Data Center Registry
EdgeConneX MIA02, Miami Gardens
Miami Gardens, Miami-Dade County, Florida · All 24 EdgeConneX sites · Every EdgeConneX case on our tracker
EdgeConneX MIA02, Miami Gardens is an operating data center in Miami Gardens, Florida (Miami-Dade County), operated by EdgeConneX. The public record puts it at 6 MW operating.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- EdgeConneX
- Facility type
- Data center
- Location
- 475 NE 185th Street, Miami Gardens, Miami-Dade County, FL, 33179
- Coordinates
- 25.9455, -80.1914 (approximate)
- Power capacity
- 6 MW operating
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- October 2, 2026OperatingEdgeConneX's Miami data sheet and PeeringDB both list this as an operating Edge Data Center. Source: PeeringDB
Opposition and litigation at this site
Nothing on record as of October 2, 2026. No lawsuit, organized opposition, or contested hearing over EdgeConneX MIA02, Miami Gardens in Miami Gardens, Miami-Dade County, Florida appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
The operator data sheet describes a 65,518 sq ft facility with 34,800 sq ft of raised floor and 6 MW N+1. The data sheet gives the city as Miami Gardens; PeeringDB lists it as Miami. ENERGY STAR certified per the operator page. Coordinates are PeeringDB's and approximate.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Cogent Hollywood, FL Data Center · Pembroke Park · Cogent Communications4 mi · Operating
- Iron Mountain MIA-1 · Westview · Iron Mountain5 mi · Under construction · 16 MW · Contested
- iM Critical Miami Data Center · Miami · iM Critical (iM Data Centers)7 mi · Operating · 5 MW
- CoreSite MI1, Miami · Miami · CoreSite11 mi · Operating
- Equinix MI1 (NAP of the Americas) · Miami · Equinix11 mi · Operating
- Digital Realty MIA10 · Miami · Digital Realty12 mi · Operating
- DataBank MIA1, Downtown Miami · Miami · DataBank12 mi · Operating · 1.6 MW
- EdgeConneX MIA03 (Beacon Station, withdrawn) · Medley · EdgeConneX13 mi · Cancelled
Questions people ask about this site
Is there opposition to the EdgeConneX MIA02, Miami Gardens data center in Miami Gardens?
Nothing on record as of October 2, 2026. No lawsuit, organized opposition, or contested hearing over EdgeConneX MIA02, Miami Gardens in Miami Gardens, Miami-Dade County, Florida appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the EdgeConneX MIA02, Miami Gardens data center?
No lawsuit over EdgeConneX MIA02, Miami Gardens appears in the record we track as of October 2, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does EdgeConneX MIA02, Miami Gardens use?
No water withdrawal figure for EdgeConneX MIA02, Miami Gardens is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates EdgeConneX MIA02, Miami Gardens, and how big is it?
EdgeConneX is the operator on record. We hold 24 sites for that company across the registry. Capacity on record is 6 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "EdgeConneX MIA02, Miami Gardens," updated October 2, 2026, https://suedatacenters.org/data-centers/edgeconnex-mia02-miami-gardens-fl.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/edgeconnex-mia02-miami-gardens-fl, retrieved October 11, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.EdgeConneX Miami (EDCMIA02) · PeeringDB · retrieved October 2, 2026
- 2.Miami, FL Data Center & Colocation (MIA01 & MIA02) · EdgeConneX · retrieved October 2, 2026
- 3.Miami MIA01 & MIA02 data sheet · EdgeConneX · retrieved October 2, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us