Data Center Registry
4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3)
Salem Township, Luzerne County, Pennsylvania
4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3) is a proposed data center in Salem Township, Pennsylvania (Luzerne County), operated by 4-3 Glenbrook Group. The public record puts it at 3.5 GW planned, 4,000 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- 4-3 Glenbrook Group
- Facility type
- Data center
- Location
- Salem Township, Luzerne County, PA
- Coordinates
- 41.1078, -76.1791 (approximate)
- Power capacity
- 3.5 GW planned
- Land
- 4,000 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 22, 2026ProposedSalem Township Planning Commission recommended the zoning expansion; the Board of Supervisors decision was pending as of August 22, 2026. Source: Times Leader
Opposition and litigation at this site
Nothing on record as of September 12, 2026. No lawsuit, organized opposition, or contested hearing over 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3) in Salem Township, Luzerne County, Pennsylvania appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Referred to locally as 'Salem 3'. A 39-building campus (subject to change) assembled from more than 4,000 acres across roughly 194-200 landowners, with at least 80% of the assembled land intended to remain undeveloped green space. Stated potential power demand is roughly 3.5 to 4 gigawatts; capacityMw.planned records the lower bound of that published range. The group describes it as 'an energy and infrastructure development, not simply a data center development', with plans for an accompanying generation facility. Land-purchase figures are reported variously as a $1.2 billion deal and $1.4 billion in land purchases; because these are land prices rather than project investment, no investmentUsd is recorded. Coordinate is a township-centroid geocode shared with the separate QTS 'Salem 2' record.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- QTS Salem Township Data Center Campus (Salem 2) · Salem Township · QTS Data Centersunder 1 mile · Proposed
- AWS Cumulus Data Center Campus, Salem Township · Salem Township · Amazon Web Services2 mi · Under construction · 960 MW · Mixed reception
- Nautilus Cryptomine - Building 1 · Berwick (Salem Township) · Talen Energy2 mi · Operating
- Project Hazelnut · Hazle Township · NorthPoint Development (NP Hazleton Holdings 1 LLC)14 mi · Proposed · In litigation
- AWS Kline Township Data Center Campus · Kline Township · Amazon Web Services18 mi · Proposed
- Panther Creek HPC/AI Data Center Campus · Nesquehoning · Bitfarms Ltd.25 mi · Under construction · 350 MW
- Panther Creek Plant · Nesquehoning · Bitfarms Ltd. (Keel Infrastructure Corp.)25 mi · Operating · 350 MW
- Talen Energy Montour Data Center Campus · Washingtonville · Talen Energy26 mi · Proposed
Questions people ask about this site
Is there opposition to the 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3) in Salem Township?
Nothing on record as of September 12, 2026. No lawsuit, organized opposition, or contested hearing over 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3) in Salem Township, Luzerne County, Pennsylvania appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3)?
No lawsuit over 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3) appears in the record we track as of September 12, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3) use?
No water withdrawal figure for 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3), and how big is it?
4-3 Glenbrook Group is the operator on record. Capacity on record is 3.5 GW. The site is recorded at 4000 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3)," updated September 12, 2026, https://suedatacenters.org/data-centers/four-three-glenbrook-salem-township-luzerne-pa.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/four-three-glenbrook-salem-township-luzerne-pa, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.$1.2 billion land deal for second data center project in Salem Township announced by 4-3 Group · Times Leader · retrieved September 12, 2026
- 2.Developers tout impacts of 3 data center campuses; Zoning meeting set for Wednesday on 4-3 Glenbrook Group project · Times Leader · retrieved September 12, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us