AWS Kline Township Data Center Campus is a proposed data center in Kline Township, Pennsylvania (Schuylkill County), operated by Amazon Web Services.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Amazon Web Services
- Facility type
- Data center
- Location
- Lofty Road, Kline Township, Schuylkill County, PA, 18245
- Coordinates
- 40.8700, -76.0216 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- PPL
- Cooling
- Hybrid
- Water use
- 0.115 million gallons a day, reported
- Jobs
- 500 permanent
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 17, 2026ProposedPreliminary and final land development plans remain under township review; Amazon requested an extension of the decision deadline to September 30, 2026 to address township professionals' comments. Source: The Shenandoah Sentinel
Opposition and litigation at this site
Nothing on record as of September 12, 2026. No lawsuit, organized opposition, or contested hearing over AWS Kline Township Data Center Campus in Kline Township, Schuylkill County, Pennsylvania appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
AWS representatives told the Kline Township planning commission the campus would cool on ambient air about 96% of the year and use water the remaining 4%. Stated permitted draw is 15,000 gallons per day domestic plus up to 100,000 gallons per day of non-contact cooling water, 115,000 gpd in total.
Notes on the record
Nine two-story data center buildings plus an administration building, a water building and a security building, totalling about 2.1-2.2 million sq ft, off Lofty Road near Route 309 and Interstate 81, across from van Hoekelen Greenhouses. Buildings stated as 'probably less than 80 feet' tall; first building completion expected 2028. Lofty Road is to be realigned near Route 309 with a new traffic light at Amazon's cost. Stated wages for the ~500 permanent roles are $80,000-$100,000, with about 90% requiring an associate degree or certificate.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Land area
- How the community has received it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Project Hazelnut · Hazle Township · NorthPoint Development (NP Hazleton Holdings 1 LLC)9 mi · Proposed · In litigation
- Panther Creek HPC/AI Data Center Campus · Nesquehoning · Bitfarms Ltd.10 mi · Under construction · 350 MW
- Panther Creek Plant · Nesquehoning · Bitfarms Ltd. (Keel Infrastructure Corp.)10 mi · Operating · 350 MW
- Nautilus Cryptomine - Building 1 · Berwick (Salem Township) · Talen Energy16 mi · Operating
- AWS Cumulus Data Center Campus, Salem Township · Salem Township · Amazon Web Services17 mi · Under construction · 960 MW · Mixed reception
- 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3) · Salem Township · 4-3 Glenbrook Group18 mi · Proposed · 3.5 GW
- QTS Salem Township Data Center Campus (Salem 2) · Salem Township · QTS Data Centers18 mi · Proposed
- Project Atlas Data Center Campus (South Whitehall Township) · South Whitehall Township · CDE Acquisitions, LLC30 mi · Proposed
Questions people ask about this site
Is there opposition to the AWS Kline Township Data Center Campus in Kline Township?
Nothing on record as of September 12, 2026. No lawsuit, organized opposition, or contested hearing over AWS Kline Township Data Center Campus in Kline Township, Schuylkill County, Pennsylvania appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the AWS Kline Township Data Center Campus?
No lawsuit over AWS Kline Township Data Center Campus appears in the record we track as of September 12, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does AWS Kline Township Data Center Campus use?
0.115 million gallons a day is the reported figure on record. Cooling is recorded as hybrid. AWS representatives told the Kline Township planning commission the campus would cool on ambient air about 96% of the year and use water the remaining 4%.
Who operates AWS Kline Township Data Center Campus, and how big is it?
Amazon Web Services is the operator on record. We hold 54 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "AWS Kline Township Data Center Campus," updated September 12, 2026, https://suedatacenters.org/data-centers/aws-kline-township-schuylkill-pa.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aws-kline-township-schuylkill-pa, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Kline supervisors grant extension for consideration of Amazon data center plans · The Shenandoah Sentinel · retrieved September 12, 2026
- 2.Amazon Rep: Schuylkill County Data Centers Only Need Cooling Water 4% of the Year · Coal Region Canary · retrieved September 12, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us