Paradox Data Union County Campus

El Dorado, Union County, Arkansas

ProposedNo reception on recordRecord updated October 18, 2026

Paradox Data Union County Campus is a proposed data center in El Dorado, Arkansas (Union County), operated by Paradox Data LLC (definitive agreement for acquisition by Z Squared Inc.). The public record puts it at announced June 25, 2026, 150 MW planned.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Paradox Data LLC (definitive agreement for acquisition by Z Squared Inc.)
Facility type
Data center
Location
713 Industrial Road, El Dorado, Union County, AR, 71730
Coordinates
33.2070, -92.6137 (approximate)
Power capacity
150 MW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
June 25, 2026
Utility
Entergy Arkansas
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. August 3, 2026
    Proposed
    Z Squared signed a definitive agreement to acquire 100% of Paradox Data. Milestones run from initial AI compute energization to 50/100/150 MW. Source: Finviz (company press release)

Opposition and litigation at this site

Nothing on record as of October 18, 2026. No lawsuit, organized opposition, or contested hearing over Paradox Data Union County Campus in El Dorado, Union County, Arkansas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Existing interruptible Entergy service arrangement for up to 8.0 MW. The development target is up to 150 MW from utility power plus on-site generation.

Notes on the record

About 8 MW is already energized. Entergy told the Democrat-Gazette Paradox is not a data center. Closing of the Z Squared deal was not confirmed. Coordinates were geocoded from the street address.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Tell us about your situation

Living near Paradox Data Union County Campus?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Paradox Data Union County Campus in El Dorado?

Nothing on record as of October 18, 2026. No lawsuit, organized opposition, or contested hearing over Paradox Data Union County Campus in El Dorado, Union County, Arkansas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Paradox Data Union County Campus?

No lawsuit over Paradox Data Union County Campus appears in the record we track as of October 18, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Paradox Data Union County Campus use?

No water withdrawal figure for Paradox Data Union County Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Paradox Data Union County Campus, and how big is it?

Paradox Data LLC (definitive agreement for acquisition by Z Squared Inc.) is the operator on record. Capacity on record is 150 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Paradox Data Union County Campus," updated October 18, 2026, https://suedatacenters.org/data-centers/paradox-data-union-county-campus-el-dorado-ar.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/paradox-data-union-county-campus-el-dorado-ar, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Florida-based firm details plans for El Dorado data center · Arkansas Democrat-Gazette · retrieved October 18, 2026
  2. 2.Z Squared Inc. Signs Definitive Agreement to Acquire 100% of Paradox Data and Its Union County Campus · Finviz (company press release) · retrieved October 18, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us