Sue Data Centers

Data Center Registry

Vantage Data Centers NV1

McCarran, Storey County, Nevada · All 20 Vantage Data Centers sites · Every Vantage Data Centers case on our tracker

Under constructionSupportedAI confirmedRecord updated September 10, 2026

Vantage Data Centers NV1 is a data center under construction in McCarran, Nevada (Storey County), operated by Vantage Data Centers. The public record puts it at announced July 2025, 224 MW planned, 137 acres, a reported $3 billion investment. It has documented public support and no documented opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Vantage Data Centers
Facility type
Data center, AI use confirmed
Location
McCarran, Storey County, NV
Coordinates
39.5311, -119.5904
Power capacity
224 MW planned
Land
137 acres
Investment
$3 billion
Announced
July 2025
Utility
NV Energy
Power source
Grid
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Supported
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. August 2025
    Under construction
    Construction underway; first building scheduled to open Q2 2026 Source: Vantage Data Centers
  2. July 2025
    Proposed
    Vantage announced $3B NV1 campus in Storey County; first two buildings fully pre-leased at announcement Source: Vantage Data Centers

Opposition and litigation at this site

Not that we can document. Local officials or residents have expressed public support for Vantage Data Centers NV1 in McCarran, Storey County, Nevada, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Storey County Manager Austin Osborne is quoted welcoming Vantage to the Tahoe-Reno Industrial Center, consistent with the county's general industrial-friendly posture toward data centers (see also tract-virginia-highlands-storey-county-nv).

How the community has taken it

Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.

Storey County Manager Austin Osborne is quoted welcoming Vantage to the Tahoe-Reno Industrial Center, consistent with the county's general industrial-friendly posture toward data centers (see also tract-virginia-highlands-storey-county-nv). Vantage also cites an EDAWN workforce-development partnership. No opposition documented. Checked: operator press release only.

Source

Power and water

NV Energy transmission via One Nevada (ON Line) 500kV corridor; geothermal and renewable sources available in region

Closed-loop chiller system minimizing water use; campus targets industry-leading low Water Usage Effectiveness (WUE); LEED certification planned

Notes on the record

Located in Tahoe Reno Industrial Center (TRIC), Storey County, NV, same industrial park as Google, Apple, Microsoft, and Switch (CITADEL tracked separately). Four multi-story buildings, 1M+ sq ft. Designed for AI densities 360W-720W per sq ft. Vantage's eighth North American market. Coordinates are approximate TRIC centroid. Primary press release states more than 1,200 individuals employed 'across the construction and ongoing operations', combined construction + permanent total; construction vs. permanent breakdown not separately disclosed.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Vantage Data Centers NV1 data center in McCarran?

Not that we can document. Local officials or residents have expressed public support for Vantage Data Centers NV1 in McCarran, Storey County, Nevada, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Storey County Manager Austin Osborne is quoted welcoming Vantage to the Tahoe-Reno Industrial Center, consistent with the county's general industrial-friendly posture toward data centers (see also tract-virginia-highlands-storey-county-nv).

Has anyone filed a lawsuit over the Vantage Data Centers NV1 data center?

No lawsuit over Vantage Data Centers NV1 appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Vantage Data Centers NV1 use?

No water withdrawal figure for Vantage Data Centers NV1 is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Vantage Data Centers NV1, and how big is it?

Vantage Data Centers is the operator on record. We hold 20 sites for that company across the registry. Capacity on record is 224 MW. The site is recorded at 137 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Vantage Data Centers NV1," updated September 10, 2026, https://suedatacenters.org/data-centers/vantage-nv1-storey-county-nv.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/vantage-nv1-storey-county-nv, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Vantage Data Centers Invests $3 Billion to Deliver AI Campus in Nevada · Vantage Data Centers · retrieved July 6, 2026
  2. 2.Vantage Data Centers NV1 Campus Announcement, BusinessWire · BusinessWire · retrieved July 6, 2026
  3. 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
  4. 4.NV1 and the Nevada Hyperscale Boom: Vantage Data Centers Bets $3B on the AI Future · Data Center Frontier · retrieved August 14, 2026
  5. 5.Vantage Data Centers invests $3 billion to deliver AI campus in growing Nevada market · retrieved September 10, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us