SmartTec Site 01 (Mead)
Mead, Bryan County, Oklahoma
SmartTec Site 01 (Mead) is a proposed data center in Mead, Oklahoma (Bryan County), operated by SmartTec by Z1Power. The public record puts it at 0.114 MW planned, 39.39 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- SmartTec by Z1Power
- Facility type
- Data center
- Location
- 8460 US Highway 70, Mead, Bryan County, OK, 73449
- Coordinates
- 34.0005, -96.5111 (approximate)
- Power capacity
- 0.114 MW planned
- Land
- 39.39 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Oklahoma Gas & Electric (OG&E)
- Power source
- Grid
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- September 14, 2026ProposedLand and buildings owned; construction start scheduled 24 September 2026, transformer commissioning 8 October 2026, fiber delivery October-November 2026. Operator states the campus is not yet offering commissioned capacity. Source: SmartTec by Z1Power
Opposition and litigation at this site
Nothing on record as of September 14, 2026. No lawsuit, organized opposition, or contested hearing over SmartTec Site 01 (Mead) in Mead, Bryan County, Oklahoma appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Existing on-site transformer rated 3,000 A at 208 V three-phase, awaiting OG&E commissioning (targeted 8 October 2026). The design is battery-backed with z1power LFP storage and sub-10 ms failover, on the stated premise that grid instability is the design basis of the site.
Initial proposal is 8 Supermicro systems using direct liquid cooling. The operator does not publish a water-use figure.
Notes on the record
Very small GPU colocation site on US-70 in Bryan County: three existing buildings (A 1,500 sq ft compute, B 2,083 sq ft batteries/utilities, C 3,535 sq ft compute), ~5,035 sq ft of gross data-center area. Phase 1A is 8× HGX-class systems, 64 GPUs, ~114 kW IT load, recorded here as 0.114 MW planned. Status is 'proposed' rather than 'under_construction' because as of 2026-09-14 the operator's own schedule puts construction start ten days out. Single-source (operator self-published), so confidence is 'reported'. Coordinates are the town of Mead; the street address did not resolve in OSM.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Questions people ask about this site
Is there opposition to the SmartTec Site 01 (Mead) data center in Mead?
Nothing on record as of September 14, 2026. No lawsuit, organized opposition, or contested hearing over SmartTec Site 01 (Mead) in Mead, Bryan County, Oklahoma appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the SmartTec Site 01 (Mead) data center?
No lawsuit over SmartTec Site 01 (Mead) appears in the record we track as of September 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does SmartTec Site 01 (Mead) use?
No water withdrawal figure for SmartTec Site 01 (Mead) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates SmartTec Site 01 (Mead), and how big is it?
SmartTec by Z1Power is the operator on record. Capacity on record is 0.114 MW. The site is recorded at 39.39 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "SmartTec Site 01 (Mead)," updated September 14, 2026, https://suedatacenters.org/data-centers/smarttec-site-01-mead-ok.
Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/smarttec-site-01-mead-ok, retrieved October 1, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Mead, Oklahoma Data Center Site, 39.39 acres, Bryan County · SmartTec by Z1Power · retrieved September 14, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us