Google Pryor Data Center Campus (Mayes County Expansion)
Pryor, Mayes County, Oklahoma · All 53 Google sites · Every Google case on our tracker
Google Pryor Data Center Campus (Mayes County Expansion) is an operating data center in Pryor, Oklahoma (Mayes County), operated by Google. The public record puts it at announced January 2007, a reported $4.4 billion investment. It has documented support and documented opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Facility type
- Data center, AI use mixed
- Location
- Pryor, Mayes County, OK
- Coordinates
- 36.3200, -95.3100
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- $4.4 billion
- Announced
- January 2007
- Utility
- Grid (Southwest Power Pool) with renewable PPAs
- Power source
- Grid
- Cooling
- Evaporative
- Water use
- 3 million gallons a day, reported
- Jobs
- Not established from a public source
- Public subsidy
- Oklahoma ad valorem manufacturing exemption (5-year property-tax exemption on data-center equipment), $45.9M in 2021 alone (largest single-year benefit; amountUsd reflects this 2021 figure); ~$239M reimbursed cumulatively over ~a decade for the Mayes County facility; existing qualifying equipment retains the exemption to 2036 under SB 609 (2021), Mayes County, OK, 2021
- Community reception
- Mixed reception
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 2025OperatingNew expansion announced as part of Google's $9B, two-year Oklahoma investment commitment. Source: Data Center Dynamics
- January 2011OperatingCampus opens in Mayes County after first announcement in 2007. Has undergone three expansions since opening. Source: Data Center Dynamics
Opposition and litigation at this site
Partly. Both documented support and documented opposition to Google Pryor Data Center Campus (Mayes County Expansion) in Pryor, Mayes County, Oklahoma appear in the record, with no clear majority position. Strong official support, Pryor Mayor Zac Doyle: Google has brought "hundreds of jobs, economic growth, and billions in investment" and supports local schools and nonprofits.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.
Strong official support, Pryor Mayor Zac Doyle: Google has brought "hundreds of jobs, economic growth, and billions in investment" and supports local schools and nonprofits. Google reports more than 800 jobs created to date in Pryor and $4.4 billion invested in Mayes County to date (company-provided figures via The Frontier). Grassroots and state-level concerns are documented: local hiring practices, rising housing costs, and heavy water use (>1.1B gal/yr); the Oklahoma Water Resources Board warned (Oct 2025) that data centers "will contribute to the strain" on water supply. Subsidy scale also criticized: ~$239M ad valorem for this facility, plus $113.9M in income-tax credits Google has claimed statewide since 2017.
Power and water
Google's second-largest data center campus in the world. Oklahoma wind generates ~42% of in-state electricity. New expansion announced as part of $9B Oklahoma investment (August 2025). Google has invested $5.7B+ in Oklahoma historically (prior to August 2025 $9B commitment).
Utility records (open-records request) show the Pryor center used more than 1.1 billion gallons Jul 2024-Jun 2025 (≈3.0 MGD, a floor) from the Neosho River via the state-owned MidAmerica Industrial Park; ~253M gallons were discharged back to the river, the remainder lost to evaporative cooling. Google was the park's second-largest water user that year.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Oklahoma ad valorem manufacturing exemption (5-year property-tax exemption on data-center equipment), $45.9M in 2021 alone (largest single-year benefit; amountUsd reflects this 2021 figure); ~$239M reimbursed cumulatively over ~a decade for the Mayes County facility; existing qualifying equipment retains the exemption to 2036 under SB 609 (2021) | $46 million | Mayes County, OK | 2021 |
Notes on the record
Campus operational since 2011; Google's second-largest data center globally per Alphabet CIO Ruth Porat. Four expansions now underway. $5.7B+ invested historically in Oklahoma prior to August 2025 $9B commitment. Expansion capacity and MW not publicly specified. Coordinates are Pryor city center.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Permanent jobs promised
- Land area
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Northern Data North American Operational Center (Pryor), cancelled · Pryor · Northern Data AG2 mi · Cancelled
- Potentia Oklahoma Campus 02 (Inola) · Inola · Potentia, Inc.16 mi · Proposed · 2 GW · Mixed reception
- Project Mustang · Claremore · Beale Infrastructure17 mi · Proposed
- Project Clydesdale · Owasso · Beale Infrastructure29 mi · Under construction · Supported
Questions people ask about this site
Is there opposition to the Google Pryor Data Center Campus (Mayes County Expansion) in Pryor?
Partly. Both documented support and documented opposition to Google Pryor Data Center Campus (Mayes County Expansion) in Pryor, Mayes County, Oklahoma appear in the record, with no clear majority position. Strong official support, Pryor Mayor Zac Doyle: Google has brought "hundreds of jobs, economic growth, and billions in investment" and supports local schools and nonprofits.
Has anyone filed a lawsuit over the Google Pryor Data Center Campus (Mayes County Expansion)?
No lawsuit over Google Pryor Data Center Campus (Mayes County Expansion) appears in the record we track as of July 6, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Google Pryor Data Center Campus (Mayes County Expansion) use?
3 million gallons a day is the reported figure on record. Cooling is recorded as evaporative. Utility records (open-records request) show the Pryor center used more than 1.1 billion gallons Jul 2024-Jun 2025 (≈3.0 MGD, a floor) from the Neosho River via the state-owned MidAmerica Industrial Park; ~253M gallons were discharged back to the river, the remainder lost to evaporative cooling.
Who operates Google Pryor Data Center Campus (Mayes County Expansion), and how big is it?
Google is the operator on record. We hold 53 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Google Pryor Data Center Campus (Mayes County Expansion)," updated July 6, 2026, https://suedatacenters.org/data-centers/google-pryor-ok.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/google-pryor-ok, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Google planning another expansion for Pryor data center · Oklahoma Department of Commerce · retrieved July 6, 2026
- 2.Google to invest $9B in cloud and AI infrastructure in Oklahoma · Data Center Dynamics · retrieved July 6, 2026
- 3.As data centers boom in Oklahoma, so does water demand · The Frontier · retrieved July 6, 2026
- 4.Oklahoma lawmakers tried to cut a costly data-center incentive, but gave Google a break · The Frontier · retrieved July 6, 2026
- 5.Google announces support for local schools and nonprofits · Pryor Information Publication · retrieved July 6, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us