Edged Energy Martindale Campus

Martindale, Caldwell County, Texas · All 6 Edged Energy sites

Under constructionNo reception on recordRecord updated October 14, 2026

Edged Energy Martindale Campus is a data center under construction in Martindale, Texas (Caldwell County), operated by Edged Energy. The public record puts it at 330 acres, a reported $2.8 billion investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Edged Energy
Facility type
Data center
Location
Martindale, Caldwell County, TX
Coordinates
29.8534, -97.8245 (approximate)
Power capacity
Not established from a public source
Land
330 acres
Investment
$2.8 billion
Announced
Not established from a public source
Utility
Not established from a public source
Power source
On site gas
Cooling
air
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. October 14, 2026
    Under construction
    Martindale 1 (869,685 sq ft) is under construction with completion slated for mid-2028. Martindale 2 is planned, and the campus is projected to exceed 2 million sq ft. Source: Baxtel

Opposition and litigation at this site

Nothing on record as of October 14, 2026. No lawsuit, organized opposition, or contested hearing over Edged Energy Martindale Campus in Martindale, Caldwell County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Initial 'clean-fuel' natural gas generation, meant to avoid grid-interconnection delays. Near the LCRA Timmerman peaker plant.

Edged's proprietary ThermalWorks waterless cooling.

Notes on the record

The investment figure ($2.8B) is the initial phase only. The county approved a tax abatement and reinvestment zone, but the amount is not stated. Coordinates are as listed by Baxtel. MW is undisclosed (an aggregator's 462 MW figure was not corroborated).

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Edged Energy Martindale Campus?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Edged Energy Martindale Campus in Martindale?

Nothing on record as of October 14, 2026. No lawsuit, organized opposition, or contested hearing over Edged Energy Martindale Campus in Martindale, Caldwell County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Edged Energy Martindale Campus?

No lawsuit over Edged Energy Martindale Campus appears in the record we track as of October 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Edged Energy Martindale Campus use?

No water withdrawal figure for Edged Energy Martindale Campus is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Edged Energy Martindale Campus, and how big is it?

Edged Energy is the operator on record. We hold 6 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 330 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Edged Energy Martindale Campus," updated October 14, 2026, https://suedatacenters.org/data-centers/edged-martindale-campus-caldwell-county-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/edged-martindale-campus-caldwell-county-tx, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Edged Energy: Martindale Campus · Baxtel · retrieved October 14, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us