Data Center Registry
Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe)
Wharncliffe, Mingo County, West Virginia · All 2 TransGas Development Systems sites
Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe) is a proposed data center in Wharncliffe, West Virginia (Mingo County), operated by TransGas Development Systems.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- TransGas Development Systems
- Facility type
- Data center
- Location
- Wharncliffe, Mingo County, WV
- Coordinates
- 37.6412, -81.9689 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of September 13, 2026. No lawsuit, organized opposition, or contested hearing over Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe) in Wharncliffe, Mingo County, West Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Proposed at the former Twisted Gun Golf Course site in Wharncliffe, Mingo County, to be powered exclusively by the co-located off-grid natural-gas plant (tracked separately as of September 2026 as the Adams Fork Energy Campus Power Plant, Twisted Gun Golf Course, Wharncliffe; WV DEP permit R13-3714, approved October 2, 2025). No data-center-specific capacity, investment, or job figures distinct from the power plant were found as of 2026-09-10; reporting describes the plant and data center as a single 'energy campus' without separately quantifying the data center building. Part of TransGas's larger 'Adams Fork Energy' project alongside a proposed large natural-gas ammonia plant. The record is marked reported rather than confirmed (as of 2026-09-10): the WV DEP permit numbers and their 2025-10-02 approval are reported consistently by two independent organisations, but the permit documents themselves (R13-3714 and R13-3715) could not be retrieved from dep.wv.gov as of September 2026, so the sourcing is advocacy-group reporting rather than the primary record.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Adams Fork Energy Campus Data Center (Harless Industrial Park, Holden) · Holden · TransGas Development Systems12 mi · Proposed
- Blockware Solutions Pike County Facility · Belfry · Blockware Solutions21 mi · Operating · 30 MW
Questions people ask about this site
Is there opposition to the Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe) in Wharncliffe?
Nothing on record as of September 13, 2026. No lawsuit, organized opposition, or contested hearing over Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe) in Wharncliffe, Mingo County, West Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe)?
No lawsuit over Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe) appears in the record we track as of September 13, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe) use?
No water withdrawal figure for Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe), and how big is it?
TransGas Development Systems is the operator on record. We hold 2 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Adams Fork Energy Campus Data Center (Twisted Gun Golf Course, Wharncliffe)," updated September 13, 2026, https://suedatacenters.org/data-centers/adams-fork-wharncliffe-datacenter-mingo-county-wv.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/adams-fork-wharncliffe-datacenter-mingo-county-wv, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Despite public pushback, West Virginia approves air quality permits for data center energy campus in Mingo County · West Virginia Highlands Conservancy · retrieved September 13, 2026
- 2.Adams Fork is a Giant Waste of Energy · Ohio River Valley Institute · retrieved September 10, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us