Questions people ask about this site
Is there opposition to the Expedient Denver (Centennial) Data Center in Centennial?
Nothing on record as of October 19, 2026. No lawsuit, organized opposition, or contested hearing over Expedient Denver (Centennial) Data Center in Centennial, Arapahoe County, Colorado appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Expedient Denver (Centennial) Data Center?
No lawsuit over Expedient Denver (Centennial) Data Center appears in the record we track as of October 19, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Expedient Denver (Centennial) Data Center use?
No water withdrawal figure for Expedient Denver (Centennial) Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Expedient Denver (Centennial) Data Center, and how big is it?
Expedient is the operator on record. We hold 11 sites for that company across the registry. Capacity on record is 2.5 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Expedient Denver (Centennial) Data Center," updated October 19, 2026, https://suedatacenters.org/data-centers/expedient-centennial-co.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/expedient-centennial-co, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Expedient Opens Denver-Area Data Center · Built In Colorado · retrieved October 19, 2026
- 2.OSM Nominatim geocode: Building C, 7347 South Revere Parkway · OpenStreetMap · retrieved October 19, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation