Data Center Registry
Foristell I-70 Data Center Site (216-acre annexation)
Foristell, Warren County, Missouri
Foristell I-70 Data Center Site (216-acre annexation) is a proposed data center in Foristell, Missouri (Warren County), operated by Undisclosed developer. The public record puts it at announced January 5, 2026, 216 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Undisclosed developer
- Facility type
- Data center
- Location
- North outer road of I-70, Foristell, Warren County, MO
- Coordinates
- 38.8151, -90.9560 (approximate)
- Power capacity
- Not established from a public source
- Land
- 216 acres
- Investment
- Not established from a public source
- Announced
- January 5, 2026
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- January 5, 2026ProposedForistell Board of Aldermen took up annexation of ~216 acres of unincorporated Warren County (three parcels on the I-70 north outer road) as a first step toward a data center. No formal data center application had been filed. Source: GovTech / St. Louis Post-Dispatch
Opposition and litigation at this site
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Foristell I-70 Data Center Site (216-acre annexation) in Foristell, Warren County, Missouri appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Out-of-state firms representing two unnamed data center developers contacted Foristell in May 2025. This record is the ~216-acre annexation site: R&R Holdings 95 ac, H. M. Boegeman Realty Co. 89 ac, Longhorn Property Management 32 ac, zoned agricultural in Warren County on the north outer road of I-70. A second ~240-acre site south of I-70, east of the American Food Groups plant, already inside city limits, is NOT recorded. The city refused to sign NDAs. No developer, end user or capacity is disclosed. As of October 2026, no fetched source states the annexation vote outcome. Minutes of the Board of Aldermen's April 20, 2026 meeting record a resident saying the data center "pulled out on the north site" (the minutes do not confirm this) and a vote, decided by the board president's tie-break, to refer a data center moratorium to the Planning & Zoning Commission. Coordinates are the Foristell town centroid (approximate).
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Crusoe Warrenton Campus · Warrenton · Crusoe10 mi · Permitted · Mixed reception
- Cloverleaf Troy Campus · Troy · Cloverleaf Infrastructure11 mi · Proposed · 500 MW
- Diamond Farms (Gateway Digital Campus) · Villa Ridge · Provident Data Centers24 mi · Permitted
- Project Cumulus (St. Charles) · St. Charles · CRG Cumulus (CRG, Clayco's development arm)26 mi · Cancelled · Opposed
- Meramec Valley Technology Park (Beltline Energy) · Beltline Energy (BLE Landholdings, LLC)28 mi · Permitted · Contested
- Google Project Spade Campus · New Florence · Google30 mi · Under construction · 1.2 GW · In litigation
Questions people ask about this site
Is there opposition to the Foristell I-70 Data Center Site (216-acre annexation) in Foristell?
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Foristell I-70 Data Center Site (216-acre annexation) in Foristell, Warren County, Missouri appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Foristell I-70 Data Center Site (216-acre annexation)?
No lawsuit over Foristell I-70 Data Center Site (216-acre annexation) appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Foristell I-70 Data Center Site (216-acre annexation) use?
No water withdrawal figure for Foristell I-70 Data Center Site (216-acre annexation) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Foristell I-70 Data Center Site (216-acre annexation), and how big is it?
Undisclosed developer is the operator on record. No capacity figure is on record for this site. The site is recorded at 216 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Foristell I-70 Data Center Site (216-acre annexation)," updated October 28, 2026, https://suedatacenters.org/data-centers/foristell-i70-annexation-data-center-site-mo.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/foristell-i70-annexation-data-center-site-mo, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Two data centers eye land near St. Charles County, Mo. (St. Louis Post-Dispatch via TNS) · GovTech / St. Louis Post-Dispatch · retrieved October 13, 2026
- 2.OpenStreetMap Nominatim geocode: Foristell, Missouri · OpenStreetMap · retrieved October 13, 2026
- 3.City of Foristell Board of Aldermen meeting minutes, April 20, 2026 · City of Foristell · retrieved October 28, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us