Sue Data Centers

Data Center Registry

Columbus Bitcoin Mining Facility (formerly Greenidge Columbus)

Columbus, Lowndes County, Mississippi

OperatingNo reception on recordRecord updated September 14, 2026

Columbus Bitcoin Mining Facility (formerly Greenidge Columbus) is an operating crypto mining site in Columbus, Mississippi (Lowndes County), operated by LM Funding America, Inc. (Power & Compute). The public record puts it at announced March 11, 2024, 8.5 MW operating, a reported $1 million investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
LM Funding America, Inc. (Power & Compute)
Facility type
Crypto mining
Location
249 Datco Industrial Road, Columbus, Lowndes County, MS
Coordinates
33.4957, -88.4273 (approximate)
Power capacity
8.5 MW operating
Land
Not established from a public source
Investment
$1 million
Announced
March 11, 2024
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 2025
    Operating
    CORRECTION: this record currently describes Greenidge Generation's own project as cancelled/divested, but the 11 MW site itself did not go dark -- it changed hands and is operating. Greenidge sold the Columbus, MS facility (per this record's own existing SEC/Business Wire sources, closed on or about 2025-09-16/17); LM Funding America, Inc. (now rebranded 'Power & Compute') announced closing its acquisition of the same 11 MW site plus ~7.5 MW / 157 PH/s of operating hashrate (~2,300 Bitmain S19-series miners) on 2025-09-18 for $4.0M total consideration, at power pricing of ~$0.036/kWh, with stated plans to fill the remaining ~3.5 MW. Status should read operational under the new operator (LM Funding America, Inc. / Power & Compute), not cancelled. Re-attempted geocoding of 249 Datco Industrial Road this run: both US Census and OSM Nominatim again failed to resolve the street (re-confirming a prior agent's result) -- no independent coordinate correction is possible, so the existing city-centroid pin is left unchanged. Source: LM Funding America, Inc. (Power & Compute)

Opposition and litigation at this site

Nothing on record as of September 14, 2026. No lawsuit, organized opposition, or contested hearing over Columbus Bitcoin Mining Facility (formerly Greenidge Columbus) in Columbus, Lowndes County, Mississippi appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Notes on the record

12-acre parcel at 249 Datco Industrial Road, Columbus (Lowndes County), MS, bought April 2024 for $1.45M, announced Mar 11 2024 alongside the North Dakota lease. Built with Greenidge's modular 'Pod X' design; live July 1, 2024 (7 MW self-mining per SEC filings). Sold via APA (closed Sept 16, 2025) for $4.2M to US Digital Mining Mississippi LLC, a subsidiary of LM Funding America (Nasdaq: LMFA). Greenidge fully divested on 2025-09-16; the site did NOT go dark. LM Funding America, Inc. (since rebranded Power & Compute) closed its acquisition of the 11 MW site plus ~7.5 MW / 157 PH/s of operating hashrate on 2025-09-18 for $4.0M, and the facility is operational under that operator. Record renamed and operator updated 2026-09-13 to match; the id is retained for stability. (Greenidge separately still owns an UNRELATED 34-acre Columbus greenfield site for a future AI/HPC datacenter - not this record.)

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Questions people ask about this site

Is there opposition to the Columbus Bitcoin Mining Facility (formerly Greenidge Columbus) in Columbus?

Nothing on record as of September 14, 2026. No lawsuit, organized opposition, or contested hearing over Columbus Bitcoin Mining Facility (formerly Greenidge Columbus) in Columbus, Lowndes County, Mississippi appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Columbus Bitcoin Mining Facility (formerly Greenidge Columbus)?

No lawsuit over Columbus Bitcoin Mining Facility (formerly Greenidge Columbus) appears in the record we track as of September 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Columbus Bitcoin Mining Facility (formerly Greenidge Columbus) use?

No water withdrawal figure for Columbus Bitcoin Mining Facility (formerly Greenidge Columbus) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Columbus Bitcoin Mining Facility (formerly Greenidge Columbus), and how big is it?

LM Funding America, Inc. (Power & Compute) is the operator on record. Capacity on record is 8.5 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Columbus Bitcoin Mining Facility (formerly Greenidge Columbus)," updated September 14, 2026, https://suedatacenters.org/data-centers/greenidge-columbus-ms.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/greenidge-columbus-ms, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Greenidge Announces Expansion of Power Capacity with 40 MW of Low-Cost Power in Key Territories · Greenidge Generation Holdings Inc. (SEC 8-K exhibit) · retrieved August 5, 2026
  2. 2.Greenidge Generation Holdings Inc. Form 10-Q, Q3 FY2025 · SEC EDGAR · retrieved August 5, 2026
  3. 3.Greenidge Generation Closes Sale of its Mississippi Bitcoin Mining Facility · Business Wire · retrieved August 5, 2026
  4. 4.Greenidge Generation Holdings Inc. Form 10-K for fiscal year ended September 30, 2025, "Mississippi Facility" · U.S. Securities and Exchange Commission (EDGAR) · retrieved September 9, 2026
  5. 5.Greenidge Generation Holdings Inc. Form 8-K, August 1, 2025, Asset Purchase Agreement with US Digital Mining Mississippi LLC · U.S. Securities and Exchange Commission (EDGAR) · retrieved September 9, 2026
  6. 6.LM Funding America Closes Acquisition of 11 MW Site and Miners in Columbus Mississippi for $4.0 Million · LM Funding America, Inc. (Power & Compute) · retrieved September 13, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us