Sue Data Centers

Data Center Registry

Nautilus Stockton 1 Data Center

Stockton, San Joaquin County, California · All 2 Nautilus Data Technologies sites

OperatingNo reception on recordRecord updated September 21, 2026

Nautilus Stockton 1 Data Center is an operating data center in Stockton, California (San Joaquin County), operated by Nautilus Data Technologies. The public record puts it at 6.5 MW operating.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
Nautilus Data Technologies
Facility type
Data center
Location
Stockton, San Joaquin County, CA
Coordinates
37.9633, -121.3681 (approximate)
Power capacity
6.5 MW operating
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Closed loop
Water use
Not established from a public source
Jobs
10 permanent
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. January 2021
    Operating
    Commissioned December 2020; operating since January 2021 and at full capacity since 2023 (about 88% utilised as of June 2026). Source: Stocktonia News

Opposition and litigation at this site

Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over Nautilus Stockton 1 Data Center in Stockton, San Joaquin County, California appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Waterborne barge facility moored in the northwest area of the Port of Stockton's West complex. The operator describes a primary/secondary heat-exchanger design whose primary side is an open loop that takes in, filters and discharges water from the San Joaquin River.

Notes on the record

6.5 MW of critical IT load across four vaults (1.0 to 2.5 MW each) in roughly 13,000 sq ft of vault space. Coordinates are the project coordinates printed on the CEQA Notice of Determination (37°57'48"N 121°22'5"W), not a surveyed footprint.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Free case review

Living near Nautilus Stockton 1 Data Center?

Tell us the basics and an independent attorney handling data center cases in your state will follow up. Free, and you are never obligated to hire anyone.

Questions people ask about this site

Is there opposition to the Nautilus Stockton 1 Data Center in Stockton?

Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over Nautilus Stockton 1 Data Center in Stockton, San Joaquin County, California appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Nautilus Stockton 1 Data Center?

No lawsuit over Nautilus Stockton 1 Data Center appears in the record we track as of September 21, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Nautilus Stockton 1 Data Center use?

No water withdrawal figure for Nautilus Stockton 1 Data Center is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Nautilus Stockton 1 Data Center, and how big is it?

Nautilus Data Technologies is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 6.5 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Nautilus Stockton 1 Data Center," updated September 21, 2026, https://suedatacenters.org/data-centers/nautilus-stockton-1-ca.

Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/nautilus-stockton-1-ca, retrieved October 1, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Stockton Data Center, Nautilus Data Technologies · Nautilus Data Technologies · retrieved September 21, 2026
  2. 2.Stockton residents push back on data centers. The city already relies on one · Stocktonia News · retrieved September 14, 2026
  3. 3.Nautilus Data Technology, Inc., Data Storage Facility, Notice of Determination (SCH 2016062010) · California Governor's Office of Land Use and Climate Innovation (CEQAnet) · retrieved September 14, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us