Data Center Registry
Nautilus Cryptomine - Building 1
Berwick (Salem Township), Luzerne County, Pennsylvania · All 2 Talen Energy sites
Nautilus Cryptomine - Building 1 is an operating crypto mining site in Berwick (Salem Township), Pennsylvania (Luzerne County), operated by Talen Energy.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Talen Energy
- Facility type
- Crypto mining
- Location
- Berwick (Salem Township), Luzerne County, PA
- Coordinates
- 41.0826, -76.1514 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Nautilus Cryptomine - Building 1 in Berwick (Salem Township), Luzerne County, Pennsylvania appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
TeraWulf began mining at the facility in February 2023 and deployed its full share of phase one, 50 MW, in April 2023 (TeraWulf, March 2024); that is TeraWulf's share of a joint venture, not a total for the facility. TeraWulf's March 2024 release said a further 50 MW was expected to come online in 2025; as of October 2026 no source found confirms it did. World Nuclear News reported 2021 plans of 180 MW for phase one and up to 300 MW overall, so no capacity is recorded. Bitcoin mining facility co-located at Susquehanna nuclear plant, powered behind-the-meter. Originally a TeraWulf/Talen joint venture; Talen acquired full ownership Oct 2024. As of October 2026, the cited Baxtel page describes one facility at 769 Salem Blvd, and a second building is not listed separately here. The map pin is the center of an OpenStreetMap building named Nautilus Cryptomine, last edited in April 2026; as of October 2026 neither OpenStreetMap's Nominatim geocoder nor the US Census geocoder resolves the Baxtel address, so the pin is marked approximate.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- AWS Cumulus Data Center Campus, Salem Township · Salem Township · Amazon Web Servicesunder 1 mile · Under construction · 960 MW · Mixed reception
- 4-3 Glenbrook Group Salem Township Data Center Campus (Salem 3) · Salem Township · 4-3 Glenbrook Group2 mi · Proposed · 3.5 GW
- QTS Salem Township Data Center Campus (Salem 2) · Salem Township · QTS Data Centers2 mi · Proposed
- Project Hazelnut · Hazle Township · NorthPoint Development (NP Hazleton Holdings 1 LLC)12 mi · Proposed · In litigation
- AWS Kline Township Data Center Campus · Kline Township · Amazon Web Services16 mi · Proposed
- Panther Creek HPC/AI Data Center Campus · Nesquehoning · Bitfarms Ltd.23 mi · Under construction · 350 MW
- Panther Creek Plant · Nesquehoning · Bitfarms Ltd. (Keel Infrastructure Corp.)23 mi · Operating · 350 MW
- Talen Energy Montour Data Center Campus · Washingtonville · Talen Energy27 mi · Proposed
Questions people ask about this site
Is there opposition to the Nautilus Cryptomine - Building 1 data center in Berwick (Salem Township)?
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Nautilus Cryptomine - Building 1 in Berwick (Salem Township), Luzerne County, Pennsylvania appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Nautilus Cryptomine - Building 1 data center?
No lawsuit over Nautilus Cryptomine - Building 1 appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Nautilus Cryptomine - Building 1 use?
No water withdrawal figure for Nautilus Cryptomine - Building 1 is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Nautilus Cryptomine - Building 1, and how big is it?
Talen Energy is the operator on record. We hold 2 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Nautilus Cryptomine - Building 1," updated October 28, 2026, https://suedatacenters.org/data-centers/nautilus-cryptomine-building-1-pa.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/nautilus-cryptomine-building-1-pa, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Baxtel data center directory + DCD reporting on Talen's full acquisition of Nautilus Cryptomine (Oct 2024) · Baxtel · retrieved July 22, 2026
- 2.OpenStreetMap way/1334234454 · OpenStreetMap · retrieved July 22, 2026
- 3.TeraWulf Reaffirms Business as Usual at the Nautilus Facility Amid Talen's Sale of Data Center Campus (March 4, 2024) · TeraWulf Inc. · retrieved October 27, 2026
- 4.US companies announce plans for nuclear-powered bitcoin mine (August 4, 2021) · World Nuclear News · retrieved October 27, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.