Core Scientific Muskogee Campus
Muskogee, Muskogee County, Oklahoma · All 10 Core Scientific sites
Core Scientific Muskogee Campus is a data center under construction in Muskogee, Oklahoma (Muskogee County), operated by Core Scientific. The public record puts it at 1 GW planned, 250 acres, a reported $4 billion investment. It has documented public support and no documented opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Core Scientific
- Facility type
- Data center, AI use confirmed
- Location
- Muskogee, Muskogee County, OK
- Coordinates
- 35.7200, -95.4200
- Power capacity
- 70 MW operating; 1 GW planned
- Land
- 250 acres
- Investment
- $4 billion
- Announced
- Not established from a public source
- Utility
- OG&E (Oklahoma Gas & Electric)
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- 150 permanent
- Public subsidy
- Not established from a public source
- Community reception
- Supported
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 2026Under constructionSecond 82.5MW building under construction; expansion plan targets ~1.5GW gross power (~1.0GW leasable), including a pending acquisition of Polaris DS LLC (440MW OG&E contract). Source: Core Scientific (investor release)
- April 2026OperatingInitial 100MW (70MW critical IT) phase delivered Q2 2026. Source: Core Scientific (investor release)
Opposition and litigation at this site
Not that we can document. Local officials or residents have expressed public support for Core Scientific Muskogee Campus in Muskogee, Muskogee County, Oklahoma, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Oklahoma Governor Stitt is quoted (2026-05-06 release) praising the expansion and the state's behind-the-meter legislation as enabling it.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.
Oklahoma Governor Stitt is quoted (2026-05-06 release) praising the expansion and the state's behind-the-meter legislation as enabling it. No resident opposition, hearings, or independent local-news coverage was checked -- this reflects state-official/company-sourced reaction only, from the operator's own press release.
Power and water
Grid power via OG&E is the defining arrangement. Core Scientific's Muskogee campus (the 100MW CoreWeave-anchor HPC facility, ~70MW critical IT load) and the adjacent Polaris DS acquisition are both served by OG&E electric service agreements totaling up to 440MW gross power under contract.
Notes on the record
1525 W Smith Ferry Rd, Port Muskogee Industrial Park. Distinct from the existing tracked Google Muskogee County campuses - same county, different developer/site. Coordinates are approximate. CoreWeave is the anchor customer.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Polaris Technologies Muskogee Bitcoin Mining Facility ("Project Bifrost") · Muskogee · Polaris Technologies, Inc.3 mi · Operating · 400 MW · Mixed reception
- Google Muskogee County Data Center Campuses · Council Hill · Google17 mi · Proposed · Supported
- Project Atlas (Coweta), withdrawn · Coweta · Beale Infrastructure21 mi · Cancelled
Questions people ask about this site
Is there opposition to the Core Scientific Muskogee Campus in Muskogee?
Not that we can document. Local officials or residents have expressed public support for Core Scientific Muskogee Campus in Muskogee, Muskogee County, Oklahoma, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Oklahoma Governor Stitt is quoted (2026-05-06 release) praising the expansion and the state's behind-the-meter legislation as enabling it.
Has anyone filed a lawsuit over the Core Scientific Muskogee Campus?
No lawsuit over Core Scientific Muskogee Campus appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Core Scientific Muskogee Campus use?
No water withdrawal figure for Core Scientific Muskogee Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Core Scientific Muskogee Campus, and how big is it?
Core Scientific is the operator on record. We hold 10 sites for that company across the registry. Capacity on record is 1 GW. The site is recorded at 250 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Core Scientific Muskogee Campus," updated September 10, 2026, https://suedatacenters.org/data-centers/core-scientific-muskogee-ok.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/core-scientific-muskogee-ok, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Core Scientific Plans Expansion to 1.5 Gigawatts of Gross Power at Muskogee, Oklahoma Campus · Core Scientific (investor release) · retrieved July 9, 2026
- 2.Core Scientific and Port Muskogee Break Ground on 100 MW HPC Data Center (investor press release) · retrieved July 24, 2026
- 3.Core Scientific Plans Expansion to 1.5 Gigawatts of Gross Power at Muskogee, Oklahoma Campus · Business Wire · retrieved August 6, 2026
- 4.Core Scientific announces 440 MW expansion at Oklahoma site · Blockspace · retrieved August 6, 2026
- 5.Core Scientific plans expansion to 1.5 gigawatts of gross power at Muskogee, Oklahoma campus · retrieved September 10, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us