Data Center Registry
Blueprint Data Centers Georgetown
Georgetown, Williamson County, Texas · All 2 Blueprint Data Centers sites
Blueprint Data Centers Georgetown is a proposed data center in Georgetown, Texas (Williamson County), operated by Blueprint Data Centers. The public record puts it at 25 MW planned.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Blueprint Data Centers
- Facility type
- Data center
- Location
- Georgetown, Williamson County, TX
- Coordinates
- 30.6370, -97.6776 (approximate)
- Power capacity
- 25 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- 10-year, 50% property tax abatement, 2025
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 2025Proposed25 MW facility with committed utility power, scheduled to be energized by 2026. Source: Converge Digest
Opposition and litigation at this site
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Blueprint Data Centers Georgetown in Georgetown, Williamson County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| 10-year, 50% property tax abatement | Not established | Not established | 2025 |
Notes on the record
Part of Blueprint's 85 MW, two-site Austin-area plan. As of October 2026, Blueprint's own site lists the Georgetown energization timeline as 2026 and 2027, later than the "energized by 2026" in the August 2025 announcement. Coordinates are the Georgetown city point. The abatement jurisdiction is not named in the source.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Sabey SDC Austin (Round Rock) · Round Rock · Sabey Data Centers9 mi · Operating · 84 MW
- Skybox PowerCampus Austin (Hutto) · Hutto · Skybox Datacenters (with Prologis)10 mi · Under construction · 600 MW
- Switch: The Rock (Round Rock) · Round Rock · Switch10 mi · Under construction · 185 MW
- Blueprint Data Centers Taylor · Taylor · Blueprint Data Centers16 mi · Proposed · 60 MW
- Iron Mountain Williamson County Data Center Campus · Iron Mountain16 mi · Proposed
- Cosmos Technology Campus (former 3M campus) · Austin · SB Energy19 mi · Under construction · 50 MW
- Element Critical Austin One · Austin · Element Critical20 mi · Operating · 5 MW
- Lumen Austin 3 · Austin · Lumen Technologies26 mi · Operating
Questions people ask about this site
Is there opposition to the Blueprint Data Centers Georgetown data center in Georgetown?
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Blueprint Data Centers Georgetown in Georgetown, Williamson County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Blueprint Data Centers Georgetown data center?
No lawsuit over Blueprint Data Centers Georgetown appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Blueprint Data Centers Georgetown use?
No water withdrawal figure for Blueprint Data Centers Georgetown is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Blueprint Data Centers Georgetown, and how big is it?
Blueprint Data Centers is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 25 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Blueprint Data Centers Georgetown," updated October 28, 2026, https://suedatacenters.org/data-centers/blueprint-georgetown-tx.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/blueprint-georgetown-tx, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Blueprint Data Centers plans 85MW Austin expansion, energized by 2026 · Converge Digest · retrieved October 14, 2026
- 2.OpenStreetMap Nominatim geocode: Georgetown, TX · OpenStreetMap contributors · retrieved October 14, 2026
- 3.Blueprint Data Centers: Taylor DC and Georgetown DC project listings · Blueprint Data Centers · retrieved October 28, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us