Data Journey Claremont Data Center (former Bed Bath & Beyond) is an operating data center in Claremont, North Carolina (Catawba County), operated by Data Journey. The public record puts it at 1 MW operating.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Data Journey
- Facility type
- Data center
- Location
- 2436 Penny Rd, Claremont, Catawba County, NC
- Coordinates
- 35.7146, -81.1462 (approximate)
- Power capacity
- 1 MW operating
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Duke Energy
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 29, 2024OperatingCatawba County EDC reports Data Journey bought the former Bed Bath & Beyond enterprise data center and converted it into a colocation facility. Source: Catawba County Economic Development Corporation
Opposition and litigation at this site
Nothing on record as of October 15, 2026. No lawsuit, organized opposition, or contested hearing over Data Journey Claremont Data Center (former Bed Bath & Beyond) in Claremont, Catawba County, North Carolina appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
The purchase price was $4M; the company puts its total outlay at nearly $7M including bankruptcy-related costs. That is an acquisition cost, not a build investment, so no investment figure is recorded. Baxtel lists 47,500 sq ft total, about 9,515 sq ft of raised floor, a 1.0 MW build-out expandable to about 3.5 MW, and a 2013 build year. Baxtel notes that a JLL sell sheet gives 3436 Penny Road instead of 2436. Coordinates are an approximate town-level placement.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Microsoft Conover Data Center · Conover · Microsoft4 mi · Under construction
- Microsoft Maiden Data Center · Maiden · Microsoft10 mi · Under construction
- Apple Maiden Data Center (iCloud) · Maiden · Apple11 mi · Operating
- Microsoft Hickory Data Center · Hickory · Microsoft11 mi · Under construction
- Compass Statesville Campus · Statesville · Compass Datacenters15 mi · Proposed · 500 MW · Contested
- DigiPower X Hildebran Data Center (Cline Park Court) · Hildebran · DigiPower X Inc. (formerly Digihost)15 mi · Proposed · 200 MW
- GIGA Data Centers Mooresville Campus · Mooresville · GIGA Data Centers21 mi · Operating · 60 MW
- Mooresville Campus · Mooresville · Tract21 mi · Cancelled
Questions people ask about this site
Is there opposition to the Data Journey Claremont Data Center (former Bed Bath & Beyond) in Claremont?
Nothing on record as of October 15, 2026. No lawsuit, organized opposition, or contested hearing over Data Journey Claremont Data Center (former Bed Bath & Beyond) in Claremont, Catawba County, North Carolina appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Data Journey Claremont Data Center (former Bed Bath & Beyond)?
No lawsuit over Data Journey Claremont Data Center (former Bed Bath & Beyond) appears in the record we track as of October 15, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Data Journey Claremont Data Center (former Bed Bath & Beyond) use?
No water withdrawal figure for Data Journey Claremont Data Center (former Bed Bath & Beyond) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Data Journey Claremont Data Center (former Bed Bath & Beyond), and how big is it?
Data Journey is the operator on record. Capacity on record is 1 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Data Journey Claremont Data Center (former Bed Bath & Beyond)," updated October 15, 2026, https://suedatacenters.org/data-centers/data-journey-claremont-catawba-county-nc.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/data-journey-claremont-catawba-county-nc, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.New life for Bed Bath & Beyond data center in Catawba County · Catawba County Economic Development Corporation · retrieved October 15, 2026
- 2.Data Journey: Claremont, NC · Baxtel · retrieved October 15, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us