Sue Data Centers

Data Center Registry

Project Q, Quiet Data Centers Enfield (Halifax County)

Enfield, Halifax County, North Carolina

ProposedMixed receptionAI likelyRecord updated September 10, 2026

Project Q, Quiet Data Centers Enfield (Halifax County) is a proposed data center in Enfield, North Carolina (Halifax County), operated by Quiet Data Centers Halifax Inc. The public record puts it at announced November 2025, 88 MW planned, 251 acres, a reported $250 million investment. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Quiet Data Centers Halifax Inc.
Facility type
Data center, AI use likely
Location
Enfield, Halifax County, NC
Coordinates
36.1800, -77.6689 (approximate)
Power capacity
88 MW planned
Land
251 acres
Investment
$250 million
Announced
November 2025
Utility
Dominion
Power source
Grid
Cooling
Closed loop
Water use
0.0025 million gallons a day, reported
Jobs
50 permanent
Public subsidy
Not established from a public source
Community reception
Mixed reception
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. August 26, 2026
    Proposed
    Halifax County held a special meeting on the conveyance; property closing expected Sept. 18, 2026. Source: Rocky Mount / Roanoke Rapids Daily Herald

Opposition and litigation at this site

Partly. Both documented support and documented opposition to Project Q, Quiet Data Centers Enfield (Halifax County) in Enfield, Halifax County, North Carolina appear in the record, with no clear majority position. Halifax County Board of Commissioners held a public hearing on 2026-08-28 for the ~251-acre Enfield site ('Project Q').

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

Halifax County Board of Commissioners held a public hearing on 2026-08-28 for the ~251-acre Enfield site ('Project Q'). Genuinely mixed reception: Halifax Electric's CEO and residents raised rate-subsidization and low-frequency-noise concerns; Enfield Mayor Mondale Robinson and a Roanoke Rapids commissioner criticized the county for excluding the municipality from early wastewater talks and called the process 'backroom dealings' (the initial Nov. 3, 2025 property hearing did not disclose the buyer was a data-center company, citing economic-development confidentiality); other speakers were supportive or conditionally supportive, focused on local-hire commitments. No vote occurred at the hearing; closing was expected 2026-09-18. No wage/job guarantee was legally binding per the county attorney -- only a 'good-faith effort.'

Source

Power and water

Company said electricity would be sourced through Dominion, with the company covering transmission/substation costs and no rate subsidy from residential customers.

Developer described roughly 2,500 gallons per day in a closed-loop cooling system.

Notes on the record

County-owned 251-acre industrial site off Trestle Road near U.S. 301 outside Enfield; the data center campus itself is described as roughly 14 to 15 acres with a 90,000 to 100,000 sq ft building. Phase 1 about 38 MW, final about 88 MW. Minimum contractual commitment is a $250M taxable investment and 50 permanent jobs; the company said the eventual investment could approach $1 billion, that larger figure is aspirational, not committed.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Project Q, Quiet Data Centers Enfield (Halifax County) data center in Enfield?

Partly. Both documented support and documented opposition to Project Q, Quiet Data Centers Enfield (Halifax County) in Enfield, Halifax County, North Carolina appear in the record, with no clear majority position. Halifax County Board of Commissioners held a public hearing on 2026-08-28 for the ~251-acre Enfield site ('Project Q').

Has anyone filed a lawsuit over the Project Q, Quiet Data Centers Enfield (Halifax County) data center?

No lawsuit over Project Q, Quiet Data Centers Enfield (Halifax County) appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Project Q, Quiet Data Centers Enfield (Halifax County) use?

0.0025 million gallons a day is the reported figure on record. Cooling is recorded as closed_loop. Developer described roughly 2,500 gallons per day in a closed-loop cooling system.

Who operates Project Q, Quiet Data Centers Enfield (Halifax County), and how big is it?

Quiet Data Centers Halifax Inc. is the operator on record. Capacity on record is 88 MW. The site is recorded at 251 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Project Q, Quiet Data Centers Enfield (Halifax County)," updated September 10, 2026, https://suedatacenters.org/data-centers/quiet-data-centers-enfield-halifax-county-nc.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/quiet-data-centers-enfield-halifax-county-nc, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Data center proposal draws questions, concerns at public hearing · Rocky Mount / Roanoke Rapids Daily Herald · retrieved August 29, 2026
  2. 2.Data centers on hold: how each county in central NC is handling data center plans (Halifax County, 251-acre site, Quiet Data Centers) · WRAL · retrieved August 29, 2026
  3. 3.Data center proposal draws questions, concerns at public hearing · retrieved September 10, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us