Boone County, West Virginia · All 2 Blockware Solutions sites

ProposedNo reception on recordRecord updated September 15, 2026

Blockware Solutions SunPark Bitcoin Mining Facility is a proposed crypto mining site in West Virginia (Boone County), operated by Blockware Solutions. The public record puts it at announced May 25, 2022, 150 MW planned, 20 acres, a reported $10 million investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Blockware Solutions
Facility type
Crypto mining
Location
Boone County, WV
Coordinates
38.0830, -81.9830 (approximate)
Power capacity
150 MW planned
Land
20 acres
Investment
$10 million
Announced
May 25, 2022
Utility
Not established from a public source
Power source
Mixed
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. May 25, 2022
    Proposed
    Blockware Solutions announced a 150-MW development at SunPark with a 60-MW, 20-acre first phase and $10 million phase-one investment; construction was expected to commence in Q4 2022. Source: PR Newswire / SEVA WV

Opposition and litigation at this site

Nothing on record as of September 15, 2026. No lawsuit, organized opposition, or contested hearing over Blockware Solutions SunPark Bitcoin Mining Facility in Boone County, West Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Announced as powered by West Virginia's PJM grid plus a planned on-site solar farm at SunPark; the 2022 releases describe a 3,000-acre solar field at the development.

Notes on the record

STALE ANNOUNCEMENT, status deliberately left at "proposed". The project was announced 2022-05-25 with construction expected in Q4 2022, and this session found no public source after 2022 confirming that construction started, that the facility energized, or that it was cancelled. investmentUsd records the $10 million phase-one figure and landAcres the 20-acre phase-one parcel, not a site total; capacityMw.planned is the announced 150 MW full build-out (phase one was 60 MW). SunPark is an extension of the Rock Creek Development on the former ~5,800-acre Hobet surface mine straddling Boone and Lincoln counties; coordinates are the Hobet mine point and the specific 20-acre parcel is not published. Counties: primarily recorded as Boone; the development spans Boone and Lincoln.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Free case review

Living near Blockware Solutions SunPark Bitcoin Mining Facility?

Tell us the basics and an independent attorney handling data center cases in your state will follow up. Free, and you are never obligated to hire anyone.

Questions people ask about this site

Is there opposition to the Blockware Solutions SunPark Bitcoin Mining Facility in Boone County, West Virginia?

Nothing on record as of September 15, 2026. No lawsuit, organized opposition, or contested hearing over Blockware Solutions SunPark Bitcoin Mining Facility in Boone County, West Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Blockware Solutions SunPark Bitcoin Mining Facility?

No lawsuit over Blockware Solutions SunPark Bitcoin Mining Facility appears in the record we track as of September 15, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Blockware Solutions SunPark Bitcoin Mining Facility use?

No water withdrawal figure for Blockware Solutions SunPark Bitcoin Mining Facility is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Blockware Solutions SunPark Bitcoin Mining Facility, and how big is it?

Blockware Solutions is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 150 MW. The site is recorded at 20 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Blockware Solutions SunPark Bitcoin Mining Facility," updated September 15, 2026, https://suedatacenters.org/data-centers/blockware-sunpark-boone-lincoln-county-wv.

Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/blockware-sunpark-boone-lincoln-county-wv, retrieved October 1, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.SEVA Announces Bitcoin Mining Partnership to Help Advance the Development of SunPark · PR Newswire / SEVA WV · retrieved September 15, 2026
  2. 2.Bitcoin mining leader to build facility as extension of former Hobet site project · WCHS-TV · retrieved September 15, 2026
  3. 3.Hobet Coal Mine, coordinates and Boone/Lincoln county straddle for the SunPark / Rock Creek redevelopment site · Wikipedia · retrieved September 15, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us