Data Center Registry
Consolidated Communications (Fidium), 266 Main St. (BURLVTMA)
Burlington, Chittenden County, Vermont · All 2 Consolidated Communications sites
Consolidated Communications (Fidium), 266 Main St. (BURLVTMA) is an operating data center in Burlington, Vermont (Chittenden County), operated by Consolidated Communications, Inc. (Fidium).
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Consolidated Communications, Inc. (Fidium)
- Facility type
- Data center
- Location
- 266 Main St., Burlington, Chittenden County, VT, 05401
- Coordinates
- 44.4765, -73.2086 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Consolidated Communications (Fidium), 266 Main St. (BURLVTMA) in Burlington, Chittenden County, Vermont appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
A carrier interconnection facility (telephone central office, CLLI BURLVTMA) listed in PeeringDB with status 'ok' and 1 network present. Lightboard's PeeringDB notes say Consolidated now operates as Fidium. This is a telecom interconnection site, not a large compute facility. No capacity data is published.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- FirstLight Burlington Data Center (110 Cherry St, former Sovernet) · Burlington · FirstLight Fiberunder 1 mile · Operating
- Lightboard ★ Vermont (530 Community Drive carrier hotel) · South Burlington · Lightboard4 mi · Operating
- Vermont Advanced Computing Center (VACC), University of Vermont · South Burlington · University of Vermont4 mi · Operating
- Tech Vault Data Center · South Burlington · Tech Vault, Inc.4 mi · Operating
- FirstLight Data Center (Williston, VT) · Williston · FirstLight Fiber4 mi · Operating
- Zafra Plattsburgh crypto-mining hosting facility · Plattsburgh · Zafra, LLC17 mi · Operating · 8 MW
- Proposed St. Albans, VT Data Center (Unbuilt) · St. Albans · Unnamed developer24 mi · Cancelled
Questions people ask about this site
Is there opposition to the Consolidated Communications (Fidium), 266 Main St. (BURLVTMA) data center in Burlington?
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Consolidated Communications (Fidium), 266 Main St. (BURLVTMA) in Burlington, Chittenden County, Vermont appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Consolidated Communications (Fidium), 266 Main St. (BURLVTMA) data center?
No lawsuit over Consolidated Communications (Fidium), 266 Main St. (BURLVTMA) appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Consolidated Communications (Fidium), 266 Main St. (BURLVTMA) use?
No water withdrawal figure for Consolidated Communications (Fidium), 266 Main St. (BURLVTMA) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Consolidated Communications (Fidium), 266 Main St. (BURLVTMA), and how big is it?
Consolidated Communications, Inc. (Fidium) is the operator on record. We hold 2 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Consolidated Communications (Fidium), 266 Main St. (BURLVTMA)," updated October 28, 2026, https://suedatacenters.org/data-centers/consolidated-fidium-burlington-266-main-st-vt.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/consolidated-fidium-burlington-266-main-st-vt, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.PeeringDB facility record 4105: Consolidated - 266 Main St. (CLLI BURLVTMA) · PeeringDB · retrieved October 28, 2026
- 2.PeeringDB facility record 14600 (Lightboard Vermont) notes listing 'Fidium (f.k.a. Consolidated Communications), 266 Main St., Burlington, VT' as an extended facility · PeeringDB · retrieved October 28, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us