Project Clydesdale
Owasso, Tulsa County, Oklahoma · All 6 Beale Infrastructure sites
Project Clydesdale is a data center under construction in Owasso, Oklahoma (Tulsa County), operated by Beale Infrastructure. The public record puts it at 506 acres, a reported $1 billion investment. It has documented public support and no documented opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Beale Infrastructure
- Facility type
- Data center, AI use likely
- Location
- Owasso, Tulsa County, OK
- Coordinates
- 36.2800, -95.8300 (approximate)
- Power capacity
- Not established from a public source
- Land
- 506 acres
- Investment
- $1 billion
- Announced
- Not established from a public source
- Utility
- Public Service Company of Oklahoma (PSO)
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Supported
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- October 2025Under constructionGroundbreaking October 30, 2025. Source: Construction Review Online
Opposition and litigation at this site
Not that we can document. Local officials or residents have expressed public support for Project Clydesdale in Owasso, Tulsa County, Oklahoma, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of October 22, 2026. The Tulsa County Board of Commissioners granted final approval, including tax incentives, on 2025-09-30.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.
The Tulsa County Board of Commissioners granted final approval, including tax incentives, on 2025-09-30. Oklahoma Lt. Gov. Matt Pinnell, Tulsa County Commissioner Stan Sallee, and Owasso Public Schools Superintendent Dr. Margaret Coates are all quoted supporting the project. One later isolated public comment on the article itself (Kyle Wilson, 2026-07-02: project 'will ruin Owasso') registers dissent, but it is a single online comment, not testimony at a hearing or an organized campaign, and it postdates the county's own unanimous-style final approval.
Power and water
News 9: the 506-acre campus plan includes 'a new PSO substation' and '1.5 miles of water lines.'
Notes on the record
Unincorporated Tulsa County near Owasso (Whirlpool Dr & E 76th St N, adjacent to Cherokee Industrial Park). Formerly known as 'Project Clydesbank.' 4 phases; electric service via PSO. End-tenant ('major data center operator' per a Quartz Mountain Properties LLC affiliate) unnamed. Coordinates are approximate. End-user unnamed.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Cherokee Data Center (Tulsa) · Tulsa · Hewlett-Packard7 mi · Operating
- Meta Project Anthem, Tulsa · Tulsa · Meta10 mi · Under construction · Contested
- Project Mustang · Claremore · Beale Infrastructure12 mi · Proposed · Mixed reception
- OneNet OSU-Tulsa Data Center · Tulsa · OneNet (Oklahoma State Regents for Higher Education)12 mi · Operating
- TierPoint Tulsa - Archer · Tulsa · TierPoint12 mi · Operating
- ENGUARD Data Center (Jackson Technical) · Tulsa · Jackson Technical12 mi · Operating · 0.4 MW
- Lumen Tulsa 1 · Tulsa · Lumen Technologies12 mi · Operating
- OCOSA Communications Tulsa Data Center (321 S Boston) · Tulsa · OCOSA Communications13 mi · Operating
Questions people ask about this site
Is there opposition to the Project Clydesdale data center in Owasso?
Not that we can document. Local officials or residents have expressed public support for Project Clydesdale in Owasso, Tulsa County, Oklahoma, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of October 22, 2026. The Tulsa County Board of Commissioners granted final approval, including tax incentives, on 2025-09-30.
Has anyone filed a lawsuit over the Project Clydesdale data center?
No lawsuit over Project Clydesdale appears in the record we track as of October 22, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Project Clydesdale use?
No water withdrawal figure for Project Clydesdale is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Project Clydesdale, and how big is it?
Beale Infrastructure is the operator on record. We hold 6 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 506 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Clydesdale," updated October 22, 2026, https://suedatacenters.org/data-centers/beale-project-clydesdale-tulsa-county-ok.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/beale-project-clydesdale-tulsa-county-ok, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Project Clydesdale: $1 billion data center in Tulsa breaks ground · Construction Review Online · retrieved September 10, 2026
- 2.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
- 3.Where are data centers being built across Oklahoma? · News 9 · retrieved October 16, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us