Legacy Investing North Loop (former Star Tribune printing plant)
Minneapolis, Hennepin County, Minnesota
Legacy Investing North Loop (former Star Tribune printing plant) is a proposed data center in Minneapolis, Minnesota (Hennepin County), operated by Legacy Investing. The public record puts it at 20 MW planned, 13 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Legacy Investing
- Facility type
- Data center
- Location
- 800 North 1st Street, Minneapolis, Hennepin County, MN, 55401
- Coordinates
- 44.9907, -93.2766
- Power capacity
- 20 MW planned
- Land
- 13 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 30, 2026ProposedLegacy Investing reached an agreement to acquire the 13-acre former Star Tribune Heritage printing site; the project is pending city approvals. Source: CBS News Minnesota
Opposition and litigation at this site
Nothing on record as of September 18, 2026. No lawsuit, organized opposition, or contested hearing over Legacy Investing North Loop (former Star Tribune printing plant) in Minneapolis, Hennepin County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
CBS reports "approximately 566,000 square feet" on 13 acres with "20 megawatts" of capacity; FOX 9 puts the building at "nearly 600,000 square feet". The Star Tribune vacated the Heritage printing facility in December 2025. Minneapolis adopted a moratorium on data centers over 350,000 sq ft; the city's preliminary zoning recommendations would require a conditional use permit and confine new data centers to the DT1/DT2 districts in existing buildings.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Lumen Minneapolis 3 · Minneapolis · Lumen Technologiesunder 1 mile · Operating
- Atomic Data Minneapolis Central (MSP250) · Minneapolis · Atomic Data LLCunder 1 mile · Operating
- T5@Minneapolis (1001 Third Avenue South) · Minneapolis · T5 Data Centers (asset owned by a Cloud Capital / Arcapita joint venture since January 2026)1 mi · Operating · 31 MW
- Cologix Minneapolis (511 Building, MIN1-MIN5) · Minneapolis · Cologix, Inc.2 mi · Operating
- DataBank Downtown Minneapolis Data Center (MSP4) · Minneapolis · DataBank2 mi · Operating · 0.779 MW
- H5 Data Centers St. Paul · St. Paul · H5 Data Centers5 mi · Operating
- DataBank West Twin Cities Data Center (MSP1) · Edina · DataBank9 mi · Operating · 1.35 MW
- EdgeConneX Minneapolis (EDCMSP01) · Eden Prairie · EdgeConneX Inc.10 mi · Operating
Questions people ask about this site
Is there opposition to the Legacy Investing North Loop (former Star Tribune printing plant) in Minneapolis?
Nothing on record as of September 18, 2026. No lawsuit, organized opposition, or contested hearing over Legacy Investing North Loop (former Star Tribune printing plant) in Minneapolis, Hennepin County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Legacy Investing North Loop (former Star Tribune printing plant)?
No lawsuit over Legacy Investing North Loop (former Star Tribune printing plant) appears in the record we track as of September 18, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Legacy Investing North Loop (former Star Tribune printing plant) use?
No water withdrawal figure for Legacy Investing North Loop (former Star Tribune printing plant) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Legacy Investing North Loop (former Star Tribune printing plant), and how big is it?
Legacy Investing is the operator on record. Capacity on record is 20 MW. The site is recorded at 13 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Legacy Investing North Loop (former Star Tribune printing plant)," updated September 18, 2026, https://suedatacenters.org/data-centers/legacy-investing-north-loop-minneapolis-mn.
Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/legacy-investing-north-loop-minneapolis-mn, retrieved October 1, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.CBS News Minnesota, Data center company acquires former Star Tribune printing site (address, 13 acres, ~566,000 sq ft, 20 MW) · CBS News Minnesota · retrieved September 18, 2026
- 2.FOX 9, Data center proposed for former Star Tribune site sparks debate in Minneapolis · FOX 9 Minneapolis-St. Paul · retrieved September 18, 2026
- 3.OpenStreetMap/Nominatim geocode, Star Tribune Heritage Center, 800 North 1st Street, Minneapolis, MN 55401 · OpenStreetMap contributors · retrieved September 18, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us