Liberty Center One Royal Oak Data Center is an operating data center in Royal Oak, Michigan (Oakland County), operated by Liberty Center One.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Liberty Center One
- Facility type
- Data center
- Location
- 4815 Delemere Ave, Royal Oak, Oakland County, MI, 48073
- Coordinates
- 42.5335, -83.1774 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Opposition and litigation at this site
Nothing on record as of September 14, 2026. No lawsuit, organized opposition, or contested hearing over Liberty Center One Royal Oak Data Center in Royal Oak, Oakland County, Michigan appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Independent Michigan colocation provider; the operator also lists a Cincinnati, OH office, which is not a Michigan facility. No square footage or MW is published on the operator site, so none is asserted.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- ManagedWay TYM1 (319 Executive Drive) · Troy · ManagedWay Company4 mi · Operating
- ManagedWay TYM2 (600 Executive Drive) · Troy · ManagedWay Company4 mi · Operating
- 123NET Southfield DC1 · Southfield · 123NET5 mi · Operating · 4 MW
- 123NET Southfield DC2 (Southfield Data Center NW) · Southfield · 123NET5 mi · Operating
- 123NET Southfield DC3 (Southfield Data Center W) · Southfield · 123NET5 mi · Operating
- 365 Data Centers Detroit (DT1) · Southfield · 365 Data Centers6 mi · Operating
- Metrobloks Southfield Data Center · Southfield · Metrobloks7 mi · Permitted · 100 MW · Contested
- EdgeConneX DET01 · Detroit (Oakland County) · EdgeConneX7 mi · Operating
Questions people ask about this site
Is there opposition to the Liberty Center One Royal Oak Data Center in Royal Oak?
Nothing on record as of September 14, 2026. No lawsuit, organized opposition, or contested hearing over Liberty Center One Royal Oak Data Center in Royal Oak, Oakland County, Michigan appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Liberty Center One Royal Oak Data Center?
No lawsuit over Liberty Center One Royal Oak Data Center appears in the record we track as of September 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Liberty Center One Royal Oak Data Center use?
No water withdrawal figure for Liberty Center One Royal Oak Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Liberty Center One Royal Oak Data Center, and how big is it?
Liberty Center One is the operator on record. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Liberty Center One Royal Oak Data Center," updated September 14, 2026, https://suedatacenters.org/data-centers/liberty-center-one-royal-oak-mi.
Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/liberty-center-one-royal-oak-mi, retrieved October 1, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Liberty Center One, "4815 Delemere Ave. Royal Oak, MI 48073 USA"; public and private cloud, colocation, disaster recovery · Liberty Center One · retrieved September 14, 2026
- 2.PeeringDB facility registry API, record "Liberty Center One", 4815 Delemere Ave, Royal Oak 48073 · PeeringDB · retrieved September 14, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us