Data Center Registry
CloudHQ MSP Campus (Chaska)
Chaska, Carver County, Minnesota · All 6 CloudHQ sites
CloudHQ MSP Campus (Chaska) is a permitted data center in Chaska, Minnesota (Carver County), operated by CloudHQ. The public record puts it at 200 MW planned.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- CloudHQ
- Facility type
- Data center
- Location
- 2007 Schoolmaster Dr, Chaska, Carver County, MN, 55318
- Coordinates
- 44.8107, -93.6356 (approximate)
- Power capacity
- 200 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- October 21, 2024PermittedCity Council approved the preliminary site plan/plat on 2024-10-21; the conditional use permit was approved 2023-10-16. Final site plan/plat approval is still outstanding. Source: City of Chaska, Minnesota
Opposition and litigation at this site
Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over CloudHQ MSP Campus (Chaska) in Chaska, Carver County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
The City of Chaska states "The anticipated water use for Cloud HQ is 14 million gallons per year", recorded as published (annual), not converted to a daily figure.
People and entities in the record
Jon Grau · public_official via Chaska City Council
Member of the Chaska City Council; voted for Resolution 2024-80, the preliminary site and building plan, preliminary plat and conditional use permit for CloudHQ. Outcome: approved 4-1 with all five members present (2024-10-21).
SourceMark Windschitl · public_official via Chaska City Council
Mayor of Chaska; voted for Resolution 2024-80, the preliminary site and building plan, preliminary plat and conditional use permit for CloudHQ. Outcome: approved 4-1 with all five members present (2024-10-21).
SourceMcKayla Hatfield · public_official via Chaska City Council
Member of the Chaska City Council; voted for Resolution 2024-80, the preliminary site and building plan, preliminary plat and conditional use permit for CloudHQ. Outcome: approved 4-1 with all five members present (2024-10-21).
SourceMike Huang · public_official via Chaska City Council
Member of the Chaska City Council; voted for Resolution 2024-80, the preliminary site and building plan, preliminary plat and conditional use permit for CloudHQ. Outcome: approved 4-1 with all five members present (2024-10-21).
SourceTaylor Hubbard · public_official via Chaska City Council
Member of the Chaska City Council; voted against Resolution 2024-80, the preliminary site and building plan, preliminary plat and conditional use permit for CloudHQ. Outcome: approved 4-1 with all five members present (2024-10-21).
Source
Notes on the record
CloudHQ markets the campus as "200 MWs Total Critical IT Load" across "one or two data centers" totalling "1,100,000 SF"; the City of Chaska describes a "Data center totaling approximately 1.5 million square feet in the West Creek Corporate Center" at 2007 Schoolmaster Dr. Chaska states "Cloud HQ has not applied for, and the City of Chaska has not offered, any form of tax relief or other subsidies." Coordinates are CloudHQ's own published campus point (44.81068, -93.63557), which sits ~200 m from the OSM point for the city-stated street address. Distinct from the two Chaska sites already tracked (Flexential MSP01 at 3500 Lyman Blvd and LightEdge at 1708 W Creek Ln).
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- LightEdge Chaska (fka Stream Data Centers Minneapolis I) · Chaska · LightEdge (GI Partners)1 mi · Operating · 3.6 MW
- UHG Chaska Data Center · Chaska · UnitedHealth Group2 mi · Operating
- Flexential Minneapolis - Chaska (MSP01) · Chaska · Flexential3 mi · Operating · 9 MW
- Shakopee Hyperscale Data Center Campus (NorthStar Digital Infrastructure) · Shakopee · NorthStar Digital Infrastructure LLC5 mi · Proposed · 80 MW
- Centersquare Shakopee (MSP1 Campus) · Shakopee · Centersquare (fka Cyxtera / Evoque; site originally built by Compass Datacenters)8 mi · Operating
- US Signal MN01 Minneapolis (Eden Prairie) · Eden Prairie · US Signal (site registered by OneNeck IT Solutions LLC)12 mi · Operating · 5.4 MW
- EdgeConneX Minneapolis (EDCMSP01) · Eden Prairie · EdgeConneX Inc.12 mi · Operating · 2.85 MW
- DataBank West Twin Cities Data Center (MSP1) · Edina · DataBank15 mi · Operating · 1.35 MW
Questions people ask about this site
Is there opposition to the CloudHQ MSP Campus (Chaska) in Chaska?
Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over CloudHQ MSP Campus (Chaska) in Chaska, Carver County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the CloudHQ MSP Campus (Chaska)?
No lawsuit over CloudHQ MSP Campus (Chaska) appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does CloudHQ MSP Campus (Chaska) use?
No water withdrawal figure for CloudHQ MSP Campus (Chaska) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates CloudHQ MSP Campus (Chaska), and how big is it?
CloudHQ is the operator on record. We hold 6 sites for that company across the registry. Capacity on record is 200 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "CloudHQ MSP Campus (Chaska)," updated November 4, 2026, https://suedatacenters.org/data-centers/cloudhq-msp-campus-chaska-mn.
Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cloudhq-msp-campus-chaska-mn, retrieved November 5, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.CloudHQ, MSP Campus specifications (200 MW critical IT load, 1,100,000 SF) · CloudHQ · retrieved September 18, 2026
- 2.City of Chaska, Cloud HQ project page (approval dates, water use, no subsidies) · City of Chaska, Minnesota · retrieved September 18, 2026
- 3.OpenStreetMap/Nominatim geocode, 2007 Schoolmaster Drive, Chaska, Carver County, MN 55318 · OpenStreetMap contributors · retrieved September 18, 2026
- 4.Chaska City Council minutes, October 21, 2024 · City of Chaska, Minnesota · retrieved November 4, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us