Data Center Registry
Project Bunkhouse (Taurus/Digital Realty Data Center Campus)
Stilesboro, Bartow County, Georgia
Project Bunkhouse (Taurus/Digital Realty Data Center Campus) is a permitted data center in Stilesboro, Georgia (Bartow County), operated by Taurus Investment Holdings (Taurus DC SPE LLC); to be managed by Digital Realty. The public record puts it at 1.8 GW planned, 876.57 acres, a reported $19 billion investment. It has documented public support and no documented opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- Taurus Investment Holdings (Taurus DC SPE LLC); to be managed by Digital Realty
- Facility type
- Data center
- Location
- Stilesboro, Bartow County, GA
- Coordinates
- 34.0870, -84.9100 (approximate)
- Power capacity
- 1.8 GW planned
- Land
- 876.57 acres
- Investment
- $19 billion
- Announced
- Not established from a public source
- Utility
- Georgia Power
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Supported
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 4, 2025Permittedpermitted per Bartow County Commissioner rezoning approval, Project Bunkhouse (Taurus DC SPE LLC) Source: Daily Tribune News
Opposition and litigation at this site
Not that we can document. Local officials or residents have expressed public support for Project Bunkhouse (Taurus/Digital Realty Data Center Campus) in Stilesboro, Bartow County, Georgia, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of July 26, 2026. Unanimous planning-commission recommendation (May 2025) followed by county approval (June 2025).
How the community has taken it
Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.
Unanimous planning-commission recommendation (May 2025) followed by county approval (June 2025).
Notes on the record
Rezoning approved by county commissioner June 4, 2025 after unanimous planning commission recommendation May 19/20, 2025. 12-building, 8.6M sq ft build-out per DCD; capacity/investment figures ($19B, 1,830MW) are widely reported industry estimates (DCD/CleanView/Server Country) tied to the project, not yet independently verified against a bond-validation dollar figure, flagged as reported-tier confidence on the financial figures even though the rezoning itself is confirmed via primary county action. Bartow County rezoning (8.3M sqft cap, 876.57 ac) confirmed via the county commissioner approval; the ~1,830 MW / ~$19B figures are widely-reported industry estimates, not a permit/bond figure, recorded reported-tier.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- DataBank Project Indo · Cartersville · DataBank8 mi · Proposed · 200 MW
- Kingston Technology Hub (Thor Equities) · Kingston · Thor Equities11 mi · Proposed · 150 MW
- Coosa Data Center (Project Gracie) · Rome · Atlas Development LLC19 mi · Permitted · Opposed
- Project Sassy (Atlas Development Rome Campus) · Rome · Atlas Development LLC19 mi · Proposed
- Microsoft Data Center Campus, Rome, GA · Rome · Microsoft19 mi · Permitted · Supported
- Project Springbank (Atlas Development Bartow County Campus) · Adairsville · Atlas Development LLC20 mi · Proposed · 432 MW
- Bells Ferry Road Data Center (MMM Acquisitions) · Marietta · MMM Acquisitions LLC (developer; end user undisclosed)22 mi · Permitted
- Liberty Road Data Center Campus (EdgeConneX) · Villa Rica · EdgeConneX (applicant East Village Dothan LLC)25 mi · Cancelled · Opposed
Questions people ask about this site
Is there opposition to the Project Bunkhouse (Taurus/Digital Realty Data Center Campus) in Stilesboro?
Not that we can document. Local officials or residents have expressed public support for Project Bunkhouse (Taurus/Digital Realty Data Center Campus) in Stilesboro, Bartow County, Georgia, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of July 26, 2026. Unanimous planning-commission recommendation (May 2025) followed by county approval (June 2025).
Has anyone filed a lawsuit over the Project Bunkhouse (Taurus/Digital Realty Data Center Campus)?
No lawsuit over Project Bunkhouse (Taurus/Digital Realty Data Center Campus) appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Project Bunkhouse (Taurus/Digital Realty Data Center Campus) use?
No water withdrawal figure for Project Bunkhouse (Taurus/Digital Realty Data Center Campus) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Project Bunkhouse (Taurus/Digital Realty Data Center Campus), and how big is it?
Taurus Investment Holdings (Taurus DC SPE LLC); to be managed by Digital Realty is the operator on record. Capacity on record is 1.8 GW. The site is recorded at 876.57 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Project Bunkhouse (Taurus/Digital Realty Data Center Campus)," updated July 26, 2026, https://suedatacenters.org/data-centers/taurus-digital-realty-project-bunkhouse-stilesboro-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/taurus-digital-realty-project-bunkhouse-stilesboro-ga, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Bartow County Commissioner rezoning approval, Project Bunkhouse (Taurus DC SPE LLC) · Daily Tribune News · retrieved July 17, 2026
- 2.Application filed for 8.6 million sq ft data center project outside Atlanta, Georgia · Data Center Dynamics · retrieved July 17, 2026
- 3.Bartow Planning Commission recommends approval of data center near Stilesboro · Coosa Valley News · retrieved July 17, 2026
- 4.Bartow County's sole commissioner discusses data centers (context on county DC pipeline) · My K Country · retrieved July 17, 2026
- 5.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us