Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C)

Ilion, Herkimer County, New York

ProposedMixed receptionAI confirmedRecord updated October 26, 2026

Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C) is a proposed data center in Ilion, New York (Herkimer County), operated by Turin Hoefler Avenue LLC. The public record puts it at 200 MW planned, 7.837 acres. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Turin Hoefler Avenue LLC
Facility type
Data center, AI use confirmed
Location
14 Hoefler Avenue, Ilion, Herkimer County, NY
Coordinates
43.0119, -75.0357 (approximate)
Power capacity
200 MW planned
Land
7.837 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
1,000 construction
Public subsidy
Not established from a public source
Community reception
Mixed reception
Source confidence
Confirmed by multiple independent sources or official documentation

Opposition and litigation at this site

Partly. Both documented support and documented opposition to Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C) in Ilion, Herkimer County, New York appear in the record, with no clear majority position. At a September 2026 hearing, residents backed a village moratorium but asked for revisions, and some worried about its effect on economic development.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

At a September 2026 hearing, residents backed a village moratorium but asked for revisions, and some worried about its effect on economic development. The vote was tabled. Turin Management says no data center end user is involved or committed and that it is also pursuing manufacturing.

Source: Spectrum News

Notes on the record

Redevelopment of the former Remington Arms firearms plant, which ceased production in 2024. WKTV: "Turin Hoefler Avenue LLC submitted a revised application" to the NYSDEC "Brownfield Cleanup Program" in January 2026 for "Site C," a "7.837-acre parcel," with a "250,000-square-foot AI data center" as the intended post-remediation use, at "14 Hoefler Ave., Ilion, NY"; the site has "widespread contamination in the soil, especially with heavy metals like arsenic, lead, and copper at levels above state cleanup standards for commercial use" and "15 vacant industrial buildings dating to the early 1900s," and the developer describes it as a "fossil-fuel-free, 100% electric site." The planned capacity of 200 MW comes from the Rockefeller Institute of Government's tracker entry for the project ("200 MW"), not from WKTV, which states no MW figure. County discrepancy: WKTV's article says Oneida County; the Rockefeller Institute says "Village of Ilion, Herkimer County." Ilion is in Herkimer County, so Herkimer is recorded and the WKTV attribution is treated as an error. The 7.837-acre figure is the Brownfield Site C parcel only; trade press describes a larger ~32-acre overall plant site and two 250,000 sq ft buildings, neither of which had been verified against a cited source as of September 2026, so neither is recorded. No permanent-jobs figure is recorded: the source says only that the project "aims to exceed the 274 positions lost when Remington closed," which is an aspiration, not a count. As of 2026-09-09, neither cited source states an investment figure, water/cooling detail, utility, or IDA or PILOT agreement. Because the site is fossil-fuel-free and 100% electric per the developer, no on-site generation is recorded.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Tell us about your situation

Living near Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C) in Ilion?

Partly. Both documented support and documented opposition to Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C) in Ilion, Herkimer County, New York appear in the record, with no clear majority position. At a September 2026 hearing, residents backed a village moratorium but asked for revisions, and some worried about its effect on economic development.

Has anyone filed a lawsuit over the Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C)?

No lawsuit over Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C) appears in the record we track as of October 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C) use?

No water withdrawal figure for Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C), and how big is it?

Turin Hoefler Avenue LLC is the operator on record. Capacity on record is 200 MW. The site is recorded at 7.837 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Turin Hoefler Avenue AI Data Center (former Remington Arms plant, Site C)," updated October 26, 2026, https://suedatacenters.org/data-centers/turin-hoefler-ilion-ny.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/turin-hoefler-ilion-ny, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.250,000-Square-Foot AI Data Center Planned for Ilion's Remington Site C · WKTV · retrieved September 9, 2026
  2. 2.Updates on the Cloud: More Moratoriums on Data Centers · Rockefeller Institute of Government · retrieved October 26, 2026
  3. 3.Ilion data center moratorium vote tabled · Spectrum News · retrieved October 26, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us