Data Center Registry
The STEM Practice Sycamore View AI Data Center
Memphis, Shelby County, Tennessee
The STEM Practice Sycamore View AI Data Center is a data center under construction in Memphis, Tennessee (Shelby County), operated by Golden Acquisitions / The STEM Practice.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Golden Acquisitions / The STEM Practice
- Facility type
- Data center, AI use confirmed
- Location
- 1341 Sycamore View Road, Memphis, Shelby County, TN
- Coordinates
- 35.1616, -89.8597
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of September 13, 2026. No lawsuit, organized opposition, or contested hearing over The STEM Practice Sycamore View AI Data Center in Memphis, Shelby County, Tennessee appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Reported 2026-01-13: 'Nate Golden of Golden Acquisitions' is purchasing the building at 1341 Sycamore View and working with The STEM Practice, described as 'a tech company that works with Oracle,' to build a modular AI data center ('will be modular instead' of a hyperscale build like xAI's Colossus). Timeline per the source: 'the plan is to have part of the data center running by May 1.' A secondary aggregator (datacentermap.com, rate-limited/not independently fetched this run) reports ~9MW at full build-out, 38,500 sq ft across a 4-story redevelopment on a 1.5-acre parcel, and states this is one of four planned STEM Practice sites in Tennessee -- those figures and the multi-site claim are omitted pending a directly-fetched primary source. Coordinates are an OSM-mapped building way at the exact street address.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- DataBank MEM1 (Memphis) · Memphis · DataBank4 mi · Operating · 0.45 MW
- 5C MEM01 Memphis (former Fred's headquarters) · Memphis · 5C Data Centers10 mi · Proposed · 15 MW
- Neural Nexus Innovation District · Memphis · Legacy Power Capital11 mi · Proposed · Mixed reception
- Colossus · Memphis · xAI11 mi · Operating · 1.2 GW · In litigation
- xAI Southaven · Southaven · xAI13 mi · Operating · 2 GW · In litigation
- Collierville Enterprise Data Center (FedEx World Technology Center Campus) · Collierville · Aphorio Carter14 mi · Operating
- Colossus 2 (Whitehaven) · Memphis · xAI15 mi · Operating
- Minihard · Memphis · xAI15 mi · Under construction
Questions people ask about this site
Is there opposition to the The STEM Practice Sycamore View AI Data Center in Memphis?
Nothing on record as of September 13, 2026. No lawsuit, organized opposition, or contested hearing over The STEM Practice Sycamore View AI Data Center in Memphis, Shelby County, Tennessee appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the The STEM Practice Sycamore View AI Data Center?
No lawsuit over The STEM Practice Sycamore View AI Data Center appears in the record we track as of September 13, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does The STEM Practice Sycamore View AI Data Center use?
No water withdrawal figure for The STEM Practice Sycamore View AI Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates The STEM Practice Sycamore View AI Data Center, and how big is it?
Golden Acquisitions / The STEM Practice is the operator on record. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "The STEM Practice Sycamore View AI Data Center," updated September 13, 2026, https://suedatacenters.org/data-centers/stem-practice-sycamore-view-memphis-tn.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/stem-practice-sycamore-view-memphis-tn, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Another AI data center coming to Memphis, sources say · Action News 5 (WMC) · retrieved September 13, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us