Sue Data Centers

Data Center Registry

Project Andromeda (Oxford Township)

Erie County, Ohio

ProposedNo reception on recordRecord updated October 14, 2026

Project Andromeda (Oxford Township) is a proposed data center in Ohio (Erie County), operated by AVAIO Digital. The public record puts it at announced July 2026, 250 MW planned, 146 acres, a reported $5.5 billion investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
AVAIO Digital
Facility type
Data center
Location
Erie County, OH
Coordinates
41.3286, -82.6878 (approximate)
Power capacity
250 MW planned
Land
146 acres
Investment
$5.5 billion
Announced
July 2026
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 14, 2026
    Proposed
    Developer and local officials held a town hall on a proposed 250 MW, 4-building (~1.2M sq ft) campus on 146 acres in southwest Erie County. It is described as a $5.5B privately funded development. The township's existing data center prohibition would have to be lifted. Source: Stay Tuned Sandusky

Opposition and litigation at this site

Nothing on record as of October 14, 2026. No lawsuit, organized opposition, or contested hearing over Project Andromeda (Oxford Township) in Erie County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Notes on the record

Coordinates are the Oxford Township centroid (Wikipedia), not the parcel. Press places the site near the EHOVE Career Center but the exact parcel was not identified. The township must lift its data center prohibition before the project can proceed.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

  • Aligned NEO-01 · Sandusky (Perkins Township) · Aligned Data Centers7 mi · Under construction · 96 MW

Tell us about your situation

Living near Project Andromeda (Oxford Township)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Project Andromeda (Oxford Township) data center in Erie County, Ohio?

Nothing on record as of October 14, 2026. No lawsuit, organized opposition, or contested hearing over Project Andromeda (Oxford Township) in Erie County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Project Andromeda (Oxford Township) data center?

No lawsuit over Project Andromeda (Oxford Township) appears in the record we track as of October 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Project Andromeda (Oxford Township) use?

No water withdrawal figure for Project Andromeda (Oxford Township) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Project Andromeda (Oxford Township), and how big is it?

AVAIO Digital is the operator on record. Capacity on record is 250 MW. The site is recorded at 146 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Project Andromeda (Oxford Township)," updated October 14, 2026, https://suedatacenters.org/data-centers/avaio-digital-project-andromeda-oxford-township-oh.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/avaio-digital-project-andromeda-oxford-township-oh, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Stay Tuned Sandusky: 'Project Andromeda' by AVAIO Digital, 250 MW, 146 acres, ~1.2M sq ft in four buildings, $5.5B; town hall July 14, 2026 · Stay Tuned Sandusky · retrieved October 14, 2026
  2. 2.Sandusky Register: 'New data center proposed in Oxford Twp.' (investment could total $5.5B) · Sandusky Register · retrieved October 14, 2026
  3. 3.More Than Just Parks tracker: Project Andromeda (AVAIO Digital, Oxford Township, Erie County), proposed, 250 MW · More Than Just Parks · retrieved October 14, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us