Digital Realty Kokomo Data Center Campus (Industrial Park North)

Kokomo, Howard County, Indiana · All 70 Digital Realty sites

ProposedNo reception on recordRecord updated October 16, 2026

Digital Realty Kokomo Data Center Campus (Industrial Park North) is a proposed data center in Kokomo, Indiana (Howard County), operated by Digital Realty. The public record puts it at announced October 2, 2026, 1.5 GW planned, 476 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Digital Realty
Facility type
Data center
Location
Kokomo, Howard County, IN
Coordinates
40.5400, -86.1300 (approximate)
Power capacity
1.5 GW planned
Land
476 acres
Investment
Not established from a public source
Announced
October 2, 2026
Utility
Duke Energy
Power source
Grid
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. October 2, 2026
    Proposed
    City of Kokomo announced Digital Realty's proposal for a three-building, ~3 million sq ft campus on ~476 acres; no rezoning needed; economic development agreement still requires Common Council approval. Source: WISH-TV

Opposition and litigation at this site

Nothing on record as of October 16, 2026. No lawsuit, organized opposition, or contested hearing over Digital Realty Kokomo Data Center Campus (Industrial Park North) in Kokomo, Howard County, Indiana appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Developer representative said the campus is expected to require about 1.5 GW of power at full build-out (WISH-TV, Oct 14, 2026). Duke Energy named as the electric provider.

Described as a closed-loop, air-cooled chiller system that recirculates water. Digital Realty to fund any needed water infrastructure upgrades; Indiana American Water says current capacity is sufficient.

Notes on the record

Three-building campus of about 3 million sq ft on ~476 acres at Industrial Park North, near U.S. 31 and County Road 400 North. Projected $1.3B-$1.7B taxable value; the city says no tax abatement. Completion projected 2033. The 1,500 MW figure is the developer's stated power requirement at full build-out. Coordinates are approximate.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Digital Realty Kokomo Data Center Campus (Industrial Park North)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Digital Realty Kokomo Data Center Campus (Industrial Park North) in Kokomo?

Nothing on record as of October 16, 2026. No lawsuit, organized opposition, or contested hearing over Digital Realty Kokomo Data Center Campus (Industrial Park North) in Kokomo, Howard County, Indiana appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Digital Realty Kokomo Data Center Campus (Industrial Park North)?

No lawsuit over Digital Realty Kokomo Data Center Campus (Industrial Park North) appears in the record we track as of October 16, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Digital Realty Kokomo Data Center Campus (Industrial Park North) use?

No water withdrawal figure for Digital Realty Kokomo Data Center Campus (Industrial Park North) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Digital Realty Kokomo Data Center Campus (Industrial Park North), and how big is it?

Digital Realty is the operator on record. We hold 70 sites for that company across the registry. Capacity on record is 1.5 GW. The site is recorded at 476 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Digital Realty Kokomo Data Center Campus (Industrial Park North)," updated October 16, 2026, https://suedatacenters.org/data-centers/digital-realty-kokomo-howard-county-in.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/digital-realty-kokomo-howard-county-in, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Digital Realty proposes $1.3 billion data center project in Kokomo · WISH-TV · retrieved October 16, 2026
  2. 2.Data center developer discusses multi-billion dollar project planned in Kokomo · WISH-TV · retrieved October 16, 2026
  3. 3.Kokomo Mayor Backs Proposed Data Center · InkFreeNews · retrieved October 16, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us