Data Center Registry
NE Edge Killingly Data Center (125 Alexander Parkway)
Killingly, Windham County, Connecticut · All 2 NE Edge sites
NE Edge Killingly Data Center (125 Alexander Parkway) is a proposed data center in Killingly, Connecticut (Windham County), operated by NE Edge LLC.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- NE Edge LLC
- Facility type
- Data center
- Location
- 125 Alexander Parkway, Killingly, Windham County, CT, 06233
- Coordinates
- 41.8703, -71.8965 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- 80 permanent; 1,500 construction
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 24, 2023ProposedKillingly approved sale of the 125 Alexander Parkway parcel to NE Edge for $5 million on August 8; NE Edge also intends to develop two adjacent parcels Source: Baxtel
Opposition and litigation at this site
Nothing on record as of October 19, 2026. No lawsuit, organized opposition, or contested hearing over NE Edge Killingly Data Center (125 Alexander Parkway) in Killingly, Windham County, Connecticut appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Jobs: the source gives 80-100 long-term and 1,500-2,000 construction jobs; the lower bounds are recorded. No post-2023 evidence of closing or construction was found, and NE Edge's other CT sites (Waterford, Groton, Bozrah) did not proceed, so treat the status as unverified.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Hanton City Business Park (data center anchor) · Smithfield · Hanton City Investments LLC19 mi · Proposed · Opposed
- Brightstar Lottery Enterprise Data Center (West Greenwich) · West Greenwich · Brightstar Lottery PLC22 mi · Operating
- Providence RI2 (former Crown Castle Fiber / Lightower), 300 Carpenter St · Providence · Zayo (formerly Crown Castle Fiber)24 mi · Operating
- Prov.net 1155 Westminster St · Providence · Provdotnet LLC24 mi · Operating
- Lumen Providence (375 Promenade St) · Providence · Lumen Technologies24 mi · Operating
- Providence RI1 (former Crown Castle Fiber / Lightower), The Foundry, 235 Promenade St · Providence · Zayo (formerly Crown Castle Fiber)25 mi · Operating
- Amazon Data Services Grafton · Grafton · Amazon Data Services28 mi · Proposed
- ReNew Amston Data Center Campus (42 Old Amston Road) · Colchester · ReNew Developers30 mi · Proposed · 10 MW · Contested
Questions people ask about this site
Is there opposition to the NE Edge Killingly Data Center (125 Alexander Parkway) in Killingly?
Nothing on record as of October 19, 2026. No lawsuit, organized opposition, or contested hearing over NE Edge Killingly Data Center (125 Alexander Parkway) in Killingly, Windham County, Connecticut appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the NE Edge Killingly Data Center (125 Alexander Parkway)?
No lawsuit over NE Edge Killingly Data Center (125 Alexander Parkway) appears in the record we track as of October 19, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does NE Edge Killingly Data Center (125 Alexander Parkway) use?
No water withdrawal figure for NE Edge Killingly Data Center (125 Alexander Parkway) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates NE Edge Killingly Data Center (125 Alexander Parkway), and how big is it?
NE Edge LLC is the operator on record. We hold 2 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "NE Edge Killingly Data Center (125 Alexander Parkway)," updated October 19, 2026, https://suedatacenters.org/data-centers/ne-edge-killingly-ct.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/ne-edge-killingly-ct, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.NE Edge purchases a parcel of land in Connecticut (Killingly, 125 Alexander Parkway) · Baxtel · retrieved October 19, 2026
- 2.OpenStreetMap Nominatim geocode, Alexander Parkway, Killingly, CT (street-level) · OpenStreetMap · retrieved October 19, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us