Sue Data Centers

Data Center Registry

Lambda MidAmerica Industrial Park Data Center

Chouteau, Mayes County, Oklahoma · All 4 Lambda sites

ProposedNo reception on recordAI confirmedRecord updated October 9, 2026

Lambda MidAmerica Industrial Park Data Center is a proposed data center in Chouteau, Oklahoma (Mayes County), operated by Lambda. The public record puts it at announced September 27, 2026.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Lambda
Facility type
Data center, AI use confirmed
Location
Chouteau, Mayes County, OK
Coordinates
36.1859, -95.3430 (approximate)
Power capacity
Not established from a public source
Land
Not established from a public source
Investment
Not established from a public source
Announced
September 27, 2026
Utility
Grand River Dam Authority (GRDA)
Cooling
Closed loop
Water use
Not established from a public source
Jobs
100 permanent; 1,000 construction
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 27, 2026
    Proposed
    Lambda announces plans to build a data center in the south section of MidAmerica Industrial Park; no construction start, completion date or total cost announced. Source: Lambda

Opposition and litigation at this site

Nothing on record as of October 9, 2026. No lawsuit, organized opposition, or contested hearing over Lambda MidAmerica Industrial Park Data Center in Chouteau, Mayes County, Oklahoma appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Lambda states it will pay 100% of the facility's energy costs and fund upfront infrastructure to serve the project, and plans to be a flexible grid customer able to shift or reduce certain loads during peak demand.

Notes on the record

Lambda announced plans on 2026-09-27 for a data center in the south section of MidAmerica Industrial Park, Mayes County, within the Chouteau-Mazie Public School District tax boundary. Capacity, GPU count, acreage, street address, timeline and total cost are not stated in the sources. The park was selected through a 'reverse RFP' by MidAmerica Industrial Park; Grand River Dam Authority (GRDA) is the power provider and Lambda is to fund the upfront infrastructure needed to serve the project; Cloverleaf Infrastructure was selected by GRDA and MidAmerica to ready the site. Lambda says it will pay 100% of the facility's energy costs and plans to act as a flexible grid customer. Company-stated figures: up to 1,000 construction jobs, up to 100 permanent positions, about $500M in tax revenue over ten years at current rates. Separate from Google's existing Pryor campus (google-pryor-ok), also in Mayes County. Coordinates are the Chouteau city point (OSM Nominatim), not the site; the sources give no parcel or address.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Land area
  • How the community has received it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Lambda MidAmerica Industrial Park Data Center?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Lambda MidAmerica Industrial Park Data Center in Chouteau?

Nothing on record as of October 9, 2026. No lawsuit, organized opposition, or contested hearing over Lambda MidAmerica Industrial Park Data Center in Chouteau, Mayes County, Oklahoma appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Lambda MidAmerica Industrial Park Data Center?

No lawsuit over Lambda MidAmerica Industrial Park Data Center appears in the record we track as of October 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Lambda MidAmerica Industrial Park Data Center use?

No water withdrawal figure for Lambda MidAmerica Industrial Park Data Center is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Lambda MidAmerica Industrial Park Data Center, and how big is it?

Lambda is the operator on record. We hold 4 sites for that company across the registry. No capacity figure is on record for this site.

How to cite this page

SueDataCenters.org Data Center Registry, "Lambda MidAmerica Industrial Park Data Center," updated October 9, 2026, https://suedatacenters.org/data-centers/lambda-midamerica-industrial-park-chouteau-ok.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/lambda-midamerica-industrial-park-chouteau-ok, retrieved October 11, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.New Lambda data center in Oklahoma · Lambda · retrieved October 9, 2026
  2. 2.AI cloud company plans data center in Mayes County · KOKH FOX 25 · retrieved October 9, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us