IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd) is an operating data center in Eagan, Minnesota (Dakota County), operated by IronGate Data Centers / Eagan Capital LLC (Swervo-affiliated). It is or has been the subject of litigation over its siting, permitting, or operation.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
IronGate Data Centers / Eagan Capital LLC (Swervo-affiliated)
Facility type
Data center
Location
3199 Pilot Knob Road, Eagan, Dakota County, MN, 55121
Coordinates
44.8426, -93.1693
Power capacity
Not established from a public source
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Minnesota data center sales tax exemption (Minn. Stat. 297A.68 subd. 42), Certified (Refurbishment), MN
Community reception
In litigation
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 15, 2026
    Operating
    Listed Certified (Refurbishment) on DEED list as 'Irongate - MSP3', company Eagan Capital LLC, Eagan. City staff found temporary trailer-mounted chillers installed and operating without permits. Source: Minnesota Department of Employment and Economic Development

Opposition and litigation at this site

Yes. IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd) in Eagan, Dakota County, Minnesota is or has been the subject of litigation over its siting, permitting, or operation. Resident noise complaints about chillers; IUP denied May 2026; Eagan Capital lawsuit against the city's moratorium filed June 2026

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: in litigation means the facility is or has been the subject of a lawsuit related to its siting, permitting, or operation.

Resident noise complaints about chillers; IUP denied May 2026; Eagan Capital lawsuit against the city's moratorium filed June 2026

Source: MPR News

Public money on the record

ProgramAmountGranted byYear
Minnesota data center sales tax exemption (Minn. Stat. 297A.68 subd. 42), Certified (Refurbishment)Not establishedMN

Notes on the record

The former Unisys data center at Unisys Park, 3199 Pilot Knob Road, sold in November 2025. Eagan denied an Interim Use Permit for outdoor chillers in May 2026. IronGate also applied for eight permanent chillers. Eagan Capital sued the city over its data center moratorium on 2026-06-15. The point is the OSM building footprint.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Permanent jobs promised
  • Land area
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd) in Eagan?

Yes. IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd) in Eagan, Dakota County, Minnesota is or has been the subject of litigation over its siting, permitting, or operation. Resident noise complaints about chillers; IUP denied May 2026; Eagan Capital lawsuit against the city's moratorium filed June 2026

Has anyone filed a lawsuit over the IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd)?

Yes. This site is recorded as being in litigation. The case, the court, and the filings we hold are listed on this page under the timeline and the sources.

How much water does IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd) use?

No water withdrawal figure for IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd), and how big is it?

IronGate Data Centers / Eagan Capital LLC (Swervo-affiliated) is the operator on record. We hold 4 sites for that company across the registry. No capacity figure is on record for this site.

How to cite this page

SueDataCenters.org Data Center Registry, "IronGate MSP3 / Eagan Capital (former Unisys data center, 3199 Pilot Knob Rd)," updated November 2, 2026, https://suedatacenters.org/data-centers/irongate-msp3-eagan-unisys-park-mn.

Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/irongate-msp3-eagan-unisys-park-mn, retrieved November 3, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Data Center Sales Tax Refund Projects (list dated 7/15/2026) · Minnesota Department of Employment and Economic Development · retrieved November 2, 2026
  2. 2.Minnesota: Elk River data center developer withdraws application (covers Eagan Capital/IronGate chiller permits at Unisys Park) · The Gazette · retrieved November 2, 2026
  3. 3.Lawsuit filed against city of Eagan over one-year data center moratorium · MPR News · retrieved November 2, 2026
  4. 4.OSM Nominatim geocode: Unisys building, 3199 Pilot Knob Road, Eagan · OpenStreetMap · retrieved November 2, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us