Data Center Registry
Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry)
Wheeling, Ohio County, West Virginia
Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry) is a proposed data center in Wheeling, West Virginia (Ohio County), operated by Silicon Foundation Energy. The public record puts it at announced June 22, 2026, 100 MW planned, 15 acres. It is or has been the subject of litigation over its siting, permitting, or operation.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Silicon Foundation Energy
- Facility type
- Data center
- Location
- 74 Warwood Avenue, Wheeling, Ohio County, WV, 26003
- Coordinates
- 40.1013, -80.7030 (approximate)
- Power capacity
- 100 MW planned
- Land
- 15 acres
- Investment
- Not established from a public source
- Announced
- June 22, 2026
- Utility
- Not established from a public source
- Power source
- Grid
- Cooling
- Not established
- Water use
- Not established from a public source
- Jobs
- 10 permanent
- Public subsidy
- Not established from a public source
- Community reception
- In litigation
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 22, 2026ProposedSilicon Foundation purchased the ~15-acre former Centre Foundry property at 74 Warwood Avenue and announced a phased data center and energy campus. Source: River News Network
Opposition and litigation at this site
Yes. Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry) in Wheeling, Ohio County, West Virginia is or has been the subject of litigation over its siting, permitting, or operation. Twelve Warwood residents sued Silicon Foundry Energy LLC (dba Silicon Foundation) in Ohio County Circuit Court in July 2026.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.
Twelve Warwood residents sued Silicon Foundry Energy LLC (dba Silicon Foundation) in Ohio County Circuit Court in July 2026. They seek declaratory and injunctive relief to halt the Warwood Data Center and argue HB 2014 is unconstitutional.
Power and water
Phase 1 is described as 10 MW drawn from the existing grid through the site's existing electrical substation, paired with battery energy storage; the development plan also cites on-site gas infrastructure for backup power. Stokes Energy is named as the EPC contractor.
West Virginia Public Broadcasting reports the development plan includes "access to river water for liquid cooling." No cooling method has been specified, so no cooling type is recorded.
Notes on the record
Phased plan: Phase 1 a 10-MW modular data center system with battery energy storage targeted for late 2026; Phase 2 expansion to 20 to 30 MW (reported as "as much as 100 megawatts" in 2027 by River News); Phase 3 a 100-MW regional compute hub. The planned capacity records the 100-MW full build-out. The foundry operated for more than 180 years until it closed in 2023. Under HB 2014 the project is exempt from county/municipal zoning and building permitting. Coordinates are the OSM address point for 74 Warwood Avenue, not a parcel-confirmed footprint.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Which utility serves it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- MARA Hopedale Data Center · Hopedale · MARA Holdings19 mi · Operating
- Bitdeer Clarington HPC/AI Campus · Clarington · Bitdeer24 mi · Under construction · 570 MW · In litigation
- Prime Data Centers Starpointe Campus · Hanover Township · Prime Data Centers LLC25 mi · Proposed · Opposed
- Zediker Station Data Center Site · South Strabane Township · CNX Resources27 mi · Proposed · Supported
Questions people ask about this site
Is there opposition to the Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry) in Wheeling?
Yes. Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry) in Wheeling, Ohio County, West Virginia is or has been the subject of litigation over its siting, permitting, or operation. Twelve Warwood residents sued Silicon Foundry Energy LLC (dba Silicon Foundation) in Ohio County Circuit Court in July 2026.
Has anyone filed a lawsuit over the Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry)?
Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.
How much water does Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry) use?
No water withdrawal figure for Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry) is on record here. Cooling is recorded as unknown, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry), and how big is it?
Silicon Foundation Energy is the operator on record. Capacity on record is 100 MW. The site is recorded at 15 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Silicon Foundation Warwood Data Center and Energy Campus (former Centre Foundry)," updated October 29, 2026, https://suedatacenters.org/data-centers/silicon-foundation-warwood-wheeling-ohio-county-wv.
Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/silicon-foundation-warwood-wheeling-ohio-county-wv, retrieved November 5, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.State's Sixth Data Center Announced Near Wheeling · West Virginia Public Broadcasting · retrieved October 28, 2026
- 2.Historic Centre Foundry Site Sold, Plans Announced for Data Center and Energy Campus in Wheeling · River News Network · retrieved September 15, 2026
- 3.OpenStreetMap Nominatim geocode, 74 Warwood Avenue, Wheeling, Ohio County, WV 26003 · OpenStreetMap · retrieved September 15, 2026
- 4.100MW Data Center Proposed for Wheeling, West Virginia · Baxtel · retrieved October 28, 2026
- 5.Warwood residents file civil suit to stop data center development · Weirton Daily Times · retrieved October 29, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us